Progress feed:
7201 NW 146th
← Back to Home Details
  • Posted by Jeff Click  |  Feb 8, 2021 - 4:53pm
    Winter Weather & What To Do
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • Marked as complete by Jeff  |  Nov 23, 2020 - 1:38pm

    Assess & Address Rusting In Shelter

  • Marked as complete by Jeff  |  Oct 7, 2020 - 4:16pm

    Assess Electrical Issues Leading to Frequent Burnout of Bulbs

  • New task added by Jeff  |  Sep 8, 2020 - 11:54am

    Gate Is Dragging Making It Difficult To Open

  • New task added by Jeff  |  Sep 8, 2020 - 11:51am

    Assess & Address Rusting In Shelter

  • New task added by Jeff  |  Aug 26, 2020 - 3:07pm

    Assess Electrical Issues Leading to Frequent Burnout of Bulbs

  • Posted by Jeff Click  |  Nov 11, 2019 - 8:59am
    This week's forecast as of Monday morning.
    Winter Advisory
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • Marked as complete by Jeff  |  Aug 30, 2019 - 10:59am

    Address transparent spot in purple wall

  • Marked as complete by Jeff  |  Aug 30, 2019 - 10:59am

    Issue with Range Wiring

  • New task added by Jeff  |  Aug 29, 2019 - 8:41pm

    Address transparent spot in purple wall

  • New task added by Jeff  |  Aug 26, 2019 - 10:22am

    Oven Control Panel Is Defective

  • Marked as complete by Jeff  |  Aug 20, 2019 - 9:05am

    Pre-Closing Walk-Through Punch Items Completed

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:39pm

    Final Tile Punch List

  • Phase Completed!  |  Aug 19, 2019 - 12:39pm

    Punch To Closed

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:39pm

    Final Paint Punch List

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:39pm

    Remaining Pre-Closing Walkthrough Items Assigned In Warranty Phase

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:39pm

    Closing-Day Final Paint Touch-Up

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:39pm

    Closing Day Pre-Closing Orientation With Client

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:39pm

    Final-Final Clean

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:39pm

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:38pm

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:38pm

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:38pm

    Yard Debris & Flag Removal

  • Phase Completed!  |  Aug 19, 2019 - 12:38pm

    Exterior Detail

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:38pm

    Address Panel Installed

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:38pm

    Post-Installation Sod Manual Watering Scheduled

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:38pm

    Sod Installation

  • Marked as complete by Jeff  |  Aug 16, 2019 - 1:13pm

    Final Concrete Flooring Punch List

  • Marked as complete by Jeff  |  Aug 15, 2019 - 4:43pm

    Certificate of Occupancy Issued

  • New task added by Jeff  |  Aug 15, 2019 - 12:08pm

    Final Tile Punch List

  • New task added by Jeff  |  Aug 15, 2019 - 12:05pm

    Final Concrete Flooring Punch List

  • Marked as complete by Jeff  |  Aug 15, 2019 - 12:05pm

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  Aug 15, 2019 - 12:05pm

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  Aug 15, 2019 - 12:05pm

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  Aug 15, 2019 - 12:04pm

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  Aug 15, 2019 - 12:04pm

    Trim & Hardware Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 11:28am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Marked as complete by Jeff  |  Aug 13, 2019 - 10:38am

    Concrete Flooring Final

  • Marked as complete by Jeff  |  Aug 13, 2019 - 10:38am

    Paint Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 10:38am

    Flooring Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 10:38am

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Aug 13, 2019 - 9:38am

    Tech & Media Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 9:38am

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 9:38am

    Masonry Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 9:38am

    Electrical Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 9:38am

    Plumbing Punch List

  • Marked as complete by Jeff  |  Aug 13, 2019 - 9:32am

    Zoning Final Inspection

  • Marked as complete by Jeff  |  Aug 13, 2019 - 9:32am

    Building Final Inspection

  • Marked as complete by Jeff  |  Aug 12, 2019 - 2:08pm

    Solid Surface Counter Top Punch List

  • Scheduled by Jeff  |  Aug 12, 2019 - 1:51pm

    Final-Final Clean

  • Marked as complete by Jeff  |  Aug 12, 2019 - 1:50pm

    Zoning Final Inspection Requested

  • Phase Completed!  |  Aug 12, 2019 - 1:50pm

    Paint To Finalled

  • Marked as complete by Jeff  |  Aug 12, 2019 - 1:50pm

    Building Final Inspection Requested

  • Scheduled by Jeff  |  Aug 8, 2019 - 8:33am

    Landscape Bed Installation

  • Scheduled by Jeff  |  Aug 8, 2019 - 8:32am

    Sod Installation

  • Marked as complete by Jeff  |  Aug 8, 2019 - 6:44am

    Drywall Punch List

  • Marked as complete by Jeff  |  Aug 8, 2019 - 6:44am

    Drywall Punch List

  • Marked as complete by Jeff  |  Aug 8, 2019 - 6:44am

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  Aug 8, 2019 - 6:44am

    Cosmetic Surface Repair Punch List

  • Marked as complete by Jeff  |  Aug 8, 2019 - 6:43am

    Storm Shelter Cleaned & Secured

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:45am

    Permanent Keys Delivery & Secure Storage

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:45am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:45am

    Glass & Mirror Punch List

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:45am

    HVAC Punch List

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:45am

    Drywall Punch List

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:44am

    Carpet Installation

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:44am

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:44am

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:44am

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:44am

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:44am

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:44am

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Jul 30, 2019 - 6:44am

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Jul 30, 2019 - 6:35am

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:49am

    Storm Shelter Installation

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:46am

    Exterior Wood Column Installation

  • Scheduled by Jeff  |  Jul 25, 2019 - 6:46am

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Jul 25, 2019 - 6:28am

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  Jul 25, 2019 - 6:27am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Jul 23, 2019 - 6:44am

    Pre-closing Walk & Client Orientation

  • Scheduled by Jeff  |  Jul 18, 2019 - 1:41pm

    Pre-closing Walk & Client Orientation

  • Scheduled by Jeff  |  Jul 18, 2019 - 9:17am

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Jul 18, 2019 - 9:16am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Jul 18, 2019 - 9:16am

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  Jul 18, 2019 - 9:15am

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  Jul 18, 2019 - 9:15am

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Jul 18, 2019 - 9:15am

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  Jul 18, 2019 - 9:15am

    Sandy Loam Load Delivery

  • Marked as complete by Jeff  |  Jul 17, 2019 - 6:30am

    Carpet Installation

  • Marked as complete by Jeff  |  Jul 16, 2019 - 6:33am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Jul 13, 2019 - 10:17am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Jul 13, 2019 - 10:17am

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Jul 13, 2019 - 10:17am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Jul 13, 2019 - 10:17am

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Jul 10, 2019 - 12:54pm

    Seamless Guttering Installation

  • Scheduled by Jeff  |  Jul 9, 2019 - 6:26am

    Preliminary Detail Clean

  • Scheduled by Jeff  |  Jul 9, 2019 - 6:24am

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Jul 9, 2019 - 6:23am

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Jul 9, 2019 - 6:22am

    Barn Door(s) Installation

  • Marked as complete by Jeff  |  Jul 9, 2019 - 6:21am

    Appliance Package Delivery

  • Marked as complete by Jeff  |  Jul 9, 2019 - 6:21am

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Jul 9, 2019 - 6:21am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Jul 9, 2019 - 6:21am

    Window Screen Installation

  • Marked as complete by Jeff  |  Jul 8, 2019 - 5:51am

    Final Site Grade

  • Scheduled by Jeff  |  Jul 1, 2019 - 6:27am

    Storm Shelter Installation

  • Marked as complete by Jeff  |  Jun 28, 2019 - 7:03am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Jun 28, 2019 - 7:02am

    Hardware Installation

  • Marked as complete by Jeff  |  Jun 27, 2019 - 6:23am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:07am

    Attic Insulation Installation

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:07am

    Fireplace Final Installation

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:07am

    Plumbing Final Installation

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:06am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:06am

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:05am

    Lighting Fixture Package Delivery

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:05am

    Appliance Package Delivery

  • Scheduled by Jeff  |  Jun 26, 2019 - 10:04am

    Window Screen Installation

  • Marked as complete by Jeff  |  Jun 26, 2019 - 10:02am

    Termite Certificate & Guarantee Received & Filed

  • Marked as complete by Jeff  |  Jun 26, 2019 - 10:02am

    Curb & Form Haul

  • Scheduled by Jeff  |  Jun 24, 2019 - 10:11am

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Jun 24, 2019 - 10:10am

    Final Site Grade

  • Scheduled by Jeff  |  Jun 24, 2019 - 10:10am

    Curb & Form Haul

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    Flatwork Pour

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:08am

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:07am

    Pre-Flatwork Conduit Sleeving

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:07am

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:07am

    Barn Door Installation Scheduled

  • Phase Completed!  |  Jun 24, 2019 - 10:07am

    Insulation To Trim

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:05am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Jun 24, 2019 - 10:05am

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Jun 20, 2019 - 6:15am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Jun 20, 2019 - 6:15am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Jun 18, 2019 - 4:45pm

    Final Exterior Door Installed

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:40pm

    Carpet Installation

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:39pm

    Carpet Installation Scheduled

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:39pm

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:38pm

    Hardware Installation

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:38pm

    Interior Stain & Painting

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:37pm

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:37pm

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:37pm

    Surplus Trim Pick-Up

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:35pm

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:35pm

    Barn Door Installation Scheduled

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:34pm

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Jun 17, 2019 - 3:34pm

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:33pm

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:32pm

    Wall Tile Details Notated On Walls

  • Phase Completed!  |  Jun 17, 2019 - 3:32pm

    Exterior Rough

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:31pm

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:31pm

    Electrical Final Meter & Service Installed

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:31pm

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:31pm

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Jun 17, 2019 - 3:31pm

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Jun 12, 2019 - 5:49am

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Jun 12, 2019 - 5:49am

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Jun 5, 2019 - 9:42am

    Natural Gas Line Installed

  • Scheduled by Jeff  |  Jun 4, 2019 - 5:50am

    Flatwork Sand On Site

  • Scheduled by Jeff  |  Jun 4, 2019 - 5:49am

    Cabinet Delivery & Installation

  • Scheduled by Jeff  |  Jun 4, 2019 - 5:48am

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Jun 4, 2019 - 5:48am

    Flatwork Sand Ordered

  • Marked as complete by Jeff  |  Jun 4, 2019 - 5:47am

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Jun 4, 2019 - 5:47am

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Jun 4, 2019 - 5:47am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Jun 4, 2019 - 5:47am

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Jun 3, 2019 - 5:45am

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  May 30, 2019 - 8:44am

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  May 30, 2019 - 8:43am

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  May 30, 2019 - 8:43am

    Garage Door Installation

  • Marked as complete by Jeff  |  May 29, 2019 - 6:33am

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  May 29, 2019 - 6:33am

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  May 29, 2019 - 6:33am

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  May 29, 2019 - 6:33am

    Mailbox Constructed (If Feasible)

  • Marked as complete by Jeff  |  May 29, 2019 - 6:33am

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  May 28, 2019 - 6:53am

    Sheetrock Installation Completion

  • Scheduled by Jeff  |  May 24, 2019 - 3:07pm

    Concrete Flooring Work Complete

  • Scheduled by Jeff  |  May 24, 2019 - 3:07pm

    Preliminary Wall Tile Completion

  • Scheduled by Jeff  |  May 24, 2019 - 3:03pm

    Drywall Tape, Bed, & Texture Completion

  • Scheduled by Jeff  |  May 24, 2019 - 3:03pm

    Garage Door Installation

  • Marked as complete by Jeff  |  May 24, 2019 - 3:01pm

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  May 24, 2019 - 3:01pm

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  May 24, 2019 - 3:00pm

    Insulation Inspection Requested & Confirmed by Jeff

  • Scheduled by Jeff  |  May 23, 2019 - 5:43am

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  May 23, 2019 - 5:43am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:42am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:41am

    Insulation & Sealant Installation Completion

  • Marked as complete by Jeff  |  May 23, 2019 - 5:41am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:40am

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:40am

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:40am

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:40am

    2nd Phase Concrete Flooring Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:40am

    Attic Access Installation Scheduled

  • Marked as complete by Jeff  |  May 23, 2019 - 5:40am

    Garage Door Installation Scheduled

  • Scheduled by Jeff  |  May 21, 2019 - 10:52am

    Cabinet Delivery & Installation Scheduled

  • Scheduled by Jeff  |  May 21, 2019 - 10:52am

    Preliminary Floor &/or Wall Tile Scheduled

  • Scheduled by Jeff  |  May 21, 2019 - 10:51am

    2nd Phase Concrete Flooring Scheduled

  • Scheduled by Jeff  |  May 21, 2019 - 10:50am

    Attic Access Installation Scheduled

  • Scheduled by Jeff  |  May 21, 2019 - 10:50am

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  May 21, 2019 - 10:47am

    Phase 2 Design Session Scheduled

  • Phase Completed!  |  May 21, 2019 - 10:47am

    Frame To Inspections

  • Marked as complete by Jeff  |  May 21, 2019 - 10:47am

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  May 21, 2019 - 10:45am

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  May 21, 2019 - 10:45am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  May 21, 2019 - 10:45am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  May 21, 2019 - 6:43am

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  May 20, 2019 - 4:43pm

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  May 20, 2019 - 4:43pm

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  May 20, 2019 - 4:43pm

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  May 17, 2019 - 6:08am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  May 17, 2019 - 6:08am

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  May 17, 2019 - 6:08am

    Drywall Material On Site

  • Marked as complete by Jeff  |  May 17, 2019 - 6:08am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  May 16, 2019 - 5:57am

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  May 16, 2019 - 5:56am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  May 16, 2019 - 5:56am

    Brick On Site

  • Marked as complete by Jeff  |  May 16, 2019 - 5:53am

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  May 16, 2019 - 5:53am

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Scheduled by Jeff  |  May 13, 2019 - 4:04pm

    Drywall Material On Site

  • Marked as complete by Jeff  |  May 13, 2019 - 4:03pm

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  May 13, 2019 - 4:03pm

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  May 13, 2019 - 4:03pm

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  May 13, 2019 - 4:03pm

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  May 13, 2019 - 4:03pm

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  May 13, 2019 - 4:03pm

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  May 13, 2019 - 10:21am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  May 13, 2019 - 9:47am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  May 10, 2019 - 6:28am

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  May 10, 2019 - 6:27am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Scheduled by Jeff  |  May 9, 2019 - 10:30am

    Surplus Lumber Pickup

  • Scheduled by Jeff  |  May 9, 2019 - 10:30am

    Exterior Brick Masonry Completion

  • Scheduled by Jeff  |  May 9, 2019 - 10:24am

    Supplemental Masonry Material On Site

  • Scheduled by Jeff  |  May 9, 2019 - 10:21am

    Brick On Site

  • Marked as complete by Jeff  |  May 9, 2019 - 10:20am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  May 9, 2019 - 10:20am

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  May 9, 2019 - 10:20am

    Exterior Masonry Scheduled

  • Marked as complete by Jeff  |  May 9, 2019 - 10:20am

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  May 9, 2019 - 10:19am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  May 9, 2019 - 10:19am

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  May 9, 2019 - 6:45am

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  May 6, 2019 - 4:04pm

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  May 6, 2019 - 5:49am

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  May 6, 2019 - 5:46am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  May 6, 2019 - 5:45am

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  May 3, 2019 - 6:45am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Scheduled by Jeff  |  May 3, 2019 - 6:45am

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  May 3, 2019 - 6:45am

    Drywall Take-off Requested

  • Scheduled by Jeff  |  May 3, 2019 - 6:45am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  May 3, 2019 - 6:44am

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  May 3, 2019 - 6:44am

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  May 3, 2019 - 6:43am

    Wall Insulation & Seal Package Scheduled

  • Marked as complete by Jeff  |  May 3, 2019 - 6:43am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Roof Installation

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Framing | Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Framing | Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  May 3, 2019 - 6:42am

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Apr 22, 2019 - 3:45pm

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Apr 22, 2019 - 3:43pm

    Framing | Joist Phase Completion

  • Marked as complete by Jeff  |  Apr 22, 2019 - 3:43pm

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Phase Completed!  |  Apr 22, 2019 - 3:43pm

    Pad To Foundation

  • Marked as complete by Jeff  |  Apr 22, 2019 - 3:43pm

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Apr 18, 2019 - 9:30am

    Framing Lumber | Decking & Cornice Order

  • Marked as complete by Jeff  |  Apr 18, 2019 - 9:30am

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Apr 18, 2019 - 9:30am

    Framing | Wall & Sheathing Phase Completion

  • Scheduled by Jeff  |  Apr 16, 2019 - 6:38am

    Final Exterior Door Ordered

  • Scheduled by Jeff  |  Apr 16, 2019 - 6:36am

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Apr 16, 2019 - 6:36am

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Apr 16, 2019 - 6:35am

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Apr 16, 2019 - 6:34am

    Roof Installation

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:33am

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:33am

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:33am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:33am

    Plumbing Rough-In Scheduled

  • Scheduled by Jeff  |  Apr 16, 2019 - 6:33am

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:33am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:32am

    Framing Lumber | Joist & Rafter Order

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:32am

    Framing Lumber | Wall Pack Order

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:32am

    Foundation Form Removal

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:32am

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Apr 16, 2019 - 6:32am

    Foundation Poured

  • Posted by Jeff Click  |  Apr 12, 2019 - 6:59am
    Foundation Prepped
    Time To Pour!
    The foundation is prepped and ready for pouring. This view is going to look dramatically different in just a few weeks! You guys have a great weekend, and looking forward to our design session next week. | jC
  • Marked as complete by Jeff  |  Apr 11, 2019 - 12:18pm

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Apr 11, 2019 - 12:18pm

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:40am

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:40am

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:40am

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:39am

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:39am

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:39am

    Post-Tension Foundation Cables Set

  • Posted by Jeff Click  |  Mar 28, 2019 - 5:13pm
    Your Design Notes
    It's Time To Design!
    We're at the point when it's time to start thinking in greater detail about your new home! Design Session 1 is upon us, which involves exterior finish selections, electrical and tech layout, flooring diagram, and more preliminary design decisions. Don't sweat these decisions! I'm here to guide you through making fantastic choices.

    Design sessions need to be scheduled during business hours, as often we need to walk a few doors down to look at materials from suppliers, or make phone calls to check on availability that other decisions depend on. DS1 can often be fully completed over a lunch hour meeting if that helps fit into your schedule better (it usually takes 1-2 hours, max).

    What are some days and times in the next 2 weeks that you have available? I'm looking forward to our next time together!

    | jC
  • Marked as complete by Jeff  |  Mar 28, 2019 - 5:13pm

    Final Design Notes Created

  • Marked as complete by Jeff  |  Mar 26, 2019 - 10:10am

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Mar 26, 2019 - 10:10am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Mar 22, 2019 - 6:55am

    Ground Electrical Installed

  • Scheduled by Jeff  |  Mar 18, 2019 - 1:09pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Mar 18, 2019 - 1:08pm

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Mar 18, 2019 - 1:08pm

    Load of Sand For Plumbers Ordered

  • Marked as complete by Jeff  |  Mar 18, 2019 - 1:08pm

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Mar 14, 2019 - 6:26am

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Mar 10, 2019 - 3:35pm

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:38am

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Mar 8, 2019 - 6:38am

    Property Pins Located On Site

  • Scheduled by Jeff  |  Mar 7, 2019 - 6:17am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Mar 7, 2019 - 6:16am

    Porta-Potty Delivered

  • Posted by Jeff Click  |  Mar 7, 2019 - 6:16am
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Scheduled by Jeff  |  Mar 2, 2019 - 10:37am

    Foundation Forms Constructed

  • Scheduled by Jeff  |  Mar 2, 2019 - 10:35am

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Mar 2, 2019 - 10:34am

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Mar 2, 2019 - 10:34am

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Mar 2, 2019 - 10:34am

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Mar 2, 2019 - 10:34am

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Mar 2, 2019 - 10:34am

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Mar 2, 2019 - 10:34am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Mar 2, 2019 - 10:34am

    Framing Engineering & Material Take-Off Requested

  • Scheduled by Jeff  |  Feb 21, 2019 - 1:21pm

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:20pm

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:20pm

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:20pm

    Site Drainage Analysis & Plan

  • Scheduled by Jeff  |  Feb 21, 2019 - 1:15pm

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:14pm

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:13pm

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:13pm

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:12pm

    Final Project Data Updated in CB

  • Posted by Jeff Click  |  Feb 21, 2019 - 1:09pm
    Check, Check, Build!
    The Plans Are Now Official
    Good news! The revised set of plans have been returned by the CAD Draftsman. I have personally cross-checked the new set of plans with our notes from the Plan Review Meeting Check-List, and all of our discussed modifications have been made to satisfaction.

    This means that the plans are now considered "official", and final. These plans are now passed on for foundation engineering, lumber/structural engineering, and window ordering.

    Lots of site progress to follow!

    | jC
  • Marked as complete by Jeff  |  Feb 21, 2019 - 1:09pm

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Feb 19, 2019 - 4:55pm

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Feb 19, 2019 - 4:55pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Feb 19, 2019 - 4:55pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Feb 19, 2019 - 4:55pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Feb 19, 2019 - 4:55pm

    Jeff's Plan Review & Pre-Con Comments

  • Posted by Jeff Click  |  Feb 19, 2019 - 10:05am
    Your Pad Site
    The Dirt Has Moved
    We've broken ground, y'all! I'll be submitting plans for permitting this week and getting the foundation and framing engineering submitted. Up next on site will be the foundation forming.

    Have a great week, and stay safe!

    | jC
  • Scheduled by Jeff  |  Feb 19, 2019 - 6:55am

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:38am

    Pad Site Grading

  • Scheduled by Jeff  |  Feb 15, 2019 - 11:35am

    Pad Site Grading

  • Marked as complete by Jeff  |  Feb 15, 2019 - 11:35am

    Site Identification Sign Installed

  • Marked as complete by Jeff  |  Feb 11, 2019 - 1:24pm

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Feb 11, 2019 - 1:24pm

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Feb 11, 2019 - 1:24pm

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Feb 11, 2019 - 1:24pm

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Feb 11, 2019 - 1:24pm

    Initial Draft of Plans Received

  • Posted by Jeff Click  |  Jan 28, 2019 - 10:39am
    SOLD!
    First Signs of Progress
    Here's what your lot looks like as of this morning! FYI, it turns out the lot you wanted is 7201, not 7129. I've updated the data accordingly but wanted to bring it to your attention just so you were aware. Have a great week, I'll be in touch!
  • Marked as complete by Jeff  |  Jan 27, 2019 - 2:48pm

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Jan 27, 2019 - 2:48pm

    Lot Closing Scheduled

  • Posted by Jeff Click  |  Jan 27, 2019 - 2:36pm
    Your House On Paper
    Let's Do This
    Tommy & Erin, I can't thank you enough for the opportunity to collaborate with you on your new home. I'm looking forward to a fun process in the months to come! | jC
  • Marked as complete by Jeff  |  Jan 27, 2019 - 2:17pm

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Jan 27, 2019 - 2:17pm

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Jan 27, 2019 - 2:17pm

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Jan 27, 2019 - 2:17pm

    Purchase Agreement Pricing Completed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Building Rough-In Inspection Passed