Progress feed:
1718 NE 16th
← Back to Home Details
  • New task added by Jonathan  |  Apr 23, 2019 - 7:29pm

    asdasdasdasd

  • New task added by Jeff  |  Apr 19, 2019 - 6:32am

    Upstairs Bathroom Correction - Failed Plumbing Inspection

  • Marked as complete by Jonathan  |  Apr 16, 2019 - 1:29pm

    Pre-Closing Walk-Through Punch Items Completed

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:30am

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:30am

    Outdoor Hand Railing Installed (or N/A

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:30am

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:30am

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:29am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:29am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:29am

    Post-Installation Sod Manual Watering Scheduled

  • Marked as complete by Jeff  |  Mar 20, 2019 - 6:29am

    Sod Installation

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:58am

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:58am

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:51am

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:51am

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:51am

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:50am

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Mar 5, 2019 - 5:34pm

    Carpet Installation

  • Marked as complete by Jeff  |  Mar 5, 2019 - 5:34pm

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Mar 5, 2019 - 5:34pm

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Mar 5, 2019 - 5:34pm

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Mar 5, 2019 - 5:34pm

    Appliance Package Delivery

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:33am

    Barn Door(s) Installation

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:33am

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:33am

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:33am

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:33am

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:33am

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:32am

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:32am

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:32am

    Sandy Loam Load Delivery

  • Marked as complete by Jeff  |  Feb 26, 2019 - 5:57am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Feb 26, 2019 - 5:57am

    Window Screen Installation

  • Marked as complete by Jeff  |  Feb 25, 2019 - 4:34pm

    Final Site Grade

  • Marked as complete by Jeff  |  Feb 25, 2019 - 4:34pm

    Curb & Form Haul

  • Marked as complete by Jeff  |  Feb 25, 2019 - 4:33pm

    Mailbox Constructed (If Feasible)

  • Phase Completed!  |  Feb 25, 2019 - 4:33pm

    Exterior Rough

  • Marked as complete by Jeff  |  Feb 25, 2019 - 4:33pm

    Electrical Final Meter & Service Installed

  • Marked as complete by Jeff  |  Feb 25, 2019 - 4:33pm

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Feb 15, 2019 - 11:27am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Feb 8, 2019 - 10:58am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Feb 6, 2019 - 9:28am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Feb 5, 2019 - 3:02pm

    Seamless Guttering Installation

  • Scheduled by Jeff  |  Feb 2, 2019 - 10:08am

    Seamless Guttering Installation

  • Scheduled by Jeff  |  Feb 2, 2019 - 9:59am

    Preliminary Detail Clean

  • Scheduled by Jeff  |  Feb 2, 2019 - 9:57am

    Attic Insulation Installation

  • Scheduled by Jeff  |  Feb 2, 2019 - 9:56am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:55am

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:54am

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:54am

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:54am

    Permanent Keys Delivery & Secure Storage

  • Scheduled by Jeff  |  Jan 30, 2019 - 11:51am

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Jan 30, 2019 - 11:47am

    Window Screen Installation

  • Marked as complete by Jeff  |  Jan 28, 2019 - 9:28am

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Flatwork Pour

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Driveway Approach & CIty-Walk Inspection

  • Scheduled by Jeff  |  Jan 22, 2019 - 4:22pm

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Jan 22, 2019 - 4:22pm

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Jan 22, 2019 - 4:21pm

    Pre-Flatwork Conduit Sleeving

  • Scheduled by Jeff  |  Jan 18, 2019 - 8:28am

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Hand Railing & Banister Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:22am

    Hardware Installation

  • Marked as complete by Jeff  |  Jan 16, 2019 - 8:28am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Jan 16, 2019 - 8:28am

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Jan 14, 2019 - 8:13am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  Jan 11, 2019 - 10:00am

    Flatwork Sand Ordered

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:40am

    Plumbing Final Installation

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:40am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:39am

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:39am

    Hardware Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Jan 1, 2019 - 10:13pm

    Flatwork Sand On Site

  • Scheduled by Jeff  |  Dec 28, 2018 - 3:49pm

    Flatwork Sand On Site

  • Scheduled by Jeff  |  Dec 28, 2018 - 3:47pm

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Dec 19, 2018 - 1:29pm

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Dec 19, 2018 - 1:29pm

    Interior Hand Railing Takeoff (Or N/A)

  • Phase Completed!  |  Dec 19, 2018 - 1:29pm

    Insulation To Trim

  • Scheduled by Jeff  |  Dec 17, 2018 - 8:27am

    Surplus Trim Pick-Up

  • Scheduled by Jeff  |  Dec 17, 2018 - 8:27am

    Interior Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:25am

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:25am

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:25am

    Outdoor Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:24am

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Dec 13, 2018 - 8:35am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Dec 13, 2018 - 8:34am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Dec 7, 2018 - 10:05am

    Tile & Hardwood Flooring Take-Off & Ordered

  • Marked as complete by Jeff  |  Dec 7, 2018 - 10:05am

    Barn Door Installation Scheduled

  • Marked as complete by Jeff  |  Dec 7, 2018 - 10:05am

    Builder Trim, Paint, & Detail Walk-Through

  • Scheduled by Jeff  |  Dec 5, 2018 - 8:30am

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Dec 5, 2018 - 8:30am

    Solid Surface Counter Top Templating

  • Scheduled by Jeff  |  Dec 5, 2018 - 8:29am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Dec 5, 2018 - 8:28am

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Dec 5, 2018 - 8:28am

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Nov 27, 2018 - 8:48am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Nov 27, 2018 - 8:48am

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Nov 27, 2018 - 8:48am

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Nov 26, 2018 - 11:44am

    Interior Trim & Doors On Site

  • Scheduled by Jeff  |  Nov 13, 2018 - 7:44pm

    Cabinet Delivery & Installation

  • Scheduled by Jeff  |  Nov 13, 2018 - 7:43pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:43pm

    Temporary Construction Heat Activated

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Oct 29, 2018 - 11:31am

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Oct 29, 2018 - 11:31am

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Oct 29, 2018 - 11:31am

    Preliminary Stained Concrete Flooring Scheduled

  • Scheduled by Jeff  |  Oct 22, 2018 - 8:14am

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Preliminary Flooring Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Garage Door Installation

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:13am

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:13am

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:13am

    Insulation Inspection Requested & Confirmed by Jeff

  • Marked as complete by Jeff  |  Oct 17, 2018 - 9:26am

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Oct 17, 2018 - 9:26am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Oct 17, 2018 - 9:26am

    Exterior Masonry Scheduled

  • Scheduled by Jeff  |  Oct 15, 2018 - 8:13am

    Preliminary Flooring Completion

  • Marked as complete by Jeff  |  Oct 15, 2018 - 8:13am

    Phase 2 Design Session Scheduled

  • Phase Completed!  |  Oct 15, 2018 - 8:13am

    Frame To Inspections

  • Marked as complete by Jeff  |  Oct 15, 2018 - 8:13am

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  Oct 13, 2018 - 6:30pm

    Drywall Phase Site Clean-Up

  • Scheduled by Jeff  |  Oct 12, 2018 - 3:54pm

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Oct 12, 2018 - 3:52pm

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Oct 12, 2018 - 3:52pm

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Wall Tile Details Notated On Walls

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Insulation Inspection Passed

  • Scheduled by Jeff  |  Oct 8, 2018 - 8:24am

    Concrete Flooring Work Complete

  • Scheduled by Jeff  |  Oct 8, 2018 - 8:23am

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Oct 5, 2018 - 11:20am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Oct 3, 2018 - 1:40pm

    Supplemental Masonry Material On Site

  • Scheduled by Jeff  |  Oct 3, 2018 - 1:40pm

    Drywall Material On Site

  • Marked as complete by Jeff  |  Oct 3, 2018 - 1:38pm

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Oct 3, 2018 - 1:37pm

    Insulation Inspection Requested

  • Marked as complete by Jeff  |  Oct 2, 2018 - 11:17am

    Wall Insulation & Seal Package Completion

  • Marked as complete by Jeff  |  Oct 2, 2018 - 11:17am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Oct 2, 2018 - 11:16am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2018 - 5:05pm

    Brick On Site

  • Marked as complete by Jeff  |  Sep 27, 2018 - 1:47pm

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Sep 27, 2018 - 1:42pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 26, 2018 - 11:43am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:16am

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:16am

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:51am

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:51am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:51am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:49am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:49am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:49am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Sep 18, 2018 - 4:09pm

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Sep 18, 2018 - 1:19pm

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Sep 17, 2018 - 11:56am

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Scheduled by Jeff  |  Sep 14, 2018 - 9:08am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:07am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:07am

    Supplemental Masonry Material Ordered

  • Scheduled by Jeff  |  Sep 14, 2018 - 9:07am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Sep 14, 2018 - 8:56am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Roof Installation

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:43am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:43am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:14am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:14am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:14am

    Exterior Wall Sheathing Inspection Passed

  • Scheduled by Jeff  |  Sep 6, 2018 - 8:23am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:18am

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    Framing - Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    Framing - Rafter & Decking Phase Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:59pm

    Wall Insulation & Seal Package Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:58pm

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:54pm

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:53pm

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:51pm

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:50pm

    Cabinet Take-Off & Design Review

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:48pm

    Roof Installation

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing - Joist Phase Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing - Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing Lumber - Decking & Cornice Order

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing Lumber - Joist & Rafter Order

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:07am

    Framing Lumber - Wall Pack Order

  • Scheduled by Jeff  |  Aug 22, 2018 - 8:58am

    Framing Lumber - Wall Pack Order

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Phase 1 Design Session Completed

  • Phase Completed!  |  Aug 16, 2018 - 11:55am

    Pad To Foundation

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Foundation Form Removal

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Foundation Poured

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:13am

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:12am

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:12am

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:11am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:11am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Windows & Exterior Doors Ordered

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Jul 31, 2018 - 9:12am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jul 31, 2018 - 9:11am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Pad Site Grading

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Site Identification Sign Installed

  • Scheduled by Jeff  |  Jul 16, 2018 - 10:40am

    Ground Plumbing Installed

  • Scheduled by Jeff  |  Jul 16, 2018 - 10:39am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Phase 1 Design Session Scheduled

  • Phase Completed!  |  Jul 11, 2018 - 8:59am

    Start To Permit

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Final Design Notes Created

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Purchase Agreement Pricing Completed

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Property Pins Located On Site

  • Posted by Jeff Click  |  Jul 11, 2018 - 8:45am
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Plans & Application Submitted for Permits

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Mar 24, 2018 - 8:34pm

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Mar 16, 2018 - 1:07pm

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Mar 16, 2018 - 1:07pm

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Mar 15, 2018 - 7:13pm

    Foundation Engineering Complete

  • Scheduled by Jeff  |  Mar 13, 2018 - 9:11am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Mar 13, 2018 - 9:06am

    Framing Engineering Ordered

  • Scheduled by Jeff  |  Mar 13, 2018 - 9:01am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Mar 13, 2018 - 9:00am

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Mar 13, 2018 - 8:58am

    Final Project Data Updated in CB

  • Marked as complete by Jeff  |  Mar 13, 2018 - 8:57am

    Final Plan Revisions JCH-Verified

  • Marked as complete by Jeff  |  Mar 13, 2018 - 8:57am

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Feb 13, 2018 - 2:43pm

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Feb 13, 2018 - 2:43pm

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jonathan  |  Invalid date - Invalid date

    Pre-Closing Walk-Through Punch Items Completed