  • New task added by Jeff  |  Aug 27, 2020 - 8:15am

    Final Trim Warranty Items

  • Marked as complete by Jeff  |  Aug 21, 2020 - 12:07pm

    Front Door Handleset Lever Defective

  • Marked as complete by Jeff  |  Jul 21, 2020 - 12:35pm

    Hall Bath Toilet Not Secure

  • New task added by Jeff  |  Jul 21, 2020 - 10:22am

    Table Not Secure To Island & Towel Bars Need Securing

  • New task added by Jeff  |  Jul 21, 2020 - 10:18am

    Hall Bath Toilet Not Secure

  • New task added by Jeff  |  Jul 21, 2020 - 10:16am

    Loose Laminated Edges

  • New task added by Jeff  |  Jul 21, 2020 - 10:14am

    Front Door Handleset Lever Defectcive

  • Marked as complete by Jeff  |  Dec 19, 2019 - 2:13pm

    Provide & Program 2 Replacement Opener Remotes

  • Posted by Jeff Click  |  Nov 11, 2019 - 8:59am
    This week's forecast as of Monday morning.
    Winter Advisory
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • New task added by Jeff  |  Nov 8, 2019 - 9:39am

    Provide & Program 2 Replacement Opener Remotes

  • Marked as complete by Jeff  |  Sep 6, 2019 - 9:53am

    Need Hardware for Cabana Mech Closet

  • Marked as complete by Jeff  |  Sep 5, 2019 - 10:36am

    Epoxy Bubbling Badly at Sink Drains

  • New task added by Jeff  |  Aug 14, 2019 - 3:55pm

    Need Hardware for Cabana Mech Closet

  • New task added by Jeff  |  Aug 14, 2019 - 3:55pm

    Need Hardware for Cabana Mech Closet

  • New task added by Jeff  |  Aug 9, 2019 - 6:56am

    Epoxy Bubbling Badly at Sink Drains

  • Marked as complete by Jeff  |  Jul 11, 2019 - 9:09am

    Sod Installation

  • New task added by Jeff  |  Jun 27, 2019 - 9:37am

    Load of Sandy Loam On Site

  • Marked as complete by Jeff  |  Jun 14, 2019 - 10:08am

    Swap Master Shower Valve For Correct Spec

  • Marked as complete by Jeff  |  Jun 14, 2019 - 7:02am

    Address Butler's Pantry Electric

  • Marked as complete by Jeff  |  Jun 14, 2019 - 7:02am

    Irrigation System Installation

  • New task added by Jeff  |  Jun 8, 2019 - 8:53am

    Address Butler's Pantry Electric

  • New task added by Jeff  |  Jun 4, 2019 - 9:22am

    Swap Master Shower Valve For Correct Spec

  • Marked as complete by Jeff  |  May 29, 2019 - 3:14pm

    Pre-Closing Walk-Through Punch Items Completed

  • New task added by Jeff  |  May 28, 2019 - 5:59am

    Irrigation System Installation

  • Marked as complete by Jeff  |  May 24, 2019 - 11:22am

    Remaining Pre-Closing Walkthrough Items Assigned In Warranty Phase

  • Marked as complete by Jeff  |  May 24, 2019 - 11:22am

    Closing-Day Final Paint Touch-Up

  • Marked as complete by Jeff  |  May 24, 2019 - 11:22am

    Closing Day Pre-Closing Orientation With Client

  • Marked as complete by Jeff  |  May 24, 2019 - 11:22am

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  May 24, 2019 - 11:22am

    Flooring Punch List

  • Marked as complete by Jeff  |  May 21, 2019 - 7:46pm

    Final-Final Clean

  • Marked as complete by Jeff  |  May 21, 2019 - 7:46pm

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Marked as complete by Jeff  |  May 21, 2019 - 7:46pm

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  May 21, 2019 - 7:46pm

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  May 21, 2019 - 7:46pm

    Glass & Mirror Punch List

  • Marked as complete by Jeff  |  May 20, 2019 - 1:32pm

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  May 20, 2019 - 1:32pm

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  May 20, 2019 - 1:32pm

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  May 20, 2019 - 5:49am

    Stained Concrete Final

  • Marked as complete by Jeff  |  May 17, 2019 - 1:48pm

    Certificate of Occupancy Issued

  • Marked as complete by Jeff  |  May 17, 2019 - 1:48pm

    Zoning Final Inspection

  • Posted by Jeff Click  |  May 17, 2019 - 11:01am
    Such a rich palette.
    Your Friday-Before-Closing Look-Book
    This combo is 🔥🔥🔥! This time next week it will be YOURS.

  • Marked as complete by Jeff  |  May 17, 2019 - 6:24am

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  May 17, 2019 - 6:24am

    Exterior Door Weather Stripping & Threshold Adjustment

  • Marked as complete by Jeff  |  May 16, 2019 - 6:30pm

    Building Final Inspection

  • Marked as complete by Jeff  |  May 16, 2019 - 6:30pm

    Paint Punch List

  • Marked as complete by Jeff  |  May 16, 2019 - 6:30pm

    Trim & Hardware Punch List

  • Marked as complete by Jeff  |  May 16, 2019 - 6:29pm

    Cabinetry Punch List

  • Scheduled by Jeff  |  May 15, 2019 - 2:21pm

    Sod Installation

  • Marked as complete by Jeff  |  May 15, 2019 - 2:21pm

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  May 15, 2019 - 2:21pm

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  May 15, 2019 - 2:20pm

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  May 15, 2019 - 5:52am

    Window & Exterior Door Punch List

  • Scheduled by Jeff  |  May 14, 2019 - 2:42pm

    Final-Final Clean

  • Marked as complete by Jeff  |  May 14, 2019 - 8:22am

    Tech & Media Punch List

  • Marked as complete by Jeff  |  May 14, 2019 - 8:22am

    HVAC Punch List

  • Marked as complete by Jeff  |  May 14, 2019 - 8:22am

    Cosmetic Surface Repair Punch List

  • Scheduled by Jeff  |  May 14, 2019 - 8:21am

    Flooring Punch List

  • Scheduled by Jeff  |  May 14, 2019 - 6:14am

    Stained Concrete Final

  • Scheduled by Jeff  |  May 14, 2019 - 6:13am

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  May 14, 2019 - 6:12am

    Plumbing Punch List

  • Marked as complete by Jeff  |  May 14, 2019 - 6:12am

    Electrical Punch List

  • Marked as complete by Jeff  |  May 14, 2019 - 6:12am

    Masonry Punch List

  • Marked as complete by Jeff  |  May 14, 2019 - 6:11am

    Electrical Final Inspection

  • Marked as complete by Jeff  |  May 14, 2019 - 6:11am

    HVAC Final Inspection

  • Marked as complete by Jeff  |  May 14, 2019 - 6:10am

    Electrical Final Inspection

  • Marked as complete by Jeff  |  May 14, 2019 - 6:09am

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  May 14, 2019 - 6:09am

    Carpet Installation

  • Marked as complete by Jeff  |  May 14, 2019 - 6:08am

    Pre-closing Walk & Client Orientation

  • Phase Completed!  |  May 14, 2019 - 6:08am

    Paint To Finalled

  • Marked as complete by Jeff  |  May 14, 2019 - 6:08am

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  May 14, 2019 - 6:08am

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  May 13, 2019 - 11:35am

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  May 13, 2019 - 11:35am

    Address Panel Installed

  • Scheduled by Jeff  |  May 13, 2019 - 11:34am

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  May 13, 2019 - 5:39am

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  May 13, 2019 - 5:39am

    Carpet Installation

  • Marked as complete by Jeff  |  May 10, 2019 - 11:42am

    Window Screen Installation

  • Marked as complete by Jeff  |  May 10, 2019 - 6:21am

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  May 10, 2019 - 6:21am

    Landscape Bed Installation

  • Marked as complete by Jeff  |  May 9, 2019 - 6:53am

    Permanent Keys Delivery & Secure Storage

  • Marked as complete by Jeff  |  May 9, 2019 - 6:51am

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  May 9, 2019 - 6:51am

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  May 9, 2019 - 6:50am

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  May 9, 2019 - 6:50am

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  May 9, 2019 - 6:50am

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  May 9, 2019 - 6:50am

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  May 9, 2019 - 6:50am

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  May 9, 2019 - 6:50am

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  May 9, 2019 - 6:50am

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  May 9, 2019 - 6:48am

    Plumbing Final Installation

  • Marked as complete by Jeff  |  May 9, 2019 - 6:45am

    Drywall Punch List

  • Marked as complete by Jeff  |  May 9, 2019 - 6:45am

    Attic Insulation Installation

  • Marked as complete by Jeff  |  May 9, 2019 - 6:45am

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  May 9, 2019 - 6:45am

    Plumbing Final Installation

  • Marked as complete by Jeff  |  May 9, 2019 - 6:44am

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  May 6, 2019 - 4:05pm

    Fireplace Final Installation

  • Marked as complete by Jeff  |  May 6, 2019 - 5:46am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  May 6, 2019 - 5:45am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  May 6, 2019 - 5:45am

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  May 3, 2019 - 6:34am

    Hand Railing & Banister Installation

  • Scheduled by Jeff  |  May 2, 2019 - 12:24pm

    Drywall Punch List

  • Marked as complete by Jeff  |  May 2, 2019 - 12:19pm

    Solid Surface Counter Top Punch List

  • Marked as complete by Jeff  |  May 2, 2019 - 12:19pm

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  May 2, 2019 - 12:18pm

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  May 2, 2019 - 12:18pm

    Hardware Installation

  • Marked as complete by Jeff  |  May 1, 2019 - 5:53am

    Appliance Package Delivery

  • Marked as complete by Jeff  |  May 1, 2019 - 5:53am

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Apr 29, 2019 - 5:13pm

    Final Site Debris Clean-Up

  • Scheduled by Jeff  |  Apr 29, 2019 - 5:12pm

    Hand Railing & Banister Installation

  • Scheduled by Jeff  |  Apr 29, 2019 - 5:11pm

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Apr 29, 2019 - 5:06pm

    Hardwood Flooring Installation

  • Marked as complete by Jeff  |  Apr 29, 2019 - 5:05pm

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Apr 29, 2019 - 5:04pm

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Apr 27, 2019 - 7:43pm

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Apr 27, 2019 - 7:42pm

    Concrete Counter Top Installation

  • Marked as complete by Jeff  |  Apr 25, 2019 - 12:57pm

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Apr 24, 2019 - 6:31am

    Preliminary Detail Clean

  • Scheduled by Jeff  |  Apr 24, 2019 - 6:31am

    Carpet Installation

  • Scheduled by Jeff  |  Apr 24, 2019 - 6:29am

    Hardware Installation

  • Scheduled by Jeff  |  Apr 24, 2019 - 6:26am

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Apr 24, 2019 - 6:23am

    Window Screen Installation

  • Marked as complete by Jeff  |  Apr 24, 2019 - 6:19am

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Apr 24, 2019 - 6:19am

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Apr 24, 2019 - 6:19am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Apr 24, 2019 - 6:18am

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Apr 24, 2019 - 6:18am

    Exterior Cornice & Trim Painting

  • Scheduled by Jeff  |  Apr 24, 2019 - 6:10am

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Apr 19, 2019 - 6:55am

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Apr 19, 2019 - 6:54am

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Apr 19, 2019 - 6:53am

    Attic Insulation Installation

  • Scheduled by Jeff  |  Apr 19, 2019 - 6:52am

    Fireplace Final Installation

  • Scheduled by Jeff  |  Apr 19, 2019 - 6:52am

    Kitchen Vent Hood Installation

  • Scheduled by Jeff  |  Apr 15, 2019 - 11:55am

    Appliance Package Delivery

  • Scheduled by Jeff  |  Apr 15, 2019 - 11:54am

    Heat, Ventilation, & Air Conditioning Final Installation

  • Scheduled by Jeff  |  Apr 15, 2019 - 11:53am

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Apr 15, 2019 - 11:44am

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Apr 15, 2019 - 11:44am

    Laminate Counter Top Installation

  • Scheduled by Jeff  |  Apr 15, 2019 - 11:43am

    Surplus Trim Pick-Up

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Mirror & Glass Templated

  • Phase Completed!  |  Apr 15, 2019 - 11:41am

    Insulation To Trim

  • Marked as complete by Jeff  |  Apr 15, 2019 - 11:41am

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Apr 13, 2019 - 2:19pm

    Seamless Guttering Installation

  • Scheduled by Jeff  |  Apr 13, 2019 - 2:17pm

    Exterior Cornice & Trim Painting

  • Scheduled by Jeff  |  Apr 13, 2019 - 2:16pm

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Apr 13, 2019 - 2:14pm

    Concrete Counter Top Installation

  • Marked as complete by Jeff  |  Apr 13, 2019 - 2:13pm

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Apr 13, 2019 - 2:12pm

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Apr 13, 2019 - 2:11pm

    Concrete Counter Top Templating

  • Marked as complete by Jeff  |  Apr 13, 2019 - 2:11pm

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Apr 13, 2019 - 2:11pm

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Phase Completed!  |  Apr 13, 2019 - 2:11pm

    Exterior Rough

  • Marked as complete by Jeff  |  Apr 13, 2019 - 2:11pm

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Apr 10, 2019 - 5:07pm

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Apr 10, 2019 - 5:58am

    Trim Sweep & Haul Scheduled

  • Marked as complete by Jeff  |  Apr 10, 2019 - 5:58am

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Apr 9, 2019 - 6:11am

    Final Site Grade

  • Marked as complete by Jeff  |  Apr 9, 2019 - 6:11am

    Curb & Form Haul

  • Marked as complete by Jeff  |  Apr 9, 2019 - 6:11am

    Flatwork Form Removal

  • Scheduled by Jeff  |  Apr 8, 2019 - 11:29am

    Plumbing Final Installation

  • Posted by Jeff Click  |  Apr 8, 2019 - 11:23am
    Hex Wall
    The Monday Hex


    LOVING how this master bathroom is shaping up!!!

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:30am

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:29am

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:29am

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:29am

    Flatwork Pour

  • Marked as complete by Jeff  |  Apr 5, 2019 - 6:17am

    Interior Hand Railing Takeoff (Or N/A)

  • Scheduled by Jeff  |  Apr 4, 2019 - 12:48pm

    Solid Surface Counter Top Templating

  • Marked as complete by Jeff  |  Apr 4, 2019 - 12:46pm

    Phase 2 Design Session Scheduled

  • Phase Completed!  |  Apr 4, 2019 - 12:46pm

    Frame To Inspections

  • Marked as complete by Jeff  |  Apr 4, 2019 - 6:34am

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Apr 4, 2019 - 6:34am

    Pre-Flatwork Conduit Sleeving

  • Marked as complete by Jeff  |  Apr 2, 2019 - 5:47pm

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Apr 2, 2019 - 6:08am

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Apr 2, 2019 - 6:08am

    Flatwork Form Setup

  • Scheduled by Jeff  |  Mar 30, 2019 - 2:25pm

    Curb & Form Haul

  • Scheduled by Jeff  |  Mar 30, 2019 - 2:10pm

    Final Site Grade

  • Scheduled by Jeff  |  Mar 30, 2019 - 2:09pm

    Interior Hand Railing Takeoff (Or N/A)

  • Scheduled by Jeff  |  Mar 30, 2019 - 2:00pm

    Cabinet Delivery & Installation

  • Scheduled by Jeff  |  Mar 30, 2019 - 1:59pm

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Mar 30, 2019 - 1:58pm

    Tile & Hardwood Flooring Take-Off & Ordered

  • Marked as complete by Jeff  |  Mar 30, 2019 - 1:58pm

    Preliminary Tile Flooring Completion

  • Marked as complete by Jeff  |  Mar 30, 2019 - 1:58pm

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Mar 30, 2019 - 1:58pm

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Mar 29, 2019 - 9:22am

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Mar 29, 2019 - 9:22am

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Mar 28, 2019 - 2:39pm

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Mar 28, 2019 - 7:33am

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Mar 28, 2019 - 7:32am

    Flatwork Sand On Site

  • Scheduled by Jeff  |  Mar 25, 2019 - 4:59pm

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Mar 25, 2019 - 4:58pm

    Flatwork Sand Ordered

  • Scheduled by Jeff  |  Mar 25, 2019 - 4:54pm

    Masonry Site-Haul Completion

  • Scheduled by Jeff  |  Mar 25, 2019 - 4:53pm

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Mar 25, 2019 - 4:52pm

    Hardscape Design Notes Complete & Posted to CB

  • Marked as complete by Jeff  |  Mar 25, 2019 - 4:46pm

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Mar 25, 2019 - 6:55am

    Interior Masonry Completion

  • Marked as complete by Jeff  |  Mar 21, 2019 - 6:45am

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Mar 21, 2019 - 6:45am

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Mar 21, 2019 - 6:45am

    Natural Gas Line Installed

  • Scheduled by Jeff  |  Mar 19, 2019 - 5:07pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Mar 19, 2019 - 5:06pm

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Mar 19, 2019 - 2:57pm

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Mar 19, 2019 - 2:57pm

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Mar 19, 2019 - 2:46pm

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Mar 19, 2019 - 6:50am

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Mar 19, 2019 - 6:50am

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Mar 19, 2019 - 6:50am

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Mar 19, 2019 - 6:50am

    Electrical Final Meter & Service Installed

  • Scheduled by Jeff  |  Mar 15, 2019 - 1:44pm

    Interior Masonry Completion

  • Marked as complete by Jeff  |  Mar 15, 2019 - 12:31pm

    Wall Tile Details Notated On Walls

  • Marked as complete by Jeff  |  Mar 15, 2019 - 12:31pm

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Mar 14, 2019 - 6:17am

    Garage Door Installation

  • Scheduled by Jeff  |  Mar 13, 2019 - 6:37am

    Preliminary Wall Tile Completion

  • Scheduled by Jeff  |  Mar 13, 2019 - 6:36am

    Preliminary Tile Flooring Completion

  • Scheduled by Jeff  |  Mar 13, 2019 - 6:35am

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Mar 13, 2019 - 6:32am

    Temporary Construction Heat Activated

  • Marked as complete by Jeff  |  Mar 13, 2019 - 6:32am

    Sheetrock Installation Completion

  • Marked as complete by Jeff  |  Mar 13, 2019 - 6:32am

    Preliminary Floor &/or Wall Tile Scheduled

  • Marked as complete by Jeff  |  Mar 13, 2019 - 6:32am

    Concrete Flooring Work Scheduled

  • Scheduled by Jeff  |  Mar 6, 2019 - 3:06pm

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Mar 6, 2019 - 3:04pm

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Mar 6, 2019 - 3:04pm

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Mar 6, 2019 - 3:04pm

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Mar 6, 2019 - 3:04pm

    Attic Access Installation Scheduled

  • Marked as complete by Jeff  |  Mar 6, 2019 - 3:04pm

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Mar 6, 2019 - 3:03pm

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Mar 6, 2019 - 3:03pm

    Lighting Selections Scheduled

  • Posted by Jeff Click  |  Mar 5, 2019 - 12:02pm
    Insulated
    The Pink Panther Has Struck
    "What the heck is he talking about?" you might be wondering. This may be before your time, but there as an old cartoon called the Pink Panther. Owens Corning had a marketing agreement with the cartoon's creators to associate the character with their brand of insulation, which is pink. That's what your home now has installed in it. Once this is inspected, we'll be sheetrocking!

    Brick will continue as soon as OKC thaws out, but we have great weather on the schedule for the rest of the week for some good progress on that front.

    | jC
  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:34am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:34am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:34am

    Insulation Inspection Requested

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:33am

    Insulation Inspection Requested & Confirmed by Jeff

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:33am

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Mar 1, 2019 - 6:33am

    Wall Insulation & Seal Package Completion

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:23am

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:23am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:23am

    Building Rough-In Inspection Passed

  • Scheduled by Jeff  |  Feb 21, 2019 - 8:54am

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Feb 21, 2019 - 8:53am

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:50am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:50am

    Interior Masonry Scheduled (Or N/A)

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:50am

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:49am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:49am

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:48am

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Feb 19, 2019 - 6:48am

    Electrical Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Feb 15, 2019 - 12:23pm

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  Feb 15, 2019 - 12:23pm

    Exterior Masonry Scheduled

  • Marked as complete by Jeff  |  Feb 15, 2019 - 12:23pm

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Feb 15, 2019 - 12:23pm

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Feb 15, 2019 - 12:23pm

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Feb 15, 2019 - 12:22pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Feb 15, 2019 - 11:26am

    Brick On Site

  • Marked as complete by Jeff  |  Feb 15, 2019 - 11:26am

    Drywall Material On Site

  • Posted by Jeff Click  |  Feb 15, 2019 - 10:06am
    Copa Cabana (Reference may be before your time...)
    Friday Morning Update
    Lots of progress on tap for the Morris Home coming up! Final cornice installations took place this week as we await all of our rough inspections...that's 7 different inspections that take place PER structure, so 14 total! Once these are all passed, we'll proceed on the interior with insulation, sheetrock, and secondo phase of polished concrete floors.

    Fortunately we are now cleared to proceed with exterior production, so brick was delivered this morning and as soon as temps allow, masons will get started bricking.

    Rather than hitting you with continued shots of the front of the house, I've changed the view up a bit for you on this one.

    Have a great weekend!

    | jC
  • Scheduled by Jeff  |  Feb 14, 2019 - 7:16am

    Exterior Brick Masonry Completion

  • Scheduled by Jeff  |  Feb 14, 2019 - 7:15am

    Brick On Site

  • Marked as complete by Jeff  |  Feb 14, 2019 - 7:13am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Feb 14, 2019 - 7:13am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Feb 14, 2019 - 7:13am

    Masonry Sand On Site

  • Scheduled by Jeff  |  Feb 14, 2019 - 6:59am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Feb 14, 2019 - 6:54am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Feb 14, 2019 - 6:51am

    Sheetrock & Materials Order Scheduled For Delivery

  • Marked as complete by Jeff  |  Feb 14, 2019 - 6:51am

    Tech & Security Rough-In Completion

  • Marked as complete by Jeff  |  Feb 14, 2019 - 6:50am

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:05pm

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:02pm

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:02pm

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:02pm

    Fireplace Gas Connections Complete & Verified

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:02pm

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:01pm

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:01pm

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:01pm

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Feb 6, 2019 - 4:01pm

    Framing | Accent Panelling Installation

  • Marked as complete by Jeff  |  Feb 6, 2019 - 9:29am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Feb 5, 2019 - 6:37am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Posted by Jeff Click  |  Jan 30, 2019 - 1:04pm
    1.30.19 Status Photo
    Mid-Week Check-In
    Things are looking good on site, now that roof is on, windows are in, and frame debris has been removed and site is clean. Up next: exterior wood installation, brick (when it's warm enough) and electrical wiring. More to come! | jC
  • Marked as complete by Jeff  |  Jan 30, 2019 - 1:01pm

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Jan 30, 2019 - 11:21am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Jan 29, 2019 - 5:50pm

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Jan 29, 2019 - 5:50pm

    Fireplace Installation

  • Marked as complete by Jeff  |  Jan 29, 2019 - 5:50pm

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Jan 29, 2019 - 5:50pm

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Jan 29, 2019 - 5:50pm

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Jan 26, 2019 - 9:09am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Scheduled by Jeff  |  Jan 26, 2019 - 9:08am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Jan 26, 2019 - 9:07am

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Jan 26, 2019 - 9:07am

    Roof Installation

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Framing - Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:20pm

    Phase 2 Design Session Scheduled

  • Phase Completed!  |  Jan 22, 2019 - 12:20pm

    Pad To Foundation

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:19pm

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Jan 22, 2019 - 12:19pm

    Phase 1 Design Session Completed

  • Scheduled by Jeff  |  Jan 17, 2019 - 7:00am

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Jan 17, 2019 - 6:59am

    Electrical Rough-In Completion

  • Scheduled by Jeff  |  Jan 17, 2019 - 6:59am

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Jan 17, 2019 - 6:58am

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Jan 17, 2019 - 6:57am

    Fireplace Installation

  • Scheduled by Jeff  |  Jan 17, 2019 - 6:57am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Jan 17, 2019 - 6:56am

    Roof Installation

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:55am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:54am

    Fireplace Installation Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:54am

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:54am

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:54am

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:54am

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:54am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Jan 17, 2019 - 6:53am

    Framing - Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  Jan 12, 2019 - 1:18pm

    Framing - Joist Phase Completion

  • Marked as complete by Jeff  |  Jan 12, 2019 - 1:18pm

    Framing - Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Jan 12, 2019 - 1:18pm

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Jan 12, 2019 - 1:17pm

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Jan 9, 2019 - 3:58pm

    Preliminary Wall Layout / Frame Started

  • Scheduled by Jeff  |  Dec 27, 2018 - 1:40pm

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Dec 27, 2018 - 1:39pm

    Framing Lumber - Decking & Cornice Order

  • Marked as complete by Jeff  |  Dec 27, 2018 - 1:39pm

    Framing Lumber - Joist & Rafter Order

  • Marked as complete by Jeff  |  Dec 27, 2018 - 1:39pm

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Dec 17, 2018 - 12:29pm

    Foundation Form Removal

  • Marked as complete by Jeff  |  Dec 12, 2018 - 9:34am

    Framing Lumber - Wall Pack Order

  • Marked as complete by Jeff  |  Dec 12, 2018 - 9:34am

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Dec 12, 2018 - 9:34am

    Foundation Poured

  • Scheduled by Jeff  |  Dec 11, 2018 - 3:18pm

    Foundation Poured

  • Marked as complete by Jeff  |  Dec 11, 2018 - 3:17pm

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Dec 11, 2018 - 3:17pm

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Dec 11, 2018 - 3:17pm

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Dec 11, 2018 - 3:17pm

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Dec 11, 2018 - 3:17pm

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Dec 10, 2018 - 9:24am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Dec 6, 2018 - 10:15am

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Dec 3, 2018 - 10:14am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Nov 26, 2018 - 3:37pm

    Ground Plumbing Installed

  • Posted by Jeff Click  |  Nov 20, 2018 - 2:05pm
    Foundation Forms For The House
    Formed Up
    Foundation forms are now complete (though at the time of this photo, they were working on the house part. The cabana is also now formed up.) That means it's time for plumbers to start ground work, which will begin on Wednesday and complete on Friday. After that, a few inspections before the foundation guys come back.

    Progress!

    You guys have a wonderful Thanksgiving. This time next year, you'll be celebrating it in a new house!

    | jC
  • Scheduled by Jeff  |  Nov 19, 2018 - 1:54pm

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:08am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:08am

    Trash Bin Constructed

  • Posted by Jeff Click  |  Nov 12, 2018 - 8:19am
    Your Design Notes
    It's Time To Design!
    We're at the point when it's time to start thinking in greater detail about your new home! Design Session 1 is upon us, which involves exterior finish selections, electrical and tech layout, flooring diagram, and more preliminary design decisions. Don't sweat these decisions! I'm here to guide you through making fantastic choices.

    Design sessions need to be scheduled during business hours, as often we need to walk a few doors down to look at materials from suppliers, or make phone calls to check on availability that other decisions depend on. DS1 can often be fully completed over a lunch hour meeting if that helps fit into your schedule better (it usually takes 1-2 hours, max).

    What are some days and times in the next 2 weeks that you have available? I'm looking forward to our next time together!

    | jC
  • Marked as complete by Jeff  |  Nov 12, 2018 - 8:19am

    Phase 1 Design Session Scheduled

  • Phase Completed!  |  Nov 12, 2018 - 8:19am

    Start To Permit

  • Marked as complete by Jeff  |  Nov 12, 2018 - 8:19am

    Final Design Notes Created

  • Marked as complete by Jeff  |  Nov 12, 2018 - 8:19am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Nov 6, 2018 - 3:35pm

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Nov 6, 2018 - 3:35pm

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Nov 6, 2018 - 3:35pm

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Nov 6, 2018 - 3:34pm

    Foundation Engineering Complete

  • Posted by Jeff Click  |  Nov 6, 2018 - 2:38pm
    Pad Site
    Ground Broken
    Pad site is prepped, and foundation contractor and plumbers scheduled. Progress underway!

    | jC
  • Scheduled by Jeff  |  Nov 6, 2018 - 2:27pm

    Ground Plumbing Installed

  • Scheduled by Jeff  |  Nov 6, 2018 - 2:23pm

    Trash Bin Constructed

  • Scheduled by Jeff  |  Nov 6, 2018 - 2:23pm

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Nov 6, 2018 - 2:19pm

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Nov 6, 2018 - 2:19pm

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Nov 6, 2018 - 2:19pm

    Site Identification Sign Installed

  • Marked as complete by Jeff  |  Nov 2, 2018 - 10:38am

    Pad Site Grading

  • Marked as complete by Jeff  |  Nov 2, 2018 - 10:37am

    Temp Electric Pole Installed

  • Scheduled by Jeff  |  Nov 1, 2018 - 9:59am

    Final Design Notes Created

  • Scheduled by Jeff  |  Nov 1, 2018 - 9:59am

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:58am

    Trash Bin Materials Ordered

  • Scheduled by Jeff  |  Nov 1, 2018 - 9:58am

    Window Take-Off & Bid Received

  • Scheduled by Jeff  |  Nov 1, 2018 - 9:57am

    Foundation Engineering JCH-Verified

  • Scheduled by Jeff  |  Nov 1, 2018 - 9:57am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:54am

    Trash Bin Materials Ordered

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:54am

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:54am

    Closing of Lot & Construction Financing Secured

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:54am

    Property Pins Located On Site

  • Posted by Jeff Click  |  Nov 1, 2018 - 9:54am
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:54am

    Plans & Application Submitted for Permits

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:53am

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:53am

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:53am

    Framing Engineering & Material Take-Off Requested

  • Scheduled by Jeff  |  Nov 1, 2018 - 9:50am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Nov 1, 2018 - 9:48am

    Foundation Engineering Ordered

  • Scheduled by Jeff  |  Oct 30, 2018 - 11:13am

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Oct 30, 2018 - 10:10am

    Final Project Data Updated in CB

  • Scheduled by Jeff  |  Oct 8, 2018 - 10:46am

    Pad Site Grading

  • Marked as complete by Jeff  |  Sep 21, 2018 - 12:00pm

    Final Plan Revisions JCH-Verified

  • Marked as complete by Jeff  |  Sep 21, 2018 - 12:00pm

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Sep 21, 2018 - 12:00pm

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Sep 21, 2018 - 12:00pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Sep 21, 2018 - 12:00pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Sep 21, 2018 - 12:00pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Sep 21, 2018 - 12:00pm

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:01pm

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:01pm

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:01pm

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:01pm

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:01pm

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Aug 31, 2018 - 1:46pm

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Aug 27, 2018 - 4:14pm

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Aug 27, 2018 - 4:14pm

    Construction Financing Budget Submitted to Bank

  • Marked as complete by Jeff  |  Aug 27, 2018 - 4:14pm

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Aug 27, 2018 - 4:14pm

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Aug 27, 2018 - 4:14pm

    Purchase Agreement Pricing Completed

  • Posted by Jeff Click  |  Jul 31, 2018 - 4:37pm
    Your Future Home Site
    Your Future Home Site
  • Marked as complete by Jeff  |  Jul 13, 2018 - 4:22pm

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Solid Surface Counter Top Installation