Progress feed:
7129 NW 146th
← Back to Home Details
  • Posted by Jeff Click  |  Feb 8, 2021 - 4:53pm
    Winter Weather & What To Do
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:38pm

    Pre-Closing Walk-Through Punch Items Completed

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Remaining Pre-Closing Walkthrough Items Assigned In Warranty Phase

  • Phase Completed!  |  Jan 17, 2020 - 12:14pm

    Punch To Closed

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Closing-Day Final Paint Touch-Up

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Closing Day Pre-Closing Orientation With Client

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Final-Final Clean

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Paint Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Tech & Media Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    HVAC Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Glass & Mirror Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Masonry Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Flooring Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Electrical Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Plumbing Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Jan 17, 2020 - 12:14pm

    Trim & Hardware Punch List

  • Scheduled by Jeff  |  Jan 10, 2020 - 3:05pm

    Plumbing Punch List

  • Scheduled by Jeff  |  Jan 9, 2020 - 8:13pm

    Final-Final Clean

  • Marked as complete by Jeff  |  Jan 9, 2020 - 8:12pm

    Certificate of Occupancy Issued

  • Marked as complete by Jeff  |  Jan 8, 2020 - 2:44pm

    Cosmetic Surface Repair Punch List

  • Marked as complete by Jeff  |  Jan 8, 2020 - 2:43pm

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Jan 8, 2020 - 2:43pm

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Jan 8, 2020 - 2:43pm

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Jan 8, 2020 - 2:43pm

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Phase Completed!  |  Jan 8, 2020 - 2:43pm

    Paint To Finalled

  • Marked as complete by Jeff  |  Jan 8, 2020 - 2:43pm

    Pre-closing Walk & Client Orientation

  • Marked as complete by Jeff  |  Jan 8, 2020 - 2:43pm

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Dec 22, 2019 - 2:05pm

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Dec 22, 2019 - 2:05pm

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Dec 11, 2019 - 9:21am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Dec 9, 2019 - 1:46pm

    Concrete Flooring Final

  • Scheduled by Jeff  |  Dec 6, 2019 - 2:54pm

    Concrete Flooring Final

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:54pm

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:54pm

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:54pm

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:54pm

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:53pm

    Air Conditioning System Charged & JCH Verified

  • Scheduled by Jeff  |  Dec 6, 2019 - 2:51pm

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Carpet Installation

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Zoning Final Inspection

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Building Final Inspection

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Solid Surface Counter Top Punch List

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Carpet Installation

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Carpet Installation

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:50pm

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:49pm

    Permanent Keys Delivery & Secure Storage

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:49pm

    Water Meter Installed & Back-filled

  • Phase Completed!  |  Dec 6, 2019 - 2:49pm

    Frame To Inspections

  • Marked as complete by Jeff  |  Dec 5, 2019 - 3:07pm

    Drywall Punch List

  • Marked as complete by Jeff  |  Dec 5, 2019 - 11:15am

    Attic Insulation Installation

  • Scheduled by Jeff  |  Dec 2, 2019 - 11:23am

    Drywall Punch List

  • Marked as complete by Jeff  |  Dec 2, 2019 - 9:40am

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  Dec 2, 2019 - 9:40am

    Barn Door(s) Installation

  • Marked as complete by Jeff  |  Dec 2, 2019 - 9:40am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  Dec 2, 2019 - 9:40am

    Window Screen Installation

  • Marked as complete by Jeff  |  Dec 2, 2019 - 9:40am

    Hardware Installation

  • Marked as complete by Jeff  |  Dec 2, 2019 - 9:40am

    Sod Installation

  • Phase Completed!  |  Dec 2, 2019 - 9:40am

    Exterior Detail

  • Marked as complete by Jeff  |  Nov 27, 2019 - 5:22pm

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Nov 26, 2019 - 4:20pm

    Fireplace Final Installation

  • Scheduled by Jeff  |  Nov 26, 2019 - 11:35am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Address Panel Installed

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Fence Panel Installation (or N/A)

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Fence Post Installation (or N/A)

  • Marked as complete by Jeff  |  Nov 25, 2019 - 10:03am

    Sandy Loam Load Delivery

  • Marked as complete by Jeff  |  Nov 15, 2019 - 10:07pm

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Nov 14, 2019 - 9:15am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Nov 14, 2019 - 9:14am

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Nov 11, 2019 - 3:03pm

    Appliance Package Delivery

  • Marked as complete by Jeff  |  Nov 11, 2019 - 3:03pm

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Nov 11, 2019 - 3:03pm

    Electrical & Lighting Final Installation

  • Posted by Jeff Click  |  Nov 8, 2019 - 9:41am
    Black Friday Sale
    Black Friday For Your House & Family Vacation
    I wanted to bring this opportunity to your attention, as my appliance supplier (Known both as Hahn Appliances *and* Metro Appliances & More...same company) is having a 10% clearance on 11/14. This could be a good opportunity to grab a nice refrigerator, washer & dryer, or anything else you have on your wish list for the new pad.

    If you don't take advantage of this sale, remember I can always get you my wholesale pricing on those items at any other time, which would include delivery and installation. Feel free to hit me up with any model numbers of items you'd like quotes on.

    Also, I wanted to let you know in advance that I will be out for the week of the 18th-22nd for an overdue family getaway. I always leave with appropriate project progress scheduled to take place where possible, and I do have assistance in getting eyes on the jobs on site. I can also check-in via my remote site cameras to monitor progress. Note that I do build in cushion into construction schedules to allow a margin for things like this, weather, and holidays. Nonetheless, I wanted to make you aware of it in case you reached out to me and didn't hear back in my usual response window.

    Have a great weekend!

    | jC
  • Scheduled by Jeff  |  Nov 7, 2019 - 9:57am

    Final Site Debris Clean-Up

  • Scheduled by Jeff  |  Nov 7, 2019 - 9:29am

    Landscape Bed Installation

  • Scheduled by Jeff  |  Nov 7, 2019 - 9:29am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Nov 7, 2019 - 9:26am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Nov 7, 2019 - 9:25am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Nov 7, 2019 - 9:25am

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Nov 7, 2019 - 9:25am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Nov 7, 2019 - 9:24am

    Final Site Grade

  • Marked as complete by Jeff  |  Nov 7, 2019 - 9:24am

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 12:24pm

    Exterior Wood Column Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 12:24pm

    Attic Access Installation Completion

  • Phase Completed!  |  Nov 4, 2019 - 12:24pm

    Insulation To Trim

  • Marked as complete by Jeff  |  Nov 4, 2019 - 10:44am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Oct 29, 2019 - 10:47am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Oct 29, 2019 - 10:47am

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Oct 29, 2019 - 10:47am

    Curb & Form Haul

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:45pm

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:45pm

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:44pm

    Fireplace Final Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:44pm

    Plumbing Final Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:43pm

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:43pm

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:43pm

    Appliance Package Delivery

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:42pm

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Flatwork Pour

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Termite Certificate & Guarantee Received & Filed

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Pre-Flatwork Conduit Sleeving

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Flatwork Sand Ordered

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:37pm

    Wall Insulation Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:17pm

    Final Site Grade

  • Phase Completed!  |  Oct 25, 2019 - 11:44am

    Exterior Rough

  • Marked as complete by Jeff  |  Oct 25, 2019 - 11:44am

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Oct 25, 2019 - 11:44am

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Oct 25, 2019 - 11:44am

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Oct 21, 2019 - 3:19pm

    Interior Trim & Doors On Site

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:34am

    Natural Gas Meter Installed

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:02am

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:01am

    Trim Sweep & Haul Scheduled

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:13am

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:13am

    Hardware Installation

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:12am

    Interior Stain & Painting

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:12am

    Cabs Pre-Drilled for Hardware

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:12am

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:11am

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:10am

    Surplus Trim Pick-Up

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:10am

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:07am

    Barn Door Installation Scheduled

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:07am

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:06am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Interior Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Barn Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:05am

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Preliminary Tile Flooring Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Interior Masonry Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Wall Tile Details Notated On Walls

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Garage Door Installation

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Insulation & Sealant Installation Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Interior Masonry Scheduled (Or N/A)

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    2nd Phase Concrete Flooring Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Temporary Construction Heat Coordinated

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Outdoor Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Electrical Final Meter & Service Installed

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Exterior Stone Masonry Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Mailbox Constructed (If Feasible)

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Insulation Inspection Requested & Confirmed by Jeff

  • Marked as complete by Jeff  |  Oct 16, 2019 - 9:04am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Oct 16, 2019 - 8:37am

    Attic Access Installation Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 8:34am

    Garage Door Installation Scheduled

  • Scheduled by Jeff  |  Oct 4, 2019 - 1:49pm

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:49pm

    Cabinet Delivery & Installation Scheduled

  • Scheduled by Jeff  |  Oct 4, 2019 - 1:46pm

    Flatwork Form Setup

  • Scheduled by Jeff  |  Oct 4, 2019 - 1:45pm

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:43pm

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Sep 30, 2019 - 10:39am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Sep 30, 2019 - 10:39am

    Brick On Site

  • Marked as complete by Jeff  |  Sep 20, 2019 - 3:37pm

    Natural Gas Line Installed

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:34am

    Preliminary Tile Flooring Completion

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:28am

    Supplemental Masonry Material On Site

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:27am

    Brick On Site

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:25am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:25am

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:25am

    Exterior Masonry Scheduled

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:25am

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:24am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Sep 12, 2019 - 11:34am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 5, 2019 - 1:07pm

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Sep 5, 2019 - 12:42pm

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  Sep 5, 2019 - 12:42pm

    Natural Gas Line Installation Scheduled

  • Scheduled by Jeff  |  Sep 5, 2019 - 12:30pm

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Sep 5, 2019 - 12:29pm

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Sep 5, 2019 - 12:29pm

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Sep 5, 2019 - 12:29pm

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:56am

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:56am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:56am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:55am

    Natural Gas System Analysis Requested

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:55am

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:55am

    HVAC Rough-In Inspection Passed

  • Scheduled by Jeff  |  Sep 3, 2019 - 6:53am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:53am

    Wall Insulation & Seal Package Scheduled

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:52am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:52am

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Fireplace Installation

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Post-Tension Cables Stressed & Secured

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:51am

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Phase Completed!  |  Sep 3, 2019 - 6:51am

    Pad To Foundation

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:50am

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:50am

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Aug 29, 2019 - 7:01am

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Aug 28, 2019 - 3:45pm

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Aug 27, 2019 - 9:15am

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Aug 25, 2019 - 3:27pm

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Aug 23, 2019 - 7:21am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Aug 19, 2019 - 12:41pm

    Roof Installation

  • Marked as complete by Jeff  |  Aug 16, 2019 - 1:48pm

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Aug 16, 2019 - 1:48pm

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Aug 16, 2019 - 1:48pm

    Framing | Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Aug 16, 2019 - 1:48pm

    Framing | Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  Aug 6, 2019 - 11:01am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Aug 6, 2019 - 11:01am

    Exterior Wall Sheathing Inspection Passed

  • Scheduled by Jeff  |  Aug 5, 2019 - 11:29am

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Aug 5, 2019 - 11:29am

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Aug 5, 2019 - 11:28am

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Aug 5, 2019 - 11:28am

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Aug 5, 2019 - 11:28am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Aug 5, 2019 - 11:27am

    Roof Installation

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Framing | Joist Phase Completion

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Framing | Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Framing Lumber | Decking & Cornice Order

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Framing Lumber | Joist & Rafter Order

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:26am

    Framing Lumber | Wall Pack Order

  • Marked as complete by Jeff  |  Aug 1, 2019 - 8:26am

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  Jul 28, 2019 - 8:42pm

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Jul 28, 2019 - 8:42pm

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Jul 28, 2019 - 8:41pm

    Foundation Form Removal

  • Marked as complete by Jeff  |  Jul 28, 2019 - 8:41pm

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Jul 28, 2019 - 8:41pm

    Foundation Poured

  • Marked as complete by Jeff  |  Jul 24, 2019 - 9:50am

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Jul 24, 2019 - 9:50am

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Jul 24, 2019 - 9:50am

    Framing Plans Distributed to Framing Contractor

  • Phase Completed!  |  Jul 24, 2019 - 9:50am

    Start To Permit

  • Marked as complete by Jeff  |  Jul 19, 2019 - 6:49am

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Jul 19, 2019 - 6:49am

    Termite Pre-Treatment For Foundation

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Site Identification Sign Installed

  • Marked as complete by Jeff  |  Jul 16, 2019 - 11:26am

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Jul 12, 2019 - 10:01am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Jul 11, 2019 - 9:21am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Jul 11, 2019 - 9:21am

    Load of Sand For Plumbers Ordered

  • Marked as complete by Jeff  |  Jul 11, 2019 - 9:21am

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Jul 11, 2019 - 9:21am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jul 11, 2019 - 9:21am

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Jul 8, 2019 - 5:51am

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Jul 5, 2019 - 8:20am

    Issuance Of Building Permit

  • Posted by Jeff Click  |  Jul 5, 2019 - 8:20am
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Jul 5, 2019 - 8:20am

    Plans & Application Submitted for Permits

  • Scheduled by Jeff  |  Jul 1, 2019 - 12:03pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:55am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:55am

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:54am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:54am

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:54am

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:54am

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:54am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:54am

    Foundation Engineering Complete

  • Posted by Jeff Click  |  Jun 17, 2019 - 8:06am
    Your Design Notes
    It's Time To Design!
    We're at the point when it's time to start thinking in greater detail about your new home! Design Session 1 is upon us, which involves exterior finish selections, electrical and tech layout, flooring diagram, and more preliminary design decisions. Don't sweat these decisions! I'm here to guide you through making fantastic choices.

    Design sessions need to be scheduled during business hours, as often we need to walk a few doors down to look at materials from suppliers, or make phone calls to check on availability that other decisions depend on. DS1 can often be fully completed over a lunch hour meeting if that helps fit into your schedule better (it usually takes 1-2 hours, max).

    What are some days and times in the next 2 weeks that you have available? I'm looking forward to our next time together!

    | jC
  • Marked as complete by Jeff  |  Jun 17, 2019 - 8:06am

    DS1 Scheduled

  • Scheduled by Jeff  |  Jun 13, 2019 - 3:39pm

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:39pm

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:37pm

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:34pm

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:34pm

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Final Design Notes Created

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Framing Engineering & Material Take-Off Requested

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Final Project Data Updated in CB

  • Posted by Jeff Click  |  Jun 13, 2019 - 3:33pm
    Check, Check, Build!
    The Plans Are Now Official
    Good news! The revised set of plans have been returned by the CAD Draftsman. I have personally cross-checked the new set of plans with our notes from the Plan Review Meeting Check-List, and all of our discussed modifications have been made to satisfaction.

    This means that the plans are now considered "official", and final. These plans are now passed on for foundation engineering, lumber/structural engineering, and window ordering.

    Lots of site progress to follow!

    | jC
  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Final Plan Revisions JCH-Verified

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:33pm

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:32pm

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Jun 11, 2019 - 9:45am

    Pad Site Grading

  • New task added by Jonathan  |  May 15, 2019 - 3:57pm

    test message logging

  • New task added by Jonathan  |  May 10, 2019 - 2:37pm

    double-checking email delivery

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Builder Trim, Paint, & Detail Walk-Through