Progress feed:
2216 Bretton Lane
← Back to Home Details
  • Marked as complete by Jeff  |  Oct 12, 2021 - 4:44pm

    Address Leak at Master Shower

  • New task added by Jeff  |  Sep 9, 2021 - 11:01am

    Address Leak at Master Shower

  • Marked as complete by Jeff  |  Jul 28, 2021 - 3:57pm

    Replace Bedroom 3 Door

  • Marked as complete by Jeff  |  Jun 23, 2021 - 9:18am

    Repair Water Damage from Ice Damming

  • Marked as complete by Jeff  |  May 27, 2021 - 12:16pm

    Complete RJ45 Connectors On Network Runs

  • New task added by Jeff  |  May 4, 2021 - 4:22pm

    Complete RJ45 Connectors On Network Runs

  • Posted by Jeff Click  |  Feb 8, 2021 - 4:53pm
    Winter Weather & What To Do
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • New task added by Jeff  |  Feb 5, 2021 - 9:56am

    Repair Water Damage from Ice Damming

  • New task added by Jeff  |  Jan 22, 2021 - 9:53am

    Replace Bedroom 3 Door

  • Marked as complete by Jeff  |  Jan 22, 2021 - 9:53am

    Address Master Bedroom Windows Whistling In Wind

  • Marked as complete by Jeff  |  Jan 4, 2021 - 12:53pm

    Door From Garage To House Whistles

  • Marked as complete by Jeff  |  Dec 7, 2020 - 10:41am

    Add separate switch for living fan, replace master, add rods to pendants

  • New task added by Jeff  |  Nov 30, 2020 - 2:12pm

    Door From Garage To House Whistles

  • New task added by Jeff  |  Nov 30, 2020 - 2:10pm

    Address Master Bedroom Windows Whistling In Wind

  • New task added by Jeff  |  Nov 13, 2020 - 11:57am

    Add separate switch for living fan, replace master, add rods to pendants

  • Marked as complete by Jeff  |  Nov 13, 2020 - 11:56am

    Address failing tub seal in master bath

  • New task added by Jeff  |  Nov 6, 2020 - 12:37pm

    Address failing tub seal in master bath

  • Marked as complete by Jeff  |  Nov 6, 2020 - 12:37pm

    Address unfinished floor area at kitchen range

  • Marked as complete by Jeff  |  Nov 2, 2020 - 11:17am

    Replace plank with defective finish

  • Marked as complete by Jeff  |  Oct 30, 2020 - 2:24pm

    Address Master Toilet Issue

  • New task added by Jeff  |  Oct 30, 2020 - 9:32am

    Address Master Toilet Issue

  • Marked as complete by Jeff  |  Oct 28, 2020 - 11:15am

    Powder Bath Sink Leak

  • New task added by Jeff  |  Oct 20, 2020 - 10:06am

    Replace plank with defective finish

  • New task added by Jeff  |  Oct 20, 2020 - 9:49am

    Address unfinished floor area at kitchen range

  • New task added by Jeff  |  Oct 20, 2020 - 9:47am

    Powder Bath Sink Leak

  • Marked as complete by Jeff  |  Oct 15, 2020 - 8:57am

    Closing-Day Final Paint Touch-Up

  • Phase Completed!  |  Oct 15, 2020 - 8:57am

    Punch To Closed

  • Marked as complete by Jeff  |  Oct 15, 2020 - 8:57am

    Closing-Day Final Paint Touch-Up

  • Marked as complete by Jeff  |  Oct 15, 2020 - 8:57am

    Closing Day Pre-Closing Orientation With Client

  • Marked as complete by Jeff  |  Oct 15, 2020 - 8:57am

    Final-Final Clean

  • Marked as complete by Jeff  |  Oct 13, 2020 - 4:59pm

    Certificate of Occupancy Issued

  • Marked as complete by Jeff  |  Oct 13, 2020 - 4:59pm

    Glass & Mirror Punch List

  • Phase Completed!  |  Oct 13, 2020 - 11:51am

    Exterior Rough

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Phase Completed!  |  Oct 13, 2020 - 11:51am

    Exterior Detail

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Pre-closing Walk & Client Orientation

  • Phase Completed!  |  Oct 13, 2020 - 11:51am

    Paint To Finalled

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Zoning Final Inspection

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Building Final Inspection

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  Oct 13, 2020 - 11:51am

    Paint Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Stained Concrete Final

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Tech & Media Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Masonry Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Flooring Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Electrical Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Trim & Hardware Punch List

  • Marked as complete by Jeff  |  Oct 12, 2020 - 4:27pm

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Oct 9, 2020 - 8:52am

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  Oct 9, 2020 - 8:52am

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  Oct 9, 2020 - 8:52am

    Cosmetic Surface Repair Punch List

  • Marked as complete by Jeff  |  Oct 9, 2020 - 8:52am

    Solid Surface Counter Top Punch List

  • Marked as complete by Jeff  |  Oct 9, 2020 - 8:51am

    Plumbing Punch List

  • Marked as complete by Jeff  |  Oct 8, 2020 - 1:57pm

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Oct 8, 2020 - 1:57pm

    Hardware Installation

  • Scheduled by Jeff  |  Oct 7, 2020 - 9:44am

    Final-Final Clean

  • Marked as complete by Jeff  |  Oct 7, 2020 - 8:55am

    HVAC Punch List

  • Marked as complete by Jeff  |  Oct 7, 2020 - 8:53am

    Drywall Punch List

  • Marked as complete by Jeff  |  Oct 5, 2020 - 2:27pm

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Oct 5, 2020 - 9:20am

    Stained Concrete Final

  • Marked as complete by Jeff  |  Oct 5, 2020 - 9:20am

    Carpet Installation

  • Marked as complete by Jeff  |  Oct 5, 2020 - 9:20am

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Oct 5, 2020 - 9:19am

    Sod Installation

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Carpet Installation

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Carpet Installation

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Fireplace Final Installation

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Post-Installation Sod Manual Watering Scheduled

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Irrigation System Programming & Activation (or N/A)

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Oct 2, 2020 - 8:48am

    Temporary Construction Heat Coordinated

  • Phase Completed!  |  Oct 2, 2020 - 8:48am

    Insulation To Trim

  • Marked as complete by Jeff  |  Sep 30, 2020 - 10:08am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Sep 28, 2020 - 9:23am

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 9:23am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 9:23am

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  Sep 28, 2020 - 9:23am

    Irrigation System Installation (or N/A)

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:28pm

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:28pm

    Hand Railing & Banister Installation

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:28pm

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:28pm

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:28pm

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:28pm

    Window Screen Installation

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:27pm

    Outdoor Hand Railing Installed (or N/A

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:27pm

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:27pm

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:27pm

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:27pm

    Final Site Grade

  • Marked as complete by Jeff  |  Sep 24, 2020 - 1:27pm

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Sep 23, 2020 - 4:06pm

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Sep 23, 2020 - 4:06pm

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Sep 23, 2020 - 4:06pm

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Sep 22, 2020 - 9:23am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Sep 22, 2020 - 9:13am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Sep 22, 2020 - 9:13am

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Sep 22, 2020 - 9:13am

    Appliance Package Delivery

  • Scheduled by Jeff  |  Sep 21, 2020 - 11:24am

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:23am

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    Permanent Keys Delivery & Secure Storage

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    Concrete Counter Top Installation

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    Sandy Loam Load Delivery

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:22am

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:21am

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:21am

    Flatwork Pour

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:21am

    Preliminary Flooring Completion

  • Marked as complete by Jeff  |  Sep 21, 2020 - 11:20am

    Hardwood Flooring Installation

  • Marked as complete by Jeff  |  Sep 21, 2020 - 10:51am

    ROWS Inspection Requested & JCH-Verified

  • Scheduled by Jeff  |  Sep 17, 2020 - 1:03pm

    Final Site Grade

  • Marked as complete by Jeff  |  Sep 17, 2020 - 11:35am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  Sep 17, 2020 - 11:35am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:12am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:12am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:11am

    Concrete Counter Top Templating

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:11am

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:11am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:11am

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:11am

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:11am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Sep 15, 2020 - 9:11am

    Electrical Final Meter & Service Installed

  • Scheduled by Jeff  |  Sep 14, 2020 - 1:13pm

    Appliance Package Delivery

  • Scheduled by Jeff  |  Sep 10, 2020 - 2:09pm

    Concrete Counter Top Templating

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:55pm

    Lighting Fixture Package Delivery

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:50pm

    Irrigation System Installation (or N/A)

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:50pm

    Seamless Guttering Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:49pm

    Flatwork Pour

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:48pm

    Address Panel Installed

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:48pm

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:48pm

    Pre-Flatwork Conduit Sleeving

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:43pm

    Hardwood Flooring Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:42pm

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:41pm

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:40pm

    Attic Insulation Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:40pm

    Fireplace Final Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:39pm

    Plumbing Final Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:39pm

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:39pm

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:38pm

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:36pm

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:36pm

    Window Screen Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:35pm

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:35pm

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:35pm

    Hardware Installation

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:34pm

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:24pm

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Sep 9, 2020 - 4:23pm

    Surplus Trim Pick-Up

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:22pm

    Concrete Counter Top Templating

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:22pm

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:22pm

    Concrete Counter Top Installation

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:22pm

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:22pm

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:22pm

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Sep 9, 2020 - 4:22pm

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Sep 3, 2020 - 10:54am

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Sep 3, 2020 - 10:54am

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Sep 3, 2020 - 10:54am

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Sep 2, 2020 - 3:27pm

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Sep 2, 2020 - 3:27pm

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Sep 2, 2020 - 3:27pm

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Sep 2, 2020 - 3:25pm

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Sep 2, 2020 - 3:25pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Sep 2, 2020 - 3:25pm

    Preliminary Wall Tile Completion

  • Scheduled by Jeff  |  Jul 29, 2020 - 3:48pm

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Garage Door Installation

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Mailbox Constructed (If Feasible)

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Jul 29, 2020 - 3:47pm

    Lighting Selections Scheduled

  • Phase Completed!  |  Jul 29, 2020 - 3:47pm

    Frame To Inspections

  • Marked as complete by Jeff  |  Jul 17, 2020 - 10:44am

    Natural Gas Line Installed

  • Scheduled by Jeff  |  Jul 9, 2020 - 10:20am

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Jul 9, 2020 - 10:20am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Jul 9, 2020 - 10:20am

    Cabinet Delivery & Installation Scheduled

  • Scheduled by Jeff  |  Jul 9, 2020 - 10:19am

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Jul 9, 2020 - 10:16am

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Jul 9, 2020 - 10:16am

    Preliminary Interior Flooring & Wall Tile Scheduled

  • Marked as complete by Jeff  |  Jul 9, 2020 - 10:16am

    Attic Access Installation Scheduled

  • Marked as complete by Jeff  |  Jul 9, 2020 - 10:16am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Jul 9, 2020 - 10:16am

    Tile & Hardwood Flooring Take-Off & Ordered

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:20pm

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:20pm

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:17pm

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:16pm

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:16pm

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:16pm

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:16pm

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:16pm

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:15pm

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:15pm

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Jul 7, 2020 - 3:15pm

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Jun 29, 2020 - 9:57am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Jun 29, 2020 - 9:57am

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:01pm

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:01pm

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:01pm

    Insulation & Sealant Installation Completion

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:01pm

    Drywall Material On Site

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:01pm

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:01pm

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:00pm

    Wall Insulation & Seal Package Completion

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:00pm

    Wall Insulation Installation

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:00pm

    Party Wall & Sound Dampened Walls Insulated

  • Marked as complete by Jeff  |  Jun 24, 2020 - 3:00pm

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Brick On Site

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Jun 22, 2020 - 11:03am

    Party Wall & Sound Dampened Wall Insulation Scheduled

  • Marked as complete by Jeff  |  Jun 19, 2020 - 10:23am

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Jun 16, 2020 - 11:23am

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Jun 16, 2020 - 11:23am

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:22am

    Exterior Masonry Scheduled

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:22am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:22am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:22am

    Wall Insulation & Seal Package Scheduled

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Natural Gas System Analysis Requested

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Post-Tension Cables Stressed & Secured

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Supervisor Rough-In Pre-Walk & Notation

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:21am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Jun 16, 2020 - 11:20am

    Framing | Accent Panelling Installation

  • Scheduled by Jeff  |  Jun 12, 2020 - 10:47am

    Masonry Sand On Site

  • Scheduled by Jeff  |  Jun 12, 2020 - 10:46am

    Supplemental Masonry Material On Site

  • Scheduled by Jeff  |  Jun 12, 2020 - 10:45am

    Brick On Site

  • Marked as complete by Jeff  |  Jun 12, 2020 - 10:43am

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  Jun 12, 2020 - 10:43am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Jun 12, 2020 - 10:18am

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  May 26, 2020 - 10:37am

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  May 20, 2020 - 9:38am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  May 20, 2020 - 9:37am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  May 20, 2020 - 9:37am

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  May 20, 2020 - 9:37am

    Roof Installation

  • Marked as complete by Jeff  |  May 20, 2020 - 9:37am

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  May 20, 2020 - 9:37am

    Framing - Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  May 18, 2020 - 3:54pm

    Fireplace Installation

  • Marked as complete by Jeff  |  May 14, 2020 - 9:25am

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  May 14, 2020 - 9:25am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  May 11, 2020 - 9:34am

    Framing - Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  May 11, 2020 - 9:34am

    Framing - Joist Phase Completion

  • Scheduled by Jeff  |  Apr 28, 2020 - 2:09pm

    Fireplace Installation

  • Scheduled by Jeff  |  Apr 28, 2020 - 2:09pm

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Apr 28, 2020 - 2:09pm

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Apr 28, 2020 - 2:08pm

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Apr 28, 2020 - 2:08pm

    Roof Installation

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:07pm

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    Framing - Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    Framing Lumber - Decking & Cornice Order

  • Marked as complete by Jeff  |  Apr 28, 2020 - 2:06pm

    Framing Lumber - Joist & Rafter Order

  • Posted by Jeff Click  |  Mar 20, 2020 - 1:40pm
    Progress Update
    Wow. Sigh. Oh, boy. All things I’m sure we’ve all said over the past week as our world has turned seemingly upside down.

    I hope this post finds you and yours well amidst all of this. I want to update you on what effects I’m seeing in the construction world right now and how it’s impacting progress on your home.

    To date, nearly all aspects of construction are still operating reasonably as-scheduled, with exception to those processes that are affected by the weather. I’ve only seen delays from a few product categories as of the time of this post related to the health crisis.

    The Clickbuild.io system, which I use to manage my projects and keep you apprised of progress, is proving invaluable as many move to a remote working mode, as nearly all of my trades and suppliers work well with me in being responsive in communication and scheduling. I will continue to work diligently and responsibly to maintain the production schedule as best I can, though there are many moving parts comprised of a labor force who depends on work to sustain their own lives, but who also make independent decisions about their response to this.

    I will continue to diligently monitor and navigate delays, as more are sure to reveal themselves over the coming few weeks that may affect your home’s completion schedule, and you can look forward to hearing from me on anything that may affect your projected completion time. In anticipation of that, I ask that you remain flexible should the schedule need to adjust, as there are simply many facets of this process and these conditions that are changing on a daily basis.

    In the meantime, I ask that you continue to work on your end on matters related to your financing in preparation for closing. Please keep me apprised of anything on your end that may have any effect on moving towards closing.

    In closing, I pray you and your family and friends remain healthy and optimistic, knowing that we will prevail through this unprecedented challenge.

    Faithfully,
    | jC

    (Cross-posted to all clients via Clickbuild.io)
  • Marked as complete by Jeff  |  Mar 19, 2020 - 1:12pm

    Foundation Poured

  • Phase Completed!  |  Mar 19, 2020 - 1:12pm

    Pad To Foundation

  • Marked as complete by Jeff  |  Mar 11, 2020 - 2:50pm

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Mar 9, 2020 - 10:22am

    Framing Lumber - Wall Pack Order

  • Marked as complete by Jeff  |  Mar 6, 2020 - 10:20am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Mar 3, 2020 - 1:27pm

    Foundation Form Removal

  • Marked as complete by Jeff  |  Feb 27, 2020 - 12:33pm

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Feb 27, 2020 - 12:33pm

    Foundation Poured

  • Scheduled by Jeff  |  Feb 25, 2020 - 4:28pm

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Feb 25, 2020 - 4:27pm

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Feb 25, 2020 - 4:26pm

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Feb 25, 2020 - 4:26pm

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Feb 21, 2020 - 3:25pm

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Feb 18, 2020 - 2:32pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Feb 12, 2020 - 3:58pm

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Feb 12, 2020 - 3:58pm

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Feb 10, 2020 - 11:07am

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Feb 10, 2020 - 11:07am

    Ground Plumbing Installed

  • Posted by Jeff Click  |  Jan 28, 2020 - 3:39pm
    The Design Notes Packet For All Our Decisions Not Reflected In the Blue Prints
    It's Time To Design!
    We're at the point when it's time to start thinking in greater detail about your new home!

    Design Session 1 is upon us, which involves:
    - Exterior finish selections (Primarily what brick we are using, and potentially some color selections)
    - Electrical Wiring Diagram (What types of lights go where, along with any special electrical needs)
    - Media & Security Diagram (TV, data, speaker wiring, etc.)
    - Flooring Diagram (what types of flooring is going in, and where)
    - A few other technical details.

    Don’t sweat these decisions! I'm here to guide you through making fantastic choices.

    Design sessions need to be scheduled during business hours, as often we need to walk a few doors down to look at materials from suppliers, or make phone calls to check on availability that other decisions depend on. DS1 can often be fully completed over a lunch hour meeting if that helps fit into your schedule better (it usually takes 1-2 hours, max).

    What are some days and times in the next 3 weeks that you have available? Hit me with a comment below and let me know and we’ll book it.

    I’m looking forward to our next time together!

    | jC
  • Marked as complete by Jeff  |  Jan 28, 2020 - 3:39pm

    Phase 1 Design Session Scheduled

  • Phase Completed!  |  Jan 28, 2020 - 3:39pm

    Start To Permit

  • Marked as complete by Jeff  |  Jan 28, 2020 - 3:39pm

    Final Design Notes Created

  • Marked as complete by Jeff  |  Jan 28, 2020 - 3:39pm

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Jan 28, 2020 - 3:39pm

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Jan 28, 2020 - 3:38pm

    Framing Engineering & Material Take-Off Received

  • Scheduled by Jeff  |  Jan 28, 2020 - 3:38pm

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Jan 27, 2020 - 11:01am

    2nd Part Permit Obtained (Or N/A)

  • Posted by Jeff Click  |  Jan 27, 2020 - 10:59am
    Check, Check, Build!
    The Plans Are Now Official
    Good news! The revised set of plans have been returned by the CAD Draftsman. I have personally cross-checked the new set of plans with our notes from the Plan Review Meeting Check-List, and all of our discussed modifications have been made to satisfaction.

    This means that the plans are now considered "official", and final. These plans are now passed on for foundation engineering, lumber/structural engineering, and window ordering.

    Lots of site progress to follow!

    | jC
  • Marked as complete by Jeff  |  Jan 27, 2020 - 10:59am

    Final Plan Revisions JCH-Verified

  • Scheduled by Jeff  |  Jan 24, 2020 - 11:11am

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Jan 24, 2020 - 11:09am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jan 24, 2020 - 11:09am

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Jan 24, 2020 - 11:09am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Jan 24, 2020 - 9:22am

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Jan 24, 2020 - 9:22am

    Final Project Data Updated in CB

  • Scheduled by Jeff  |  Jan 17, 2020 - 9:06am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Jan 17, 2020 - 9:06am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2020 - 9:06am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2020 - 9:05am

    Windows & Exterior Doors Ordered

  • Posted by Jeff Click  |  Jan 13, 2020 - 5:25pm
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Jan 13, 2020 - 5:25pm

    Plans & Application Submitted for Permits

  • Marked as complete by Jeff  |  Jan 13, 2020 - 5:25pm

    Permit-Ready Plans Printed For Permitting

  • Scheduled by Jeff  |  Jan 13, 2020 - 5:24pm

    Ground Plumbing Installed

  • Scheduled by Jeff  |  Jan 13, 2020 - 5:20pm

    Trash Bin Constructed

  • Scheduled by Jeff  |  Jan 13, 2020 - 5:20pm

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Jan 13, 2020 - 5:15pm

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Jan 13, 2020 - 5:15pm

    Pad Site Grading

  • Marked as complete by Jeff  |  Jan 13, 2020 - 5:15pm

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Jan 13, 2020 - 5:13pm

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Jan 10, 2020 - 9:37am

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Jan 10, 2020 - 9:37am

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Jan 10, 2020 - 9:37am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Jan 10, 2020 - 9:37am

    Award Of Project To Trades & Contractors

  • Scheduled by Jeff  |  Jan 6, 2020 - 4:38pm

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Jan 6, 2020 - 4:34pm

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Jan 6, 2020 - 4:34pm

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Jan 6, 2020 - 4:34pm

    Framing Engineering Ordered

  • Marked as complete by Jeff  |  Jan 6, 2020 - 4:33pm

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Dec 31, 2019 - 1:14pm

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Dec 31, 2019 - 1:14pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Dec 31, 2019 - 1:14pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Dec 31, 2019 - 1:14pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Dec 30, 2019 - 4:02pm

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Dec 12, 2019 - 11:54am

    Client Pre-Con Scheduled

  • Scheduled by Jeff  |  Dec 12, 2019 - 11:45am

    Property Pins Located On Site

  • Scheduled by Jeff  |  Dec 12, 2019 - 11:44am

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Dec 12, 2019 - 11:41am

    Site Identification Sign Installed

  • Marked as complete by Jeff  |  Dec 12, 2019 - 11:41am

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Dec 12, 2019 - 11:41am

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Dec 12, 2019 - 11:41am

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Dec 5, 2019 - 10:53am

    Closing of Lot & Construction Financing Secured

  • Scheduled by Jeff  |  Nov 13, 2019 - 4:15pm

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Nov 13, 2019 - 4:14pm

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Nov 13, 2019 - 4:14pm

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Posted by Jeff Click  |  Nov 13, 2019 - 2:24pm
    Purchase Agreement
    Purchase Agreement
    Preston & Melissa, I'm thrilled at the opportunity to collaborate with you on your new home. Thanks for entrusting me to guide you through the experience and process! I've scanned and posted your Purchase Agreement in the files section, which can also be downloaded via this link. Note that after you left, I refreshed the "pretty" pricing page and the information updated to the proper price, and I've included that version in the scan.

    I'll have the plans drafted up while I'm away on our family trip, and will aim to kick them over to you with the checklist for likely review over the Thanksgiving Holiday.

    In the meantime, thanks again, and I'll look forward to our next meeting in a few weeks. | jC
  • Marked as complete by Jeff  |  Nov 13, 2019 - 2:12pm

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Nov 13, 2019 - 2:12pm

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Nov 13, 2019 - 2:12pm

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Nov 13, 2019 - 2:12pm

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Nov 13, 2019 - 2:12pm

    Purchase Agreement Pricing Completed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Foundation Poured

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Concrete Counter Top Installation

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Stained Concrete Final

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Closing-Day Final Paint Touch-Up