Progress feed:
7225 NW 146th
← Back to Home Details
  • Posted by Jeff Click  |  Feb 8, 2021 - 4:53pm
    Winter Weather & What To Do
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • Marked as complete by Jeff  |  Mar 2, 2020 - 2:16pm

    Pre-Closing Walk-Through Punch Items Completed

  • Marked as complete by Jeff  |  Feb 21, 2020 - 10:57am

    Pre-closing Walk & Client Orientation

  • Phase Completed!  |  Feb 21, 2020 - 10:57am

    Punch To Closed

  • Marked as complete by Jeff  |  Feb 21, 2020 - 10:57am

    Pre-closing Walk & Client Orientation

  • Marked as complete by Jeff  |  Feb 21, 2020 - 10:57am

    Remaining Pre-Closing Walkthrough Items Assigned In Warranty Phase

  • Marked as complete by Jeff  |  Feb 21, 2020 - 10:57am

    Closing-Day Final Paint Touch-Up

  • Marked as complete by Jeff  |  Feb 21, 2020 - 10:57am

    Closing Day Pre-Closing Orientation With Client

  • Marked as complete by Jeff  |  Feb 21, 2020 - 10:57am

    Preliminary Detail Clean

  • Phase Completed!  |  Feb 21, 2020 - 10:57am

    Paint To Finalled

  • Marked as complete by Jeff  |  Jan 25, 2020 - 3:22pm

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  Jan 25, 2020 - 3:22pm

    Carpet Installation

  • Marked as complete by Jeff  |  Dec 18, 2019 - 11:05am

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  Dec 18, 2019 - 11:05am

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  Dec 18, 2019 - 11:05am

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Marked as complete by Jeff  |  Dec 18, 2019 - 11:05am

    Certificate of Occupancy Issued

  • Marked as complete by Jeff  |  Dec 18, 2019 - 11:05am

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Dec 18, 2019 - 11:04am

    Carpet Installation

  • Marked as complete by Jeff  |  Dec 17, 2019 - 3:13pm

    Final-Final Clean

  • Scheduled by Jeff  |  Dec 13, 2019 - 9:11am

    Final-Final Clean

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Paint Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Drywall Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Tech & Media Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Cosmetic Surface Repair Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Solid Surface Counter Top Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Masonry Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Flooring Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Electrical Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Plumbing Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Trim & Hardware Punch List

  • Marked as complete by Jeff  |  Dec 13, 2019 - 8:51am

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  Dec 9, 2019 - 3:55pm

    Concrete Flooring Final

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:41pm

    Drywall Punch List

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:41pm

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:41pm

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:41pm

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:41pm

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:37pm

    Glass & Mirror Punch List

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:37pm

    HVAC Punch List

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:37pm

    Permanent Keys Delivery & Secure Storage

  • Marked as complete by Jeff  |  Dec 6, 2019 - 2:37pm

    Termite Certificate & Guarantee Received & Filed

  • Phase Completed!  |  Dec 6, 2019 - 2:37pm

    Exterior Detail

  • Marked as complete by Jeff  |  Dec 6, 2019 - 8:38am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Dec 5, 2019 - 10:08am

    Zoning Final Inspection

  • Marked as complete by Jeff  |  Dec 5, 2019 - 10:08am

    Building Final Inspection

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Barn Door(s) Installation

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Outdoor Hand Railing Installed (or N/A

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Address Panel Installed

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Fence Panel Installation (or N/A)

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Post-Installation Sod Manual Watering Scheduled

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Irrigation System Programming & Activation (or N/A)

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Sod Installation

  • Marked as complete by Jeff  |  Dec 3, 2019 - 11:00am

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Dec 3, 2019 - 10:59am

    Irrigation System Installation (or N/A)

  • Marked as complete by Jeff  |  Dec 3, 2019 - 10:59am

    Specialty Outdoor Feature Installation (or N/A)

  • Marked as complete by Jeff  |  Dec 3, 2019 - 10:59am

    Fence Post Installation (or N/A)

  • Marked as complete by Jeff  |  Dec 3, 2019 - 10:59am

    Sandy Loam Load Delivery

  • Marked as complete by Jeff  |  Dec 3, 2019 - 10:59am

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Dec 3, 2019 - 10:59am

    Exterior Wood Column Installation

  • Marked as complete by Jeff  |  Dec 3, 2019 - 10:59am

    Curb & Form Haul

  • Marked as complete by Jeff  |  Dec 2, 2019 - 3:52pm

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Dec 2, 2019 - 2:56pm

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Nov 26, 2019 - 4:20pm

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Nov 26, 2019 - 4:20pm

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Nov 26, 2019 - 4:20pm

    Window Screen Installation

  • Marked as complete by Jeff  |  Nov 26, 2019 - 4:20pm

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Nov 26, 2019 - 12:47pm

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Nov 14, 2019 - 11:00am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Nov 14, 2019 - 9:14am

    Final Site Grade

  • Marked as complete by Jeff  |  Nov 14, 2019 - 9:14am

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Nov 9, 2019 - 12:09pm

    Preliminary Detail Clean

  • Scheduled by Jeff  |  Nov 8, 2019 - 12:57pm

    Window Screen Installation

  • Scheduled by Jeff  |  Nov 8, 2019 - 12:57pm

    Window & Exterior Door Punch List

  • Scheduled by Jeff  |  Nov 8, 2019 - 12:54pm

    Cabinet Final & Adjustments

  • Posted by Jeff Click  |  Nov 8, 2019 - 9:41am
    Black Friday Sale
    Black Friday For Your House & Family Vacation
    I wanted to bring this opportunity to your attention, as my appliance supplier (Known both as Hahn Appliances *and* Metro Appliances & More...same company) is having a 10% clearance on 11/14. This could be a good opportunity to grab a nice refrigerator, washer & dryer, or anything else you have on your wish list for the new pad.

    If you don't take advantage of this sale, remember I can always get you my wholesale pricing on those items at any other time, which would include delivery and installation. Feel free to hit me up with any model numbers of items you'd like quotes on.

    Also, I wanted to let you know in advance that I will be out for the week of the 18th-22nd for an overdue family getaway. I always leave with appropriate project progress scheduled to take place where possible, and I do have assistance in getting eyes on the jobs on site. I can also check-in via my remote site cameras to monitor progress. Note that I do build in cushion into construction schedules to allow a margin for things like this, weather, and holidays. Nonetheless, I wanted to make you aware of it in case you reached out to me and didn't hear back in my usual response window.

    Have a great weekend!

    | jC
  • Scheduled by Jeff  |  Nov 7, 2019 - 9:31am

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Nov 5, 2019 - 11:08am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Nov 5, 2019 - 11:07am

    Fireplace Final Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:10pm

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Nov 4, 2019 - 3:10pm

    Appliance Package Delivery

  • Marked as complete by Jeff  |  Nov 4, 2019 - 12:36pm

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Nov 1, 2019 - 3:52pm

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Nov 1, 2019 - 3:50pm

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Nov 1, 2019 - 3:50pm

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Nov 1, 2019 - 3:50pm

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  Nov 1, 2019 - 3:50pm

    Hardware Installation

  • Marked as complete by Jeff  |  Nov 1, 2019 - 3:50pm

    Interior Stain & Painting

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:33pm

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:33pm

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:32pm

    Fireplace Final Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:32pm

    Plumbing Final Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:31pm

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:30pm

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:30pm

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:29pm

    Appliance Package Delivery

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:29pm

    Lighting Fixture Package Delivery

  • Scheduled by Jeff  |  Oct 25, 2019 - 12:15pm

    Final Site Grade

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:04pm

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:04pm

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:04pm

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:04pm

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Oct 25, 2019 - 12:04pm

    Flatwork Pour

  • Scheduled by Jeff  |  Oct 23, 2019 - 9:23am

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Oct 23, 2019 - 9:20am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Oct 23, 2019 - 9:18am

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Oct 23, 2019 - 9:18am

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Oct 23, 2019 - 9:18am

    Pre-Flatwork Conduit Sleeving

  • Marked as complete by Jeff  |  Oct 23, 2019 - 9:18am

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Oct 23, 2019 - 9:18am

    Laminate Counter Top Templating

  • Phase Completed!  |  Oct 23, 2019 - 9:18am

    Insulation To Trim

  • Marked as complete by Jeff  |  Oct 23, 2019 - 9:18am

    Temporary Exterior Door Hardware Installation

  • Phase Completed!  |  Oct 23, 2019 - 9:18am

    Exterior Rough

  • Marked as complete by Jeff  |  Oct 22, 2019 - 4:37pm

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Oct 18, 2019 - 11:03am

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Oct 18, 2019 - 11:03am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Oct 18, 2019 - 11:03am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Oct 18, 2019 - 11:03am

    Cabs Pre-Drilled for Hardware

  • Scheduled by Jeff  |  Oct 16, 2019 - 12:44pm

    Cabs Pre-Drilled for Hardware

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:41am

    Natural Gas Meter Installed

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Interior Hand Railing Takeoff (Or N/A)

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Barn Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:09am

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:08am

    Temporary Construction Heat Coordinated

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:08am

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:08am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:08am

    Electrical Final Meter & Service Installed

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:08am

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2019 - 11:08am

    Natural Gas Meter Installation Scheduled

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:08am

    Barn Door Installation Scheduled

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:07am

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:05am

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:05am

    Interior Stain & Painting

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:04am

    Hardware Installation

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:00am

    Surplus Trim Pick-Up

  • Scheduled by Jeff  |  Oct 16, 2019 - 11:00am

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Oct 16, 2019 - 10:57am

    Solid Surface Counter Top Templating

  • Scheduled by Jeff  |  Oct 16, 2019 - 9:14am

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Oct 14, 2019 - 9:54am

    Preliminary Tile Flooring Completion

  • Marked as complete by Jeff  |  Oct 7, 2019 - 8:47am

    Concrete Flooring Work Complete

  • Scheduled by Jeff  |  Oct 4, 2019 - 1:46pm

    Concrete Flooring Work Complete

  • Scheduled by Jeff  |  Oct 4, 2019 - 1:45pm

    Flatwork Form Setup

  • Scheduled by Jeff  |  Oct 4, 2019 - 1:44pm

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:43pm

    Flatwork Sand Ordered

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:43pm

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:42pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Wall Tile Details Notated On Walls

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:41pm

    Mailbox Constructed (If Feasible)

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:40pm

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 4, 2019 - 1:40pm

    Water Meter Installed & Back-filled

  • Phase Completed!  |  Oct 4, 2019 - 1:40pm

    Frame To Inspections

  • Marked as complete by Jeff  |  Sep 30, 2019 - 10:39am

    Garage Door Installation

  • Marked as complete by Jeff  |  Sep 27, 2019 - 12:45pm

    2nd Phase Concrete Flooring Scheduled

  • Scheduled by Jeff  |  Sep 25, 2019 - 2:40pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Sep 25, 2019 - 2:39pm

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Sep 23, 2019 - 8:54am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Sep 23, 2019 - 8:54am

    Brick On Site

  • Marked as complete by Jeff  |  Sep 20, 2019 - 3:37pm

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Sep 20, 2019 - 3:37pm

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Sep 20, 2019 - 3:37pm

    Garage Door Installation

  • Scheduled by Jeff  |  Sep 18, 2019 - 9:13am

    2nd Phase Concrete Flooring Scheduled

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:33am

    Preliminary Tile Flooring Completion

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:32am

    Garage Door Installation

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:30am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:30am

    Insulation & Sealant Installation Completion

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:30am

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:30am

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:30am

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:29am

    Attic Access Installation Scheduled

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:29am

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:29am

    Wall Insulation Installation

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:22am

    Masonry Sand On Site

  • Scheduled by Jeff  |  Sep 16, 2019 - 8:21am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:20am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:20am

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:18am

    Exterior Masonry Scheduled

  • Marked as complete by Jeff  |  Sep 16, 2019 - 8:18am

    Insulation Inspection Requested & Confirmed by Jeff

  • Scheduled by Jeff  |  Sep 11, 2019 - 10:31am

    Wall Insulation Installation

  • Marked as complete by Jeff  |  Sep 10, 2019 - 10:07am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 10, 2019 - 10:07am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Sep 10, 2019 - 10:06am

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  Sep 5, 2019 - 3:53pm

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Sep 5, 2019 - 12:22pm

    Cabinet Take-Off & Design Review

  • Scheduled by Jeff  |  Sep 5, 2019 - 11:48am

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Sep 5, 2019 - 9:11am

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:54am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:54am

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:53am

    Natural Gas System Analysis Requested

  • Marked as complete by Jeff  |  Sep 4, 2019 - 6:53am

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 3, 2019 - 6:57am

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:46pm

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:45pm

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:45pm

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:44pm

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:44pm

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:44pm

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:44pm

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Aug 29, 2019 - 1:44pm

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Aug 29, 2019 - 7:03am

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:58am

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:58am

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:58am

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:58am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:58am

    Wall Insulation & Seal Package Scheduled

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:58am

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:58am

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:57am

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Aug 29, 2019 - 6:56am

    Fireplace Installation

  • Marked as complete by Jeff  |  Aug 28, 2019 - 3:41pm

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Aug 27, 2019 - 9:15am

    Drywall Material On Site

  • Scheduled by Jeff  |  Aug 27, 2019 - 7:16am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Aug 27, 2019 - 7:16am

    Post-Tension Cables Stressed & Secured

  • Marked as complete by Jeff  |  Aug 27, 2019 - 7:15am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Aug 27, 2019 - 7:15am

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Aug 27, 2019 - 7:15am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Aug 27, 2019 - 7:15am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Aug 27, 2019 - 7:15am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Aug 23, 2019 - 7:21am

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Aug 16, 2019 - 1:50pm

    Drywall Material On Site

  • Marked as complete by Jeff  |  Aug 16, 2019 - 1:50pm

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Aug 15, 2019 - 12:22pm

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Aug 13, 2019 - 7:10am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Aug 13, 2019 - 7:10am

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:32am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:31am

    Roof Installation

  • Marked as complete by Jeff  |  Aug 5, 2019 - 11:31am

    Framing | Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:48am

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:48am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Jul 31, 2019 - 6:48am

    Framing | Rafter & Decking Phase Completion

  • Scheduled by Jeff  |  Jul 29, 2019 - 6:34am

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Jul 29, 2019 - 6:34am

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Jul 29, 2019 - 6:33am

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Jul 29, 2019 - 6:33am

    Fireplace Installation

  • Scheduled by Jeff  |  Jul 29, 2019 - 6:32am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Jul 29, 2019 - 6:32am

    Roof Installation

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:31am

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:31am

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:31am

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:31am

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:31am

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:31am

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Framing | Joist Phase Completion

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Framing | Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Framing Lumber | Decking & Cornice Order

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Framing Lumber | Joist & Rafter Order

  • Marked as complete by Jeff  |  Jul 29, 2019 - 6:30am

    Framing Lumber | Wall Pack Order

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Framing Plans Distributed to Framing Contractor

  • Phase Completed!  |  Jul 18, 2019 - 6:32am

    Pad To Foundation

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Jul 18, 2019 - 6:32am

    Foundation Form Removal

  • Marked as complete by Jeff  |  Jul 15, 2019 - 4:15pm

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Jul 15, 2019 - 4:14pm

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Jul 15, 2019 - 4:14pm

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Jul 15, 2019 - 4:14pm

    Foundation Poured

  • Marked as complete by Jeff  |  Jul 15, 2019 - 4:14pm

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Jul 8, 2019 - 6:07am

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Jul 8, 2019 - 6:07am

    Termite Pre-Treatment For Foundation

  • Marked as complete by Jeff  |  Jul 8, 2019 - 6:07am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Jul 8, 2019 - 5:51am

    Ground Electrical Installed

  • Scheduled by Jeff  |  Jul 1, 2019 - 12:03pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Jul 1, 2019 - 12:02pm

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Jul 1, 2019 - 12:02pm

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Jul 1, 2019 - 12:01pm

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Jul 1, 2019 - 12:01pm

    Load of Sand For Plumbers Ordered

  • Marked as complete by Jeff  |  Jul 1, 2019 - 12:01pm

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:54am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:53am

    Framing Engineering & Material Take-Off Received

  • Phase Completed!  |  Jun 19, 2019 - 5:53am

    Start To Permit

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:52am

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Jun 19, 2019 - 5:52am

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:31pm

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:30pm

    Site Identification Sign Installed

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:30pm

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Jun 13, 2019 - 3:30pm

    Pricing Updated From Pre-Con

  • Scheduled by Jeff  |  Jun 11, 2019 - 9:39am

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Jun 11, 2019 - 9:38am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Jun 11, 2019 - 9:38am

    Pad Site Grading

  • Marked as complete by Jeff  |  Jun 11, 2019 - 9:38am

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Jun 11, 2019 - 9:37am

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Jun 11, 2019 - 9:37am

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Jun 11, 2019 - 9:37am

    Final Design Notes Created

  • Posted by Jeff Click  |  Jun 11, 2019 - 6:06am
    Your Design Notes
    It's Time To Design!
    We're at the point when it's time to start thinking in greater detail about your new home! Design Session 1 is upon us, which involves exterior finish selections, electrical and tech layout, flooring diagram, and more preliminary design decisions. Don't sweat these decisions! I'm here to guide you through making fantastic choices.

    Design sessions need to be scheduled during business hours, as often we need to walk a few doors down to look at materials from suppliers, or make phone calls to check on availability that other decisions depend on. DS1 can often be fully completed over a lunch hour meeting if that helps fit into your schedule better (it usually takes 1-2 hours, max).

    What are some days and times in the next 2 weeks that you have available? I'm looking forward to our next time together!

    | jC
  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:06am

    DS1 Scheduled

  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:06am

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:06am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:06am

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:06am

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:06am

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Jun 11, 2019 - 6:06am

    Framing Engineering & Material Take-Off Requested

  • Marked as complete by Jeff  |  Jun 10, 2019 - 4:10pm

    Final Project Data Updated in CB

  • Posted by Jeff Click  |  Jun 10, 2019 - 4:10pm
    Check, Check, Build!
    The Plans Are Now Official
    Good news! The revised set of plans have been returned by the CAD Draftsman. I have personally cross-checked the new set of plans with our notes from the Plan Review Meeting Check-List, and all of our discussed modifications have been made to satisfaction.

    This means that the plans are now considered "official", and final. These plans are now passed on for foundation engineering, lumber/structural engineering, and window ordering.

    Lots of site progress to follow!

    | jC
  • Marked as complete by Jeff  |  Jun 10, 2019 - 4:10pm

    Final Plan Revisions JCH-Verified

  • Marked as complete by Jeff  |  Jun 10, 2019 - 4:08pm

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Jun 10, 2019 - 4:08pm

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Jun 4, 2019 - 7:12am

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Jun 4, 2019 - 7:12am

    Final Plan Revisions Submitted To Draftsman

  • Posted by Jeff Click  |  May 24, 2019 - 6:37am
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  May 24, 2019 - 6:37am

    Plans & Application Submitted for Permits

  • Marked as complete by Jeff  |  May 24, 2019 - 6:37am

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  May 24, 2019 - 6:20am

    Foundation Engineering Complete

  • Scheduled by Jeff  |  May 20, 2019 - 1:52pm

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  May 20, 2019 - 1:52pm

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  May 16, 2019 - 6:04am

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  May 16, 2019 - 6:04am

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  May 16, 2019 - 6:04am

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  May 16, 2019 - 6:04am

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  May 16, 2019 - 6:04am

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  May 16, 2019 - 6:04am

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  May 16, 2019 - 6:04am

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  May 15, 2019 - 8:16am

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  May 15, 2019 - 8:16am

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Garage Door Installation

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Pre-closing Walk & Client Orientation