1121 NW 56
← Back to Home Details
  • Marked as complete by Jeff  |  Dec 14, 2020 - 2:46pm

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Dec 14, 2020 - 2:46pm

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Nov 30, 2020 - 1:49pm

    Drywall Material On Site

  • Marked as complete by Jeff  |  Nov 30, 2020 - 1:49pm

    Wall Insulation & Seal Package Scheduled

  • Marked as complete by Jeff  |  Nov 30, 2020 - 1:49pm

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Nov 30, 2020 - 1:49pm

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Nov 30, 2020 - 1:48pm

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Oct 30, 2020 - 11:36am

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Oct 30, 2020 - 11:36am

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Oct 30, 2020 - 11:36am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Oct 30, 2020 - 11:36am

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Natural Gas System Analysis Requested

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:48pm

    Fireplace Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Post-Tension Cables Stressed & Secured

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:47pm

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Natural Gas System Analysis Requested

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Fireplace Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:42pm

    Post-Tension Cables Stressed & Secured

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  Sep 28, 2020 - 1:41pm

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Sep 22, 2020 - 9:13am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Roof Installation

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Framing | Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Framing | Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Framing | Joist Phase Completion

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Framing | Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Framing Lumber | Decking & Cornice Order

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:37pm

    Framing Lumber | Joist & Rafter Order

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Framing Lumber | Wall Pack Order

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Phase Completed!  |  Aug 5, 2020 - 2:36pm

    Pad To Foundation

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Foundation Form Removal

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Foundation Poured

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Termite Pre-Treatment For Foundation

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Aug 5, 2020 - 2:36pm

    Post-Tension Foundation Cables Set

  • Scheduled by Jeff  |  Jul 27, 2020 - 1:16pm

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Jul 27, 2020 - 1:12pm

    Roof Installation

  • Marked as complete by Jeff  |  Jul 27, 2020 - 1:08pm

    Roofing Material & Labor Scheduled

  • Posted by Jeff Click  |  Mar 20, 2020 - 1:40pm
    Progress Update
    Wow. Sigh. Oh, boy. All things I’m sure we’ve all said over the past week as our world has turned seemingly upside down.

    I hope this post finds you and yours well amidst all of this. I want to update you on what effects I’m seeing in the construction world right now and how it’s impacting progress on your home.

    To date, nearly all aspects of construction are still operating reasonably as-scheduled, with exception to those processes that are affected by the weather. I’ve only seen delays from a few product categories as of the time of this post related to the health crisis.

    The Clickbuild.io system, which I use to manage my projects and keep you apprised of progress, is proving invaluable as many move to a remote working mode, as nearly all of my trades and suppliers work well with me in being responsive in communication and scheduling. I will continue to work diligently and responsibly to maintain the production schedule as best I can, though there are many moving parts comprised of a labor force who depends on work to sustain their own lives, but who also make independent decisions about their response to this.

    I will continue to diligently monitor and navigate delays, as more are sure to reveal themselves over the coming few weeks that may affect your home’s completion schedule, and you can look forward to hearing from me on anything that may affect your projected completion time. In anticipation of that, I ask that you remain flexible should the schedule need to adjust, as there are simply many facets of this process and these conditions that are changing on a daily basis.

    In the meantime, I ask that you continue to work on your end on matters related to your financing in preparation for closing. Please keep me apprised of anything on your end that may have any effect on moving towards closing.

    In closing, I pray you and your family and friends remain healthy and optimistic, knowing that we will prevail through this unprecedented challenge.

    Faithfully,
    | jC

    (Cross-posted to all clients via Clickbuild.io)
  • Marked as complete by Jeff  |  Mar 19, 2020 - 1:10pm

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Mar 6, 2020 - 10:27am

    Load of Sand For Plumbers Ordered

  • Marked as complete by Jeff  |  Mar 3, 2020 - 11:50am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Feb 7, 2020 - 9:32am

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Feb 7, 2020 - 9:32am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Feb 7, 2020 - 9:32am

    Pad Site Grading

  • Marked as complete by Jeff  |  Feb 7, 2020 - 9:32am

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Feb 7, 2020 - 9:32am

    Site Identification Sign Installed

  • Marked as complete by Jeff  |  Jan 13, 2020 - 2:04pm

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jan 13, 2020 - 2:02pm

    Temp Electric Pole Installed

  • Scheduled by Jeff  |  Dec 27, 2019 - 11:45am

    Ground Plumbing Installed

  • Scheduled by Jeff  |  Dec 23, 2019 - 11:11am

    Temp Electric Pole Installed

  • Posted by Jeff Click  |  Nov 8, 2019 - 9:41am
    Black Friday Sale
    Black Friday For Your House & Family Vacation
    I wanted to bring this opportunity to your attention, as my appliance supplier (Known both as Hahn Appliances *and* Metro Appliances & More...same company) is having a 10% clearance on 11/14. This could be a good opportunity to grab a nice refrigerator, washer & dryer, or anything else you have on your wish list for the new pad.

    If you don't take advantage of this sale, remember I can always get you my wholesale pricing on those items at any other time, which would include delivery and installation. Feel free to hit me up with any model numbers of items you'd like quotes on.

    Also, I wanted to let you know in advance that I will be out for the week of the 18th-22nd for an overdue family getaway. I always leave with appropriate project progress scheduled to take place where possible, and I do have assistance in getting eyes on the jobs on site. I can also check-in via my remote site cameras to monitor progress. Note that I do build in cushion into construction schedules to allow a margin for things like this, weather, and holidays. Nonetheless, I wanted to make you aware of it in case you reached out to me and didn't hear back in my usual response window.

    Have a great weekend!

    | jC
  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:38pm

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Sep 18, 2019 - 11:37am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Sep 5, 2019 - 4:50pm

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Framing Engineering & Material Take-Off Requested

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Final Project Data Updated in CB

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Aug 30, 2019 - 9:21am

    Purchase Agreement Pricing Completed

  • Posted by Jeff Click  |  Aug 26, 2019 - 12:47pm
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Aug 26, 2019 - 12:47pm

    Plans & Application Submitted for Permits

  • Posted by Jeff Click  |  Aug 26, 2019 - 7:00am
    Check, Check, Build!
    The Plans Are Now Official
    Good news! The revised set of plans have been returned by the CAD Draftsman. I have personally cross-checked the new set of plans with our notes from the Plan Review Meeting Check-List, and all of our discussed modifications have been made to satisfaction.

    This means that the plans are now considered "official", and final. These plans are now passed on for foundation engineering, lumber/structural engineering, and window ordering.

    Lots of site progress to follow!

    | jC
  • Marked as complete by Jeff  |  Aug 26, 2019 - 7:00am

    Final Plan Revisions JCH-Verified

  • Scheduled by Jeff  |  Aug 26, 2019 - 6:56am

    Window Take-Off & Bid Received

  • Scheduled by Jeff  |  Aug 26, 2019 - 6:52am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Aug 26, 2019 - 6:36am

    Framing Engineering & Material Take-Off Received

  • Scheduled by Jeff  |  Aug 26, 2019 - 6:35am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Aug 26, 2019 - 6:33am

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Building Rough-In Inspection Requested