Progress feed:
1718 NE 16th
← Back to Home Details
  • Marked as complete by Jeff  |  Feb 15, 2019 - 11:27am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Feb 8, 2019 - 10:58am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Feb 6, 2019 - 9:28am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Feb 5, 2019 - 3:02pm

    Seamless Guttering Installation

  • Scheduled by Jeff  |  Feb 2, 2019 - 10:08am

    Seamless Guttering Installation

  • Scheduled by Jeff  |  Feb 2, 2019 - 9:59am

    Preliminary Detail Clean

  • Scheduled by Jeff  |  Feb 2, 2019 - 9:57am

    Attic Insulation Installation

  • Scheduled by Jeff  |  Feb 2, 2019 - 9:56am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:55am

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:54am

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:54am

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Feb 2, 2019 - 9:54am

    Permanent Keys Delivery & Secure Storage

  • Scheduled by Jeff  |  Jan 30, 2019 - 11:51am

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Jan 30, 2019 - 11:47am

    Window Screen Installation

  • Marked as complete by Jeff  |  Jan 28, 2019 - 9:28am

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Flatwork Pour

  • Marked as complete by Jeff  |  Jan 28, 2019 - 8:15am

    Driveway Approach & CIty-Walk Inspection

  • Scheduled by Jeff  |  Jan 22, 2019 - 4:22pm

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Jan 22, 2019 - 4:22pm

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Jan 22, 2019 - 4:21pm

    Pre-Flatwork Conduit Sleeving

  • Scheduled by Jeff  |  Jan 18, 2019 - 8:28am

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Hand Railing & Banister Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:23am

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 8:22am

    Hardware Installation

  • Marked as complete by Jeff  |  Jan 16, 2019 - 8:28am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Jan 16, 2019 - 8:28am

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Jan 14, 2019 - 8:13am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  Jan 11, 2019 - 10:00am

    Flatwork Sand Ordered

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:40am

    Plumbing Final Installation

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:40am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:39am

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Jan 9, 2019 - 9:39am

    Hardware Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Jan 9, 2019 - 9:37am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Jan 1, 2019 - 10:13pm

    Flatwork Sand On Site

  • Scheduled by Jeff  |  Dec 28, 2018 - 3:49pm

    Flatwork Sand On Site

  • Scheduled by Jeff  |  Dec 28, 2018 - 3:47pm

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Dec 19, 2018 - 1:29pm

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Dec 19, 2018 - 1:29pm

    Interior Hand Railing Takeoff (Or N/A)

  • Phase Completed!  |  Dec 19, 2018 - 1:29pm

    Insulation To Trim

  • Scheduled by Jeff  |  Dec 17, 2018 - 8:27am

    Surplus Trim Pick-Up

  • Scheduled by Jeff  |  Dec 17, 2018 - 8:27am

    Interior Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:25am

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:25am

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:25am

    Outdoor Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Dec 17, 2018 - 8:24am

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Dec 13, 2018 - 8:35am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Dec 13, 2018 - 8:34am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Dec 7, 2018 - 10:05am

    Tile & Hardwood Flooring Take-Off & Ordered

  • Marked as complete by Jeff  |  Dec 7, 2018 - 10:05am

    Barn Door Installation Scheduled

  • Marked as complete by Jeff  |  Dec 7, 2018 - 10:05am

    Builder Trim, Paint, & Detail Walk-Through

  • Scheduled by Jeff  |  Dec 5, 2018 - 8:30am

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Dec 5, 2018 - 8:30am

    Solid Surface Counter Top Templating

  • Scheduled by Jeff  |  Dec 5, 2018 - 8:29am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Dec 5, 2018 - 8:28am

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Dec 5, 2018 - 8:28am

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Nov 27, 2018 - 8:48am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Nov 27, 2018 - 8:48am

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Nov 27, 2018 - 8:48am

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Nov 26, 2018 - 11:44am

    Interior Trim & Doors On Site

  • Scheduled by Jeff  |  Nov 13, 2018 - 7:44pm

    Cabinet Delivery & Installation

  • Scheduled by Jeff  |  Nov 13, 2018 - 7:43pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:43pm

    Temporary Construction Heat Activated

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Nov 13, 2018 - 7:42pm

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Oct 29, 2018 - 11:31am

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Oct 29, 2018 - 11:31am

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Oct 29, 2018 - 11:31am

    Preliminary Stained Concrete Flooring Scheduled

  • Scheduled by Jeff  |  Oct 22, 2018 - 8:14am

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Preliminary Flooring Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Garage Door Installation

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:14am

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:13am

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:13am

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Oct 22, 2018 - 8:13am

    Insulation Inspection Requested & Confirmed by Jeff

  • Marked as complete by Jeff  |  Oct 17, 2018 - 9:26am

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Oct 17, 2018 - 9:26am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Oct 17, 2018 - 9:26am

    Exterior Masonry Scheduled

  • Scheduled by Jeff  |  Oct 15, 2018 - 8:13am

    Preliminary Flooring Completion

  • Marked as complete by Jeff  |  Oct 15, 2018 - 8:13am

    Phase 2 Design Session Scheduled

  • Phase Completed!  |  Oct 15, 2018 - 8:13am

    Frame To Inspections

  • Marked as complete by Jeff  |  Oct 15, 2018 - 8:13am

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  Oct 13, 2018 - 6:30pm

    Drywall Phase Site Clean-Up

  • Scheduled by Jeff  |  Oct 12, 2018 - 3:54pm

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Oct 12, 2018 - 3:52pm

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Oct 12, 2018 - 3:52pm

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Wall Tile Details Notated On Walls

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 8:25am

    Insulation Inspection Passed

  • Scheduled by Jeff  |  Oct 8, 2018 - 8:24am

    Concrete Flooring Work Complete

  • Scheduled by Jeff  |  Oct 8, 2018 - 8:23am

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Oct 5, 2018 - 11:20am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Oct 3, 2018 - 1:40pm

    Supplemental Masonry Material On Site

  • Scheduled by Jeff  |  Oct 3, 2018 - 1:40pm

    Drywall Material On Site

  • Marked as complete by Jeff  |  Oct 3, 2018 - 1:38pm

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Oct 3, 2018 - 1:37pm

    Insulation Inspection Requested

  • Marked as complete by Jeff  |  Oct 2, 2018 - 11:17am

    Wall Insulation & Seal Package Completion

  • Marked as complete by Jeff  |  Oct 2, 2018 - 11:17am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Oct 2, 2018 - 11:16am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Oct 1, 2018 - 8:15am

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2018 - 5:05pm

    Brick On Site

  • Marked as complete by Jeff  |  Sep 27, 2018 - 1:47pm

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Sep 27, 2018 - 1:42pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 26, 2018 - 11:43am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:16am

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:16am

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:51am

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:51am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:51am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:49am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:49am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Sep 19, 2018 - 9:49am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Sep 18, 2018 - 4:09pm

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Sep 18, 2018 - 1:19pm

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Sep 17, 2018 - 11:56am

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Scheduled by Jeff  |  Sep 14, 2018 - 9:08am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:07am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:07am

    Supplemental Masonry Material Ordered

  • Scheduled by Jeff  |  Sep 14, 2018 - 9:07am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Sep 14, 2018 - 8:56am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:51am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Roof Installation

  • Marked as complete by Jeff  |  Sep 14, 2018 - 8:50am

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:43am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:43am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:14am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:14am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Sep 10, 2018 - 8:14am

    Exterior Wall Sheathing Inspection Passed

  • Scheduled by Jeff  |  Sep 6, 2018 - 8:23am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:18am

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    Framing - Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Sep 6, 2018 - 8:13am

    Framing - Rafter & Decking Phase Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:59pm

    Wall Insulation & Seal Package Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:58pm

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:54pm

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:53pm

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:51pm

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:50pm

    Cabinet Take-Off & Design Review

  • Scheduled by Jeff  |  Aug 30, 2018 - 5:48pm

    Roof Installation

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:48pm

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing - Joist Phase Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing - Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing Lumber - Decking & Cornice Order

  • Marked as complete by Jeff  |  Aug 30, 2018 - 5:47pm

    Framing Lumber - Joist & Rafter Order

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:07am

    Framing Lumber - Wall Pack Order

  • Scheduled by Jeff  |  Aug 22, 2018 - 8:58am

    Framing Lumber - Wall Pack Order

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Phase 1 Design Session Completed

  • Phase Completed!  |  Aug 16, 2018 - 11:55am

    Pad To Foundation

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Foundation Form Removal

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Foundation Poured

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Aug 10, 2018 - 1:36pm

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:13am

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:12am

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:12am

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:11am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Aug 7, 2018 - 11:11am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Windows & Exterior Doors Ordered

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Aug 2, 2018 - 9:49am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Jul 31, 2018 - 9:12am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jul 31, 2018 - 9:11am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Pad Site Grading

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Jul 23, 2018 - 2:02pm

    Site Identification Sign Installed

  • Scheduled by Jeff  |  Jul 16, 2018 - 10:40am

    Ground Plumbing Installed

  • Scheduled by Jeff  |  Jul 16, 2018 - 10:39am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Phase 1 Design Session Scheduled

  • Phase Completed!  |  Jul 11, 2018 - 8:59am

    Start To Permit

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Final Design Notes Created

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:58am

    Purchase Agreement Pricing Completed

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Property Pins Located On Site

  • Jeff Click (El JefĂ© Clicko)  |  Jul 11, 2018 - 8:45am
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.<br /> <br /> Stand by for some fun visual progress on site in the coming days!<br /> <br /> -JC
  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Plans & Application Submitted for Permits

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:45am

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Mar 24, 2018 - 8:34pm

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Mar 16, 2018 - 1:07pm

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Mar 16, 2018 - 1:07pm

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Mar 15, 2018 - 7:13pm

    Foundation Engineering Complete

  • Scheduled by Jeff  |  Mar 13, 2018 - 9:11am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Mar 13, 2018 - 9:06am

    Framing Engineering Ordered

  • Scheduled by Jeff  |  Mar 13, 2018 - 9:01am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Mar 13, 2018 - 9:00am

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Mar 13, 2018 - 8:58am

    Final Project Data Updated in CB

  • Marked as complete by Jeff  |  Mar 13, 2018 - 8:57am

    Final Plan Revisions JCH-Verified

  • Marked as complete by Jeff  |  Mar 13, 2018 - 8:57am

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Mar 8, 2018 - 12:43pm

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Feb 13, 2018 - 2:43pm

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Feb 13, 2018 - 2:43pm

    Plan Redline Submitted To Draftsman