Progress feed:
7124 NW 146th
← Back to Home Details
  • Posted by Jeff Click  |  Nov 11, 2019 - 8:59am
    This week's forecast as of Monday morning.
    Winter Advisory
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:39am

    Garage Door Opening Randomly

  • New task added by Jeff  |  Aug 30, 2019 - 8:44am

    Garage Door Opening Randomly

  • Marked as complete by Jeff  |  Jul 3, 2019 - 8:32am

    Back-Fill Low Spots in Back Yard

  • Marked as complete by Jeff  |  May 28, 2019 - 8:46am

    Pre-Closing Walk-Through Punch Items Completed

  • New task added by Jeff  |  May 28, 2019 - 5:46am

    Back-Fill Low Spots in Back Yard

  • Marked as complete by Jeff  |  May 28, 2019 - 5:46am

    Remaining Pre-Closing Walkthrough Items Assigned In Warranty Phase

  • Phase Completed!  |  May 28, 2019 - 5:46am

    Punch To Closed

  • Marked as complete by Jeff  |  May 28, 2019 - 5:46am

    Closing-Day Final Paint Touch-Up

  • Marked as complete by Jeff  |  May 28, 2019 - 5:45am

    Pre-closing Walk & Client Orientation

  • Phase Completed!  |  May 28, 2019 - 5:45am

    Paint To Finalled

  • Marked as complete by Jeff  |  May 28, 2019 - 5:45am

    Fence Panel Installation (or N/A)

  • Phase Completed!  |  May 28, 2019 - 5:45am

    Exterior Detail

  • Marked as complete by Jeff  |  May 21, 2019 - 6:21am

    Address Panel Installed

  • Marked as complete by Jeff  |  May 21, 2019 - 6:21am

    Fence Post Installation (or N/A)

  • Scheduled by Jeff  |  May 7, 2019 - 5:54am

    Electrical Punch List

  • Scheduled by Jeff  |  Apr 23, 2019 - 6:02am

    Fence Post Installation (or N/A)

  • Marked as complete by Jeff  |  Mar 26, 2019 - 6:58am

    Replace Broken Island Globe

  • Marked as complete by Jeff  |  Mar 25, 2019 - 7:01am

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  Mar 25, 2019 - 7:01am

    Certificate of Occupancy Issued

  • Marked as complete by Jeff  |  Mar 25, 2019 - 7:01am

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:59am

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:59am

    Paint Punch List

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Stained Concrete Final

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Zoning Final Inspection

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Building Final Inspection

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:58am

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:57am

    Trim & Hardware Punch List

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:56am

    Electrical Punch List

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:56am

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:56am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:56am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:53am

    Drywall Punch List

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:53am

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:52am

    Final-Final Clean

  • Marked as complete by Jeff  |  Mar 16, 2019 - 10:54am

    Flooring Punch List

  • Marked as complete by Jeff  |  Mar 15, 2019 - 9:15am

    Permanent Keys Delivery & Secure Storage

  • New task added by Jeff  |  Mar 13, 2019 - 1:01pm

    Replace Broken Island Globe

  • Scheduled by Jeff  |  Mar 13, 2019 - 1:00pm

    Final-Final Clean

  • Scheduled by Jeff  |  Mar 13, 2019 - 12:59pm

    Drywall Punch List

  • Scheduled by Jeff  |  Mar 13, 2019 - 12:59pm

    Window & Exterior Door Punch List

  • Scheduled by Jeff  |  Mar 13, 2019 - 12:58pm

    Laminate Counter Top Punch List

  • Scheduled by Jeff  |  Mar 13, 2019 - 12:57pm

    Flooring Punch List

  • Scheduled by Jeff  |  Mar 13, 2019 - 12:56pm

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:54pm

    Carpet Installation

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Tech & Media Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    HVAC Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Glass & Mirror Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Cosmetic Surface Repair Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Solid Surface Counter Top Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Masonry Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Plumbing Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:53pm

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  Mar 13, 2019 - 12:52pm

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  Mar 8, 2019 - 7:01am

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Mar 8, 2019 - 7:01am

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Mar 8, 2019 - 7:01am

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Mar 8, 2019 - 7:01am

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Mar 8, 2019 - 7:01am

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Mar 8, 2019 - 7:01am

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:36am

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:35am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:35am

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:35am

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Feb 28, 2019 - 6:14am

    Carpet Installation

  • Marked as complete by Jeff  |  Feb 28, 2019 - 6:14am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Feb 28, 2019 - 6:14am

    Window Screen Installation

  • Marked as complete by Jeff  |  Feb 28, 2019 - 6:14am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Feb 28, 2019 - 6:13am

    Plumbing Final Installation

  • Posted by Jeff Click  |  Feb 26, 2019 - 9:49am
    Exterior Painted
    Exterior Completion
  • Marked as complete by Jeff  |  Feb 26, 2019 - 5:56am

    Hardware Installation

  • Marked as complete by Jeff  |  Feb 26, 2019 - 5:56am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Feb 22, 2019 - 12:21pm

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Feb 22, 2019 - 12:21pm

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Feb 22, 2019 - 6:28am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Feb 21, 2019 - 8:18am

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Feb 21, 2019 - 8:18am

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Feb 21, 2019 - 6:32am

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Feb 21, 2019 - 6:23am

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Feb 21, 2019 - 6:23am

    Appliance Package Delivery

  • Scheduled by Jeff  |  Feb 19, 2019 - 8:31am

    Carpet Installation

  • Scheduled by Jeff  |  Feb 19, 2019 - 8:29am

    Kitchen Vent Hood Installation

  • Scheduled by Jeff  |  Feb 19, 2019 - 8:29am

    Window Screen Installation

  • Marked as complete by Jeff  |  Feb 19, 2019 - 8:28am

    Fireplace Final Installation

  • Marked as complete by Jeff  |  Feb 19, 2019 - 8:27am

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  Feb 19, 2019 - 8:27am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Feb 18, 2019 - 1:26pm

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Feb 15, 2019 - 6:32am

    Preliminary Detail Clean

  • Scheduled by Jeff  |  Feb 15, 2019 - 6:31am

    Final Site Debris Clean-Up

  • Scheduled by Jeff  |  Feb 15, 2019 - 6:31am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Feb 15, 2019 - 6:28am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Feb 15, 2019 - 6:27am

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Feb 14, 2019 - 6:33am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:38pm

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:32pm

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:32pm

    Attic Insulation Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:32pm

    Fireplace Final Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:31pm

    Plumbing Final Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:30pm

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:30pm

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:30pm

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:29pm

    Appliance Package Delivery

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:28pm

    Lighting Fixture Package Delivery

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:28pm

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:27pm

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Feb 5, 2019 - 2:26pm

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Feb 5, 2019 - 2:25pm

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Barn Door Installation Scheduled

  • Phase Completed!  |  Feb 5, 2019 - 12:08pm

    Insulation To Trim

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Feb 5, 2019 - 12:08pm

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Feb 1, 2019 - 12:00pm

    Hardware Installation

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:59am

    Solid Surface Counter Top Templating

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:59am

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:59am

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:58am

    Surplus Trim Pick-Up

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:58am

    Trim Sweep & Haul Complete

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:58am

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:57am

    Trim Sweep & Haul Scheduled

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:57am

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:56am

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Feb 1, 2019 - 11:55am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:54am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:54am

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Sod Installation

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:53am

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:52am

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:52am

    Temporary Construction Heat Activated

  • Phase Completed!  |  Feb 1, 2019 - 11:52am

    Exterior Rough

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:52am

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Feb 1, 2019 - 11:52am

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Jan 21, 2019 - 12:13pm

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Jan 18, 2019 - 3:57pm

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:55pm

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:55pm

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:55pm

    2nd Phase Concrete Flooring Scheduled

  • Marked as complete by Jeff  |  Jan 14, 2019 - 10:38am

    Final Site Grade

  • Marked as complete by Jeff  |  Dec 21, 2018 - 10:55am

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  Dec 21, 2018 - 10:55am

    Electrical Final Meter & Service Installed

  • Marked as complete by Jeff  |  Dec 14, 2018 - 11:20am

    Preliminary Tile Flooring Completion

  • Marked as complete by Jeff  |  Dec 14, 2018 - 11:20am

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Dec 14, 2018 - 11:20am

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Dec 14, 2018 - 11:20am

    Wall Tile Details Notated On Walls

  • Marked as complete by Jeff  |  Dec 14, 2018 - 11:20am

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Dec 14, 2018 - 11:20am

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Exterior Wood Column Installation

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Curb & Form Haul

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Flatwork Pour

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Pre-Flatwork Conduit Sleeving

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Flatwork Sand Ordered

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:29pm

    Interior Masonry Scheduled (Or N/A)

  • Marked as complete by Jeff  |  Dec 4, 2018 - 1:28pm

    Insulation Inspection Requested & Confirmed by Jeff

  • Marked as complete by Jeff  |  Dec 2, 2018 - 1:47pm

    Garage Door Installation

  • Marked as complete by Jeff  |  Dec 2, 2018 - 1:47pm

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Dec 2, 2018 - 1:47pm

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Dec 2, 2018 - 1:47pm

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Scheduled by Jeff  |  Nov 19, 2018 - 11:21am

    Attic Access Installation Completion

  • Scheduled by Jeff  |  Nov 19, 2018 - 11:21am

    Drywall Phase Site Clean-Up

  • Scheduled by Jeff  |  Nov 19, 2018 - 11:20am

    Garage Door Installation

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:18am

    Sheetrock Installation Completion

  • Scheduled by Jeff  |  Nov 19, 2018 - 11:18am

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:18am

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:18am

    Attic Access Installation Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:17am

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:17am

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:17am

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:17am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:17am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    HERS Energy Performance Inspection Completion (Or N/A)

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    HERS Energy Performance Inspection Scheduled (Or N/A)

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    Insulation Inspection Requested

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:16am

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:15am

    Framer Punch-List Completion

  • Phase Completed!  |  Nov 19, 2018 - 11:15am

    Frame To Inspections

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:15am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:15am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:15am

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Nov 15, 2018 - 5:23pm

    Wall Insulation & Seal Package Completion

  • Scheduled by Jeff  |  Nov 8, 2018 - 4:40pm

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Scheduled by Jeff  |  Nov 8, 2018 - 4:40pm

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Nov 8, 2018 - 4:39pm

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Nov 8, 2018 - 4:39pm

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:54pm

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:54pm

    Mailbox Constructed (If Feasible)

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:54pm

    Exterior Brick Masonry Completion

  • Scheduled by Jeff  |  Nov 6, 2018 - 1:54pm

    Wall Insulation & Seal Package Completion

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:53pm

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:53pm

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Nov 5, 2018 - 10:40am

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Nov 5, 2018 - 10:40am

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Nov 5, 2018 - 10:40am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Nov 5, 2018 - 10:40am

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Nov 5, 2018 - 10:40am

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Nov 5, 2018 - 10:40am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Nov 2, 2018 - 10:38am

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Nov 1, 2018 - 8:45am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Nov 1, 2018 - 8:44am

    Sheetrock & Materials Order Scheduled For Delivery

  • Scheduled by Jeff  |  Oct 29, 2018 - 8:54am

    Masonry Sand On Site

  • Scheduled by Jeff  |  Oct 29, 2018 - 8:53am

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:50am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:50am

    Exterior Masonry Scheduled

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:50am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:48am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:48am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:48am

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:45am

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:45am

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  Oct 24, 2018 - 4:22pm

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Oct 23, 2018 - 2:50pm

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Oct 23, 2018 - 2:49pm

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:22pm

    Brick On Site

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:20pm

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:20pm

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:20pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    Fireplace Installation

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:31am

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Oct 15, 2018 - 1:31pm

    Roof Installation

  • Scheduled by Jeff  |  Oct 8, 2018 - 10:24am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Oct 8, 2018 - 10:23am

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Oct 8, 2018 - 10:23am

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Oct 4, 2018 - 8:38am

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Oct 4, 2018 - 8:38am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Oct 4, 2018 - 8:38am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Posted by Jeff Click  |  Oct 3, 2018 - 1:19pm
    Your Design Notes
    It's Time To Design!
    We're at the point when it's time to start thinking in greater detail about your new home! Design Session 1 is upon us, which involves exterior finish selections, electrical and tech layout, flooring diagram, and more preliminary design decisions. Don't sweat these decisions! I'm here to guide you through making fantastic choices.

    Design sessions need to be scheduled during business hours, as often we need to walk a few doors down to look at materials from suppliers, or make phone calls to check on availability that other decisions depend on. DS1 can often be fully completed over a lunch hour meeting if that helps fit into your schedule better (it usually takes 1-2 hours, max).

    What are some days and times in the next 2 weeks that you have available? I'm looking forward to our next time together!

    | jC
  • Marked as complete by Jeff  |  Oct 3, 2018 - 1:19pm

    Phase 1 Design Session Scheduled

  • Scheduled by Jeff  |  Oct 2, 2018 - 12:53pm

    Supplemental Masonry Material On Site

  • Scheduled by Jeff  |  Oct 2, 2018 - 12:52pm

    Brick On Site

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:51pm

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:50pm

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:48pm

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:48pm

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:44pm

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:44pm

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:44pm

    Foundation Form Removal

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:44pm

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Oct 2, 2018 - 12:44pm

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Oct 2, 2018 - 9:24am

    Framing - Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Oct 2, 2018 - 9:24am

    Framing - Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  Oct 2, 2018 - 9:24am

    Framing - Joist Phase Completion

  • Scheduled by Jeff  |  Sep 29, 2018 - 12:20pm

    Fireplace Installation

  • Scheduled by Jeff  |  Sep 29, 2018 - 12:19pm

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Sep 29, 2018 - 12:19pm

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Sep 29, 2018 - 12:19pm

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Sep 29, 2018 - 12:18pm

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Sep 29, 2018 - 12:17pm

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  Sep 29, 2018 - 12:16pm

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 29, 2018 - 12:16pm

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 29, 2018 - 12:16pm

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 29, 2018 - 12:16pm

    Framing - Wall & Sheathing Phase Completion

  • Scheduled by Jeff  |  Sep 28, 2018 - 10:24am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Sep 28, 2018 - 10:22am

    Roof Installation

  • Marked as complete by Jeff  |  Sep 28, 2018 - 10:21am

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2018 - 10:21am

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2018 - 10:21am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2018 - 10:20am

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Sep 28, 2018 - 10:20am

    Framing Lumber - Decking & Cornice Order

  • Marked as complete by Jeff  |  Sep 28, 2018 - 10:20am

    Framing Lumber - Joist & Rafter Order

  • Marked as complete by Jeff  |  Sep 20, 2018 - 12:37pm

    Foundation Poured

  • Marked as complete by Jeff  |  Sep 20, 2018 - 10:46am

    Ground Electrical Installed

  • Scheduled by Jeff  |  Sep 18, 2018 - 9:38am

    Framing Lumber - Wall Pack Order

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:37am

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:35am

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:34am

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:34am

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:34am

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:34am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:34am

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:34am

    3rd Party Engineering Inspection

  • Scheduled by Jeff  |  Sep 18, 2018 - 9:34am

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Sep 18, 2018 - 9:33am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:46am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Framing Lumber - Wall Pack Order

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Sewer Installed, Tapped, & Back-filled

  • Phase Completed!  |  Aug 27, 2018 - 9:27am

    Pad To Foundation

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Foundation Form Removal

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Foundation Poured

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:27am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:23am

    Site Identification Sign Installed

  • Scheduled by Jeff  |  Aug 21, 2018 - 3:26pm

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:51pm

    Phase 1 Design Session Scheduled

  • Phase Completed!  |  Aug 21, 2018 - 2:51pm

    Start To Permit

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:51pm

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:51pm

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:51pm

    Final Design Notes Created

  • Posted by Jeff Click  |  Aug 21, 2018 - 2:51pm
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:51pm

    Plans & Application Submitted for Permits

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:51pm

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:49pm

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:49pm

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Aug 21, 2018 - 2:49pm

    Pad Site Grading

  • Marked as complete by Jeff  |  Aug 3, 2018 - 8:31am

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Aug 3, 2018 - 8:31am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Aug 3, 2018 - 8:31am

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Aug 3, 2018 - 8:31am

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Aug 3, 2018 - 8:31am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Jul 31, 2018 - 9:12am

    Framing Engineering & Material Take-Off Received

  • Scheduled by Jeff  |  Jul 13, 2018 - 8:01am

    Trash Bin Materials Ordered

  • Scheduled by Jeff  |  Jul 13, 2018 - 8:00am

    Window Take-Off & Bid Received

  • Scheduled by Jeff  |  Jul 13, 2018 - 7:59am

    Framing Engineering & Material Take-Off Received

  • Scheduled by Jeff  |  Jul 13, 2018 - 7:58am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Jul 13, 2018 - 7:57am

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Jul 13, 2018 - 7:56am

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Jul 13, 2018 - 7:56am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Jul 13, 2018 - 7:56am

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Framing Engineering & Material Take-Off Requested

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Final Project Data Updated in CB

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Final Plan Revisions JCH-Verified

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Jul 11, 2018 - 8:59am

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Jul 3, 2018 - 12:39pm

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Jul 3, 2018 - 12:38pm

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Jul 3, 2018 - 12:36pm

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Jul 3, 2018 - 12:09pm

    Purchase Agreement Pricing Completed

  • Marked as complete by Jeff  |  Jul 3, 2018 - 12:09pm

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Jul 3, 2018 - 12:09pm

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Jul 3, 2018 - 12:09pm

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Framing Engineering & Material Take-Off Requested

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Foundation Form Removal

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Foundation Poured

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Phase 1 Design Session Scheduled