Progress feed:
2108 Heavenly Drive
← Back to Home Details
  • Marked as complete by Jeff  |  Dec 13, 2019 - 3:47pm

    Remaining Pre-Closing Walkthrough Items Assigned In Warranty Phase

  • Phase Completed!  |  Dec 13, 2019 - 3:47pm

    Punch To Closed

  • Marked as complete by Jeff  |  Dec 13, 2019 - 3:47pm

    Closing-Day Final Paint Touch-Up

  • Marked as complete by Jeff  |  Dec 13, 2019 - 3:47pm

    Closing Day Pre-Closing Orientation With Client

  • Marked as complete by Jeff  |  Dec 11, 2019 - 2:56pm

    Final-Final Clean

  • Marked as complete by Jeff  |  Dec 11, 2019 - 2:56pm

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Paint Punch List

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Trim & Hardware Punch List

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Plumbing Punch List

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Electrical Punch List

  • Marked as complete by Jeff  |  Dec 10, 2019 - 10:23am

    Flooring Punch List

  • Marked as complete by Jeff  |  Dec 9, 2019 - 1:46pm

    Window & Exterior Door Punch List

  • Scheduled by Jeff  |  Dec 6, 2019 - 8:49am

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Dec 6, 2019 - 8:36am

    Pre-closing Walk & Client Orientation

  • Phase Completed!  |  Dec 6, 2019 - 8:36am

    Paint To Finalled

  • Marked as complete by Jeff  |  Dec 6, 2019 - 8:36am

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  Dec 6, 2019 - 8:36am

    Permanent Keys Delivery & Secure Storage

  • Marked as complete by Jeff  |  Dec 6, 2019 - 8:36am

    Fence Panel Installation (or N/A)

  • Phase Completed!  |  Dec 6, 2019 - 8:36am

    Exterior Detail

  • Marked as complete by Jeff  |  Dec 4, 2019 - 10:57am

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  Dec 4, 2019 - 10:57am

    Storm Shelter Cleaned & Secured

  • Marked as complete by Jeff  |  Dec 4, 2019 - 10:57am

    Certificate of Occupancy Issued

  • Marked as complete by Jeff  |  Dec 4, 2019 - 10:56am

    Carpet Installation

  • Marked as complete by Jeff  |  Dec 4, 2019 - 10:56am

    Carpet Installation

  • Marked as complete by Jeff  |  Dec 4, 2019 - 10:56am

    Fence Post Installation (or N/A)

  • Marked as complete by Jeff  |  Dec 4, 2019 - 10:56am

    Exterior Stone Masonry Completion

  • Phase Completed!  |  Dec 4, 2019 - 10:56am

    Exterior Rough

  • Marked as complete by Jeff  |  Dec 4, 2019 - 9:39am

    Storm Shelter Installation

  • Marked as complete by Jeff  |  Dec 3, 2019 - 12:34pm

    Zoning Final Inspection

  • Marked as complete by Jeff  |  Dec 3, 2019 - 12:34pm

    Building Final Inspection

  • Marked as complete by Jeff  |  Dec 3, 2019 - 12:34pm

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Dec 3, 2019 - 12:34pm

    Glass & Mirror Punch List

  • Scheduled by Jeff  |  Dec 2, 2019 - 12:55pm

    Final-Final Clean

  • Marked as complete by Jeff  |  Dec 2, 2019 - 12:53pm

    Hardware Installation

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:55am

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:55am

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:55am

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:55am

    Drywall Punch List

  • Scheduled by Jeff  |  Dec 2, 2019 - 10:54am

    Glass & Mirror Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Concrete Flooring Final

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Tech & Media Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    HVAC Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Cosmetic Surface Repair Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Solid Surface Counter Top Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Masonry Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Outdoor Hand Railing Installed (or N/A

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Address Panel Installed

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Marked as complete by Jeff  |  Dec 2, 2019 - 10:52am

    Exterior Facade Expansion Joint Sealing

  • Scheduled by Jeff  |  Nov 26, 2019 - 2:54pm

    Concrete Flooring Final

  • Marked as complete by Jeff  |  Nov 12, 2019 - 1:40pm

    Drywall Punch List

  • Scheduled by Jeff  |  Nov 11, 2019 - 1:46pm

    Fence Panel Installation (or N/A)

  • Scheduled by Jeff  |  Nov 11, 2019 - 1:45pm

    Fence Post Installation (or N/A)

  • Marked as complete by Jeff  |  Nov 11, 2019 - 1:44pm

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Nov 11, 2019 - 1:44pm

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  Nov 11, 2019 - 1:44pm

    Post-Installation Sod Manual Watering Scheduled

  • Marked as complete by Jeff  |  Nov 11, 2019 - 1:44pm

    Sod Installation

  • Scheduled by Jeff  |  Nov 11, 2019 - 12:54pm

    Drywall Punch List

  • Marked as complete by Jeff  |  Nov 11, 2019 - 8:55am

    Preliminary Detail Clean

  • Posted by Jeff Click  |  Nov 8, 2019 - 9:41am
    Black Friday Sale
    Black Friday For Your House & Family Vacation
    I wanted to bring this opportunity to your attention, as my appliance supplier (Known both as Hahn Appliances *and* Metro Appliances & More...same company) is having a 10% clearance on 11/14. This could be a good opportunity to grab a nice refrigerator, washer & dryer, or anything else you have on your wish list for the new pad.

    If you don't take advantage of this sale, remember I can always get you my wholesale pricing on those items at any other time, which would include delivery and installation. Feel free to hit me up with any model numbers of items you'd like quotes on.

    Also, I wanted to let you know in advance that I will be out for the week of the 18th-22nd for an overdue family getaway. I always leave with appropriate project progress scheduled to take place where possible, and I do have assistance in getting eyes on the jobs on site. I can also check-in via my remote site cameras to monitor progress. Note that I do build in cushion into construction schedules to allow a margin for things like this, weather, and holidays. Nonetheless, I wanted to make you aware of it in case you reached out to me and didn't hear back in my usual response window.

    Have a great weekend!

    | jC
  • Marked as complete by Jeff  |  Nov 8, 2019 - 9:22am

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Nov 8, 2019 - 9:22am

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Nov 6, 2019 - 9:23am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:33pm

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:33pm

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:32pm

    Irrigation System Programming & Activation (or N/A)

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:32pm

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:32pm

    Irrigation System Installation (or N/A)

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:32pm

    Termite Certificate & Guarantee Received & Filed

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:11pm

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 2:35pm

    Exterior Wood Column Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 2:35pm

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Nov 4, 2019 - 2:34pm

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Nov 4, 2019 - 10:45am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Nov 4, 2019 - 10:44am

    Window Screen Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 10:44am

    Plumbing Final Installation

  • Scheduled by Jeff  |  Oct 30, 2019 - 2:50pm

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Oct 30, 2019 - 2:34pm

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Oct 30, 2019 - 2:34pm

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Oct 30, 2019 - 2:34pm

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Oct 30, 2019 - 12:04pm

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Oct 30, 2019 - 12:04pm

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Oct 30, 2019 - 12:04pm

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Oct 30, 2019 - 12:02pm

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Oct 29, 2019 - 3:28pm

    Fireplace Final Installation

  • Marked as complete by Jeff  |  Oct 29, 2019 - 3:27pm

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Oct 29, 2019 - 3:27pm

    Appliance Package Delivery

  • Marked as complete by Jeff  |  Oct 29, 2019 - 3:27pm

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Oct 29, 2019 - 3:27pm

    Sewer Clean-Out Cut-Down & Capping

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:49pm

    Preliminary Detail Clean

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:48pm

    Window Screen Installation

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:48pm

    Pre-Paint Drywall Punch LIst

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:47pm

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:47pm

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:47pm

    Exterior Door Painting

  • Marked as complete by Jeff  |  Oct 25, 2019 - 11:44am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Oct 25, 2019 - 11:44am

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Oct 21, 2019 - 2:08pm

    Attic Insulation Installation

  • Scheduled by Jeff  |  Oct 21, 2019 - 2:07pm

    Kitchen Vent Hood Installation

  • Scheduled by Jeff  |  Oct 21, 2019 - 2:06pm

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Oct 21, 2019 - 2:04pm

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Oct 21, 2019 - 2:02pm

    Lighting Fixture Package Delivery

  • Scheduled by Jeff  |  Oct 21, 2019 - 2:02pm

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Oct 21, 2019 - 2:02pm

    Appliance Package Delivery

  • Scheduled by Jeff  |  Oct 21, 2019 - 11:22am

    Fireplace Final Installation

  • Scheduled by Jeff  |  Oct 21, 2019 - 11:17am

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Oct 21, 2019 - 11:15am

    Hand Railing & Banister Installation

  • Marked as complete by Jeff  |  Oct 21, 2019 - 11:14am

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Oct 21, 2019 - 11:14am

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Oct 21, 2019 - 11:14am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Oct 21, 2019 - 11:14am

    Mailbox Constructed (If Feasible)

  • Marked as complete by Jeff  |  Oct 21, 2019 - 11:14am

    Stone On Site (Or N/A)

  • Marked as complete by Jeff  |  Oct 21, 2019 - 11:13am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  Oct 18, 2019 - 11:03am

    Final Site Grade

  • Marked as complete by Jeff  |  Oct 18, 2019 - 11:03am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Oct 14, 2019 - 9:54am

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Oct 14, 2019 - 9:54am

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:38am

    Surplus Trim Pick-Up

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:38am

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:37am

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:37am

    Cabs Pre-Drilled for Hardware

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:36am

    Interior Stain & Painting

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:29am

    Plumbing Final Installation

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:27am

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:26am

    Hand Railing & Banister Installation

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:26am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:23am

    Final Site Grade

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:23am

    Final Site Grade

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:18am

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:18am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:18am

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Curb & Form Haul

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Flatwork Pour

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Pre-Flatwork Conduit Sleeving

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Interior Hand Railing Takeoff (Or N/A)

  • Phase Completed!  |  Oct 7, 2019 - 9:17am

    Insulation To Trim

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Outdoor Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Oct 7, 2019 - 9:17am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Scheduled by Jeff  |  Oct 7, 2019 - 9:16am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Sep 30, 2019 - 10:40am

    Drywall Punch List

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Sep 24, 2019 - 4:04pm

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Sep 20, 2019 - 3:37pm

    Garage Door Installation

  • Marked as complete by Jeff  |  Sep 20, 2019 - 3:37pm

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Sep 20, 2019 - 3:37pm

    Preliminary Tile Flooring Completion

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:35am

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Sep 9, 2019 - 4:26pm

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Sep 9, 2019 - 4:26pm

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Sep 9, 2019 - 4:26pm

    Exterior Brick Masonry Completion

  • Scheduled by Jeff  |  Sep 7, 2019 - 10:05am

    Preliminary Tile Flooring Completion

  • Scheduled by Jeff  |  Sep 5, 2019 - 4:48pm

    Flatwork Sand On Site

  • Scheduled by Jeff  |  Sep 5, 2019 - 4:46pm

    Exterior Brick Masonry Completion

  • Scheduled by Jeff  |  Sep 5, 2019 - 4:46pm

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Sep 5, 2019 - 4:46pm

    Flatwork Sand Ordered

  • Marked as complete by Jeff  |  Sep 5, 2019 - 4:46pm

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Sep 5, 2019 - 4:46pm

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Sep 5, 2019 - 4:46pm

    Water Meter Installed & Back-filled

  • Phase Completed!  |  Sep 5, 2019 - 4:46pm

    Frame To Inspections

  • Scheduled by Jeff  |  Sep 5, 2019 - 12:43pm

    Drywall Punch List

  • Marked as complete by Jeff  |  Sep 3, 2019 - 7:01am

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Sep 3, 2019 - 7:01am

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Sep 3, 2019 - 7:01am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Sep 3, 2019 - 7:01am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Sep 3, 2019 - 7:00am

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Sep 3, 2019 - 7:00am

    Preliminary Floor &/or Wall Tile Scheduled

  • Scheduled by Jeff  |  Aug 30, 2019 - 8:06am

    Garage Door Installation

  • Marked as complete by Jeff  |  Aug 30, 2019 - 8:02am

    Electrical Final Meter & Service Installed

  • Marked as complete by Jeff  |  Aug 30, 2019 - 8:02am

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2019 - 8:02am

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:56am

    Drywall Phase Site Clean-Up

  • Scheduled by Jeff  |  Aug 28, 2019 - 1:02pm

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Aug 28, 2019 - 9:52am

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Aug 28, 2019 - 9:31am

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Aug 28, 2019 - 9:30am

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Aug 28, 2019 - 9:30am

    Trim & Interior Door Material Take-Off & Ordered

  • Scheduled by Jeff  |  Aug 26, 2019 - 3:56pm

    2nd Phase Concrete Flooring Scheduled

  • Scheduled by Jeff  |  Aug 26, 2019 - 3:47pm

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Aug 26, 2019 - 3:43pm

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Aug 26, 2019 - 3:42pm

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Aug 26, 2019 - 3:42pm

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Aug 26, 2019 - 3:42pm

    2nd Phase Concrete Flooring Scheduled

  • Marked as complete by Jeff  |  Aug 26, 2019 - 3:42pm

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Aug 26, 2019 - 3:41pm

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Aug 23, 2019 - 7:21am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Aug 21, 2019 - 12:55pm

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Aug 21, 2019 - 6:48am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Aug 21, 2019 - 6:48am

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  Aug 20, 2019 - 8:19am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Aug 20, 2019 - 8:19am

    Insulation Inspection Requested & Confirmed by Jeff

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:53pm

    Wall Insulation Installation

  • Marked as complete by Jeff  |  Aug 15, 2019 - 7:04pm

    Brick On Site

  • Marked as complete by Jeff  |  Aug 15, 2019 - 7:04pm

    Exterior Masonry Scheduled

  • Marked as complete by Jeff  |  Aug 15, 2019 - 7:03pm

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Aug 15, 2019 - 7:03pm

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Aug 15, 2019 - 7:03pm

    Building Rough-In Inspection Passed

  • Scheduled by Jeff  |  Aug 14, 2019 - 8:59am

    Wall Insulation Installation

  • Scheduled by Jeff  |  Aug 14, 2019 - 8:35am

    Supplemental Masonry Material On Site

  • Scheduled by Jeff  |  Aug 14, 2019 - 8:34am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Aug 14, 2019 - 8:31am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Aug 14, 2019 - 8:31am

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  Aug 14, 2019 - 8:30am

    Exterior Facade Materials Ordered

  • Scheduled by Jeff  |  Aug 14, 2019 - 8:26am

    Brick On Site

  • Marked as complete by Jeff  |  Aug 9, 2019 - 3:59pm

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Aug 9, 2019 - 3:59pm

    Natural Gas System Analysis Requested

  • Marked as complete by Jeff  |  Aug 9, 2019 - 2:54pm

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Aug 9, 2019 - 2:54pm

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Aug 9, 2019 - 2:53pm

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Aug 9, 2019 - 2:53pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Aug 9, 2019 - 2:53pm

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Aug 8, 2019 - 6:42am

    Insulation & Sealant Installation Completion

  • Marked as complete by Jeff  |  Aug 8, 2019 - 6:42am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Aug 5, 2019 - 9:05am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Aug 5, 2019 - 9:04am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Aug 5, 2019 - 9:04am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:30am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Scheduled by Jeff  |  Aug 2, 2019 - 10:11am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:11am

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:11am

    Drywall Contractor Scheduled

  • Scheduled by Jeff  |  Aug 2, 2019 - 10:09am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:08am

    Sheetrock & Materials Order Scheduled For Delivery

  • Scheduled by Jeff  |  Aug 2, 2019 - 10:06am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:04am

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:04am

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:03am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Aug 2, 2019 - 10:02am

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Aug 1, 2019 - 8:51am

    Insulation & Sealant Installation Completion

  • Marked as complete by Jeff  |  Aug 1, 2019 - 8:50am

    Wall Insulation & Seal Package Scheduled

  • Posted by Jeff Click  |  Jul 30, 2019 - 1:12pm
    Pool Pre-Wire Quote
    Steve & Jamie, my electricians have begun their work at the house and as promised, I've asked them to quote me a price for work they can do now to provide savings later regarding the pool. To fully support the future pool, the electrical panel will need to be upgraded from a 200AMP to 400AMP breaker panel. That upgrade, along with running the service to our previously discussed pool equipment spot, would run $2500 if done now. If they do it later after construction, they estimate it would cost $4,000, not including any sheetrock or brick repairs needed for concealment of the wiring.

    Please let me know by commenting here or emailing me separately if you would like me to proceed with this and I will add it to the pricing.

    Thanks!
    | jC
  • Marked as complete by Jeff  |  Jul 30, 2019 - 6:34am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Jul 25, 2019 - 6:44pm

    Post-Tension Cables Stressed & Secured

  • Marked as complete by Jeff  |  Jul 25, 2019 - 6:43pm

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Jul 25, 2019 - 6:42pm

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Jul 25, 2019 - 6:42pm

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Jul 25, 2019 - 6:42pm

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Jul 23, 2019 - 6:44am

    Fireplace Installation

  • Marked as complete by Jeff  |  Jul 17, 2019 - 1:19pm

    Roof Installation

  • Marked as complete by Jeff  |  Jul 15, 2019 - 8:16am

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Jul 15, 2019 - 8:16am

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Jul 15, 2019 - 8:16am

    Framing | Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Jul 10, 2019 - 11:13am

    Framing | Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  Jul 10, 2019 - 11:13am

    Framing | Joist Phase Completion

  • Scheduled by Jeff  |  Jul 3, 2019 - 7:03am

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Jul 3, 2019 - 7:03am

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Jul 3, 2019 - 7:02am

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Jul 3, 2019 - 7:02am

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Jul 3, 2019 - 7:02am

    Fireplace Installation

  • Marked as complete by Jeff  |  Jul 3, 2019 - 7:01am

    Electrical Rough-In Scheduled

  • Scheduled by Jeff  |  Jul 3, 2019 - 7:01am

    Roof Installation

  • Marked as complete by Jeff  |  Jul 3, 2019 - 7:00am

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  Jul 3, 2019 - 7:00am

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 3, 2019 - 7:00am

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 3, 2019 - 7:00am

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 3, 2019 - 7:00am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 3, 2019 - 6:59am

    Framing | Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Jul 3, 2019 - 6:59am

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Jul 3, 2019 - 6:59am

    Framing Lumber | Decking & Cornice Order

  • Marked as complete by Jeff  |  Jul 3, 2019 - 6:59am

    Framing Lumber | Joist & Rafter Order

  • Marked as complete by Jeff  |  Jul 3, 2019 - 6:59am

    Foundation Form Removal

  • Phase Completed!  |  Jul 3, 2019 - 6:59am

    Pad To Foundation

  • Marked as complete by Jeff  |  Jun 21, 2019 - 6:26am

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Jun 21, 2019 - 6:26am

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Jun 21, 2019 - 6:26am

    Foundation Poured

  • Marked as complete by Jeff  |  Jun 13, 2019 - 12:36pm

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Jun 13, 2019 - 12:36pm

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Jun 13, 2019 - 12:36pm

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Jun 13, 2019 - 12:36pm

    Termite Pre-Treatment For Foundation

  • Marked as complete by Jeff  |  Jun 13, 2019 - 12:36pm

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Jun 13, 2019 - 12:36pm

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:40am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Jun 10, 2019 - 6:53am

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  May 31, 2019 - 9:54am

    Ground Electrical Installed

  • Marked as complete by Jeff  |  May 31, 2019 - 6:16am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  May 24, 2019 - 10:00pm

    Ground Plumbing Installed

  • Scheduled by Jeff  |  May 24, 2019 - 3:16pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  May 24, 2019 - 7:59am

    Framing Lumber | Wall Pack Order

  • Marked as complete by Jeff  |  May 14, 2019 - 6:06am

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  May 14, 2019 - 6:06am

    Load of Sand For Plumbers Ordered

  • Marked as complete by Jeff  |  May 9, 2019 - 6:45am

    Trash Bin Constructed

  • Marked as complete by Jeff  |  May 9, 2019 - 6:44am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  May 6, 2019 - 4:04pm

    Foundation Forms Constructed

  • Scheduled by Jeff  |  Apr 30, 2019 - 12:45pm

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Apr 30, 2019 - 12:32pm

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Apr 30, 2019 - 12:32pm

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Apr 30, 2019 - 12:32pm

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Apr 30, 2019 - 12:32pm

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Apr 27, 2019 - 7:42pm

    Pad Site Grading

  • Marked as complete by Jeff  |  Apr 26, 2019 - 2:58pm

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Apr 24, 2019 - 5:01pm

    Pricing Updated From Pre-Con

  • Phase Completed!  |  Apr 24, 2019 - 5:01pm

    Start To Permit

  • Marked as complete by Jeff  |  Apr 24, 2019 - 5:01pm

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Apr 24, 2019 - 5:01pm

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Apr 23, 2019 - 8:01am

    Final Design Notes Created

  • Scheduled by Jeff  |  Apr 22, 2019 - 3:28pm

    Foundation Forms Constructed

  • Scheduled by Jeff  |  Apr 22, 2019 - 3:27pm

    Trash Bin Constructed

  • Posted by Jeff Click  |  Apr 21, 2019 - 8:19pm
    Your Design Notes
    It's Time To Design!
    We're at the point when it's time to start thinking in greater detail about your new home! Design Session 1 is upon us, which involves exterior finish selections, electrical and tech layout, flooring diagram, and more preliminary design decisions. Don't sweat these decisions! I'm here to guide you through making fantastic choices.

    Design sessions need to be scheduled during business hours, as often we need to walk a few doors down to look at materials from suppliers, or make phone calls to check on availability that other decisions depend on. DS1 can often be fully completed over a lunch hour meeting if that helps fit into your schedule better (it usually takes 1-2 hours, max).

    What are some days and times in the next 2 weeks that you have available? I'm looking forward to our next time together!

    | jC
  • Marked as complete by Jeff  |  Apr 17, 2019 - 6:09am

    Framing Engineering & Material Take-Off Received

  • Scheduled by Jeff  |  Apr 11, 2019 - 8:21am

    Ground Plumbing Installed

  • Scheduled by Jeff  |  Apr 11, 2019 - 8:19am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Apr 11, 2019 - 8:18am

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Apr 11, 2019 - 8:18am

    Site Identification Sign Installed

  • Posted by Jeff Click  |  Apr 11, 2019 - 8:18am
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Apr 11, 2019 - 8:18am

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Apr 11, 2019 - 8:17am

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Apr 11, 2019 - 8:03am

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Apr 11, 2019 - 8:03am

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Apr 11, 2019 - 8:03am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:17am

    Window Take-Off & Bid Received

  • Scheduled by Jeff  |  Apr 3, 2019 - 1:39pm

    Window Take-Off & Bid Received

  • Scheduled by Jeff  |  Apr 3, 2019 - 1:36pm

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Apr 3, 2019 - 1:34pm

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Apr 3, 2019 - 1:34pm

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Apr 3, 2019 - 1:33pm

    Framing Engineering & Material Take-Off Requested

  • Marked as complete by Jeff  |  Apr 3, 2019 - 1:33pm

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Apr 3, 2019 - 1:33pm

    Final Project Data Updated in CB

  • Posted by Jeff Click  |  Apr 3, 2019 - 1:32pm
    Check, Check, Build!
    The Plans Are Now Official
    Good news! The revised set of plans have been returned by the CAD Draftsman. I have personally cross-checked the new set of plans with our notes from the Plan Review Meeting Check-List, and all of our discussed modifications have been made to satisfaction.

    This means that the plans are now considered "official", and final. These plans are now passed on for foundation engineering, lumber/structural engineering, and window ordering.

    Lots of site progress to follow!

    | jC
  • Marked as complete by Jeff  |  Apr 2, 2019 - 3:30pm

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Mar 25, 2019 - 1:15pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Mar 23, 2019 - 3:19pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Mar 23, 2019 - 3:19pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:53am

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Mar 14, 2019 - 3:53pm

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Mar 14, 2019 - 3:16pm

    Pre-con Meeting Packet Created

  • Scheduled by Jeff  |  Mar 9, 2019 - 10:29am

    Pad Site Grading

  • Scheduled by Jeff  |  Mar 9, 2019 - 10:29am

    Trash Bin Materials Ordered

  • Scheduled by Jeff  |  Mar 9, 2019 - 10:28am

    Site Drainage Analysis & Plan

  • Scheduled by Jeff  |  Mar 9, 2019 - 10:28am

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Mar 9, 2019 - 10:25am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Mar 9, 2019 - 10:25am

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Mar 7, 2019 - 9:46pm

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Mar 7, 2019 - 9:46pm

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Mar 7, 2019 - 6:03am

    Temp Electric Pole Installed

  • Scheduled by Jeff  |  Feb 19, 2019 - 6:58am

    Temp Electric Pole Installed

  • Posted by Jeff Click  |  Feb 11, 2019 - 10:52am
    Plan Order
    Order Up!
    We've hit the ground running this morning with good progress. The lot closing is scheduled, and plans are ordered. I'll be in touch with the initial plan draft and check-list when ready. In the meantime, your to-do items: 1) prequalification letter emailed to me at jeff@clickenterprises.com , and 2) Deposit check when you can swing it by.

    You guys have a great week!

    | jC
  • Marked as complete by Jeff  |  Feb 11, 2019 - 10:49am

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Feb 11, 2019 - 10:49am

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Feb 11, 2019 - 10:49am

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Feb 10, 2019 - 3:05pm

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Feb 10, 2019 - 3:05pm

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Feb 10, 2019 - 3:05pm

    Purchase Agreement Pricing Completed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Final Site Grade

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Window & Exterior Door Punch List