Progress feed:
7232 NW 146th
← Back to Home Details
  • Posted by Jeff Click  |  Nov 11, 2019 - 8:59am
    This week's forecast as of Monday morning.
    Winter Advisory
    With this week's incoming weather, I'd like to offer some advice on how best to prepare and protect your home from its effects. These are simple but important tasks to perform to prevent inconveniences and potential harm that extreme temperatures can bring to homes, including new ones.

    1) Disconnect all exterior hoses from the faucets. Your exterior faucets (called hose bibs) are designed to withstand the elements of harsh weather. However, having a hose connected dramatically increases the potential for water within the hose to freeze and expand into the inner portions of the hose bib, potentially rupturing its supply pipe. Simply disconnecting the hose is the best way to prevent this.

    2) Close that garage door. During nicer weather, it's not unusual for some to be in the habit of leaving the overhead door up for a bit into the evening. However, during extremely colder temperatures, doing so will increase the load on your home's energy performance, causing your HVAC system to have to work harder to keep your home comfortable. You also risk forgetting to close the door overnight, which exposes the plumbing to and from your hot water closet to potential freezing and rupturing.

    3) Test that heat & fireplace. When going into Fall, it's always a good idea to test your heater(s) and fireplace before you actually need them. That way if something isn't working properly it can be addressed before it beomes an urgent need. Run your heater(s) for a few minutes to ensure they are emitting warm air, and don't be alarmed if you smell a hint of a burning smell. This is simply the result of burning off dust on the coils that haven't been hot for a while.

    4) Replace those filters. When your heater can breath better, it heats better. If you haven't changed your air filters at the returns in the past 30 days, you definitely want to do that to help make way for maximum airflow and energy performance (which results in greater comfort.). Remember, don't buy the expensive ones. Get mid-level ones from Lowe's and change them often (every 30 days is the best practice).

    5) Be aware of plumbing on exterior walls. If you have any bathroom sinks or shower/tub faucets that are on exterior walls, there are a couple of techniques you'll want to be aware of when temps are expected to dip into the teens or below. For any bathroom sinks on exterior walls, leave the cabinet doors open that are underneath the sink to provide better warm air to circulate. For both sinks and tubs/showers on exterior walls, it may also be necessary to turn on the faucets to a slow drip during extreme temperatures, as moving water helps prevent freezing.

    6) Turn off your yard's irrigation system if you have one. This is easy to do, and involves two steps: 1) Turn your controller to off. Your controller is mounted on the inside wall of your garage. In most models, this is simply a dial that you turn to the "Off" position. Turning off prevents the controller from telling your solenoid valves to turn on/off unnecessarily. This is known as dry-firing since it's turning the valves on when water isn't present. 2) Turn off the water supply to the system by turning off a valve at your backflow preventer, which is usually inside your hot water tank closet. You have two valves similar to the blue levers shown below, and turning one of them perpendicular to the pipe will turn off the water supply to the system. (Reverse this process in the spring, or any time temperatures get back into the range of needing to water your landscape.)

    A typical bakcflow preventer, located within your hot water closet.


    Accomplishing these simple tasks will go a long way towards making wintery weather more bearable. Don't forget to start the coffee maker! | jC
  • Marked as complete by Jeff  |  Mar 5, 2019 - 6:45am

    Pre-Closing Walk-Through Punch Items Completed

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:35am

    Remaining Pre-Closing Walkthrough Items Assigned In Warranty Phase

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:35am

    Final-Final Clean

  • Marked as complete by Jeff  |  Feb 27, 2019 - 6:35am

    Paint Touch Up Kit Created & Neatly Stored In Utility Room

  • Scheduled by Jeff  |  Feb 21, 2019 - 8:16am

    Final-Final Clean

  • Marked as complete by Jeff  |  Feb 6, 2019 - 3:09pm

    Garage Baseboards, Doors, & Casings Wiped Down Post-Power Wash

  • Marked as complete by Jeff  |  Feb 6, 2019 - 3:09pm

    Surplus Tile Materials Gathered & Stored For Future Use

  • Marked as complete by Jeff  |  Feb 6, 2019 - 3:09pm

    Certificate of Occupancy Issued

  • Marked as complete by Jeff  |  Feb 6, 2019 - 3:09pm

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Jan 28, 2019 - 9:27pm

    Permanent Keys Delivery & Secure Storage

  • Phase Completed!  |  Jan 28, 2019 - 9:27pm

    Paint To Finalled

  • Marked as complete by Jeff  |  Jan 28, 2019 - 9:27pm

    Debris & Materials Removed & Dirt Smoothed On Any Adjacent Property

  • Marked as complete by Jeff  |  Jan 28, 2019 - 9:27pm

    Electrical Final Inspection

  • Marked as complete by Jeff  |  Jan 25, 2019 - 9:50am

    Plumbing Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Misc. Punch Items Needing Addressed

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Paint Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Drywall Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Tech & Media Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Window & Exterior Door Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Glass & Mirror Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Cosmetic Surface Repair Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Laminate Counter Top Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Solid Surface Counter Top Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Masonry Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Flooring Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Electrical Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Cabinetry Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Trim & Hardware Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Surplus Trim Material Pick-Up

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    HVAC Punch List

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:17pm

    Flowerbed Debris & Weed Removal & Mulch Refreshment

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:16pm

    Carpet Installation

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:16pm

    Garage, Drive, & Flatwork Power-Washing

  • Marked as complete by Jeff  |  Jan 24, 2019 - 12:16pm

    Attic Insulation Installation

  • Marked as complete by Jeff  |  Jan 18, 2019 - 10:58pm

    Plumbing Final Inspection

  • Marked as complete by Jeff  |  Jan 18, 2019 - 10:58pm

    HVAC Final Inspection

  • Marked as complete by Jeff  |  Jan 18, 2019 - 10:57pm

    Zoning Final Inspection

  • Marked as complete by Jeff  |  Jan 18, 2019 - 10:57pm

    Building Final Inspection

  • Marked as complete by Jeff  |  Jan 18, 2019 - 10:57pm

    Punch Lists Entered in CB & Transmitted To Respective Contractors

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:33pm

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:33pm

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:32pm

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:31pm

    Pre-closing Walk & Client Orientation

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Carpet Installation

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    HVAC Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Plumbing Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Electrical Final Inspection Requested & JCH-Confirmed

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Zoning Final Inspection Requested

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Building Final Inspection Requested

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Final Site Debris Clean-Up

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Kitchen Vent Hood Installation

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Air Conditioning System Charged & JCH Verified

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Window Screen Installation

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Address Panel Installed

  • Phase Completed!  |  Jan 17, 2019 - 5:30pm

    Exterior Detail

  • Marked as complete by Jeff  |  Jan 17, 2019 - 5:30pm

    Exterior Door Weather Stripping & Threshold Adjustment

  • Scheduled by Jeff  |  Jan 14, 2019 - 9:14am

    Carpet Installation

  • Marked as complete by Jeff  |  Jan 14, 2019 - 9:12am

    Blank-Plating of Media Wiring JCH-Verified

  • Marked as complete by Jeff  |  Jan 14, 2019 - 9:12am

    Water Meter Adjustment (or N/A)

  • Marked as complete by Jeff  |  Jan 14, 2019 - 9:12am

    Sewer Clean-Out Cut-Down & Capping

  • Marked as complete by Jeff  |  Jan 14, 2019 - 9:12am

    Exterior Door Painting

  • Marked as complete by Jeff  |  Jan 14, 2019 - 9:12am

    Exterior Facade Expansion Joint Sealing

  • Marked as complete by Jeff  |  Jan 13, 2019 - 1:46pm

    Cabinet Final & Adjustments

  • Marked as complete by Jeff  |  Jan 13, 2019 - 1:45pm

    Heat, Ventilation, & Air Conditioning Final Installation

  • Marked as complete by Jeff  |  Jan 10, 2019 - 6:59am

    Garage Door Opener Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 3:57pm

    Glass & Mirror Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 3:28pm

    Security, Media, & Tech Final

  • Marked as complete by Jeff  |  Jan 9, 2019 - 1:29pm

    Carpet Installation Scheduled

  • Marked as complete by Jeff  |  Jan 9, 2019 - 1:27pm

    Natural Gas Connections Completed & JCH-Verified

  • Marked as complete by Jeff  |  Jan 9, 2019 - 1:27pm

    Plumbing Final Installation

  • Marked as complete by Jeff  |  Jan 9, 2019 - 1:25pm

    Sod Installation

  • Scheduled by Jeff  |  Jan 7, 2019 - 12:02pm

    Preliminary Detail Clean

  • Marked as complete by Jeff  |  Jan 7, 2019 - 12:01pm

    Adjacent Lot Dirt & Debris Removed

  • Marked as complete by Jeff  |  Jan 7, 2019 - 12:01pm

    Yard Debris & Flag Removal

  • Marked as complete by Jeff  |  Jan 7, 2019 - 12:00pm

    Barn Door(s) Installation

  • Marked as complete by Jeff  |  Jan 7, 2019 - 11:59am

    Electrical & Lighting Final Installation

  • Marked as complete by Jeff  |  Jan 7, 2019 - 11:59am

    Appliance Package Delivery

  • Marked as complete by Jeff  |  Jan 7, 2019 - 11:59am

    Lighting Fixture Package Delivery

  • Marked as complete by Jeff  |  Jan 7, 2019 - 11:59am

    Backsplash & Remaining Wall Tile Installation

  • Marked as complete by Jeff  |  Jan 7, 2019 - 11:59am

    Laminate Counter Top Installation

  • Marked as complete by Jeff  |  Jan 3, 2019 - 11:36am

    Hardware Installation

  • Scheduled by Jeff  |  Jan 2, 2019 - 9:56pm

    Garage Door Opener Installation

  • Scheduled by Jeff  |  Jan 2, 2019 - 9:55pm

    Glass & Mirror Installation

  • Scheduled by Jeff  |  Jan 2, 2019 - 9:54pm

    Cabinet Final & Adjustments

  • Scheduled by Jeff  |  Jan 2, 2019 - 9:52pm

    Attic Insulation Installation

  • Scheduled by Jeff  |  Jan 2, 2019 - 9:51pm

    Window Screen Installation

  • Marked as complete by Jeff  |  Jan 2, 2019 - 9:48pm

    Window & Door Lintels Painted

  • Marked as complete by Jeff  |  Jan 2, 2019 - 9:48pm

    Landscape Bed Installation

  • Marked as complete by Jeff  |  Jan 2, 2019 - 9:43pm

    Solid Surface Counter Top Installation

  • Scheduled by Jeff  |  Dec 21, 2018 - 8:36am

    Lighting Fixture Package Delivery

  • Scheduled by Jeff  |  Dec 21, 2018 - 8:35am

    Appliance Package Delivery

  • Scheduled by Jeff  |  Dec 21, 2018 - 8:34am

    Plumbing Final Installation

  • Scheduled by Jeff  |  Dec 21, 2018 - 8:33am

    Security, Media, & Tech Final

  • Scheduled by Jeff  |  Dec 21, 2018 - 8:32am

    Electrical & Lighting Final Installation

  • Scheduled by Jeff  |  Dec 21, 2018 - 8:32am

    Backsplash & Remaining Wall Tile Installation

  • Scheduled by Jeff  |  Dec 21, 2018 - 8:31am

    Solid Surface Counter Top Installation

  • Marked as complete by Jeff  |  Dec 21, 2018 - 8:30am

    Cabs Pre-Drilled for Hardware

  • Marked as complete by Jeff  |  Dec 21, 2018 - 8:30am

    Mirror & Glass Templated

  • Marked as complete by Jeff  |  Dec 19, 2018 - 7:25pm

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Dec 19, 2018 - 7:25pm

    Exterior Cornice & Trim Painting

  • Marked as complete by Jeff  |  Dec 19, 2018 - 10:14am

    Laminate Counter Top Templating

  • Marked as complete by Jeff  |  Dec 19, 2018 - 10:14am

    Solid Surface Counter Top Templating

  • Scheduled by Jeff  |  Dec 17, 2018 - 1:19pm

    Seamless Guttering Installation

  • Marked as complete by Jeff  |  Dec 17, 2018 - 1:18pm

    Specialty Outdoor Feature Installation (or N/A)

  • Marked as complete by Jeff  |  Dec 17, 2018 - 1:18pm

    Sandy Loam Load Delivery

  • Scheduled by Jeff  |  Dec 17, 2018 - 1:18pm

    Laminate Counter Top Templating

  • Scheduled by Jeff  |  Dec 17, 2018 - 1:17pm

    Solid Surface Counter Top Templating

  • Scheduled by Jeff  |  Dec 17, 2018 - 1:16pm

    Mirror & Glass Templated

  • Scheduled by Jeff  |  Dec 17, 2018 - 1:16pm

    Barn Door Installation Scheduled

  • Marked as complete by Jeff  |  Dec 17, 2018 - 1:15pm

    Interior Stain & Painting

  • Marked as complete by Jeff  |  Dec 17, 2018 - 1:15pm

    Trim Sweep & Haul Complete

  • Marked as complete by Jeff  |  Dec 17, 2018 - 1:15pm

    Trim Back-Out & Detail

  • Marked as complete by Jeff  |  Dec 17, 2018 - 1:15pm

    Trim Sweep & Haul Scheduled

  • Phase Completed!  |  Dec 17, 2018 - 1:15pm

    Insulation To Trim

  • Marked as complete by Jeff  |  Dec 17, 2018 - 1:15pm

    Barn Door Installation Scheduled

  • Marked as complete by Jeff  |  Dec 5, 2018 - 9:41pm

    Final Site Grade

  • Marked as complete by Jeff  |  Dec 5, 2018 - 9:41pm

    Exterior Wood Column Installation

  • Marked as complete by Jeff  |  Nov 26, 2018 - 3:20pm

    Curb & Form Haul

  • Marked as complete by Jeff  |  Nov 26, 2018 - 3:20pm

    Flatwork Form Removal

  • Marked as complete by Jeff  |  Nov 26, 2018 - 3:20pm

    ROWS Inspection Passed & JCH Verified

  • Marked as complete by Jeff  |  Nov 26, 2018 - 3:20pm

    ROWS Inspection Requested & JCH-Verified

  • Marked as complete by Jeff  |  Nov 26, 2018 - 3:20pm

    Flatwork Relief Cuts & Caulking

  • Marked as complete by Jeff  |  Nov 26, 2018 - 3:20pm

    Flatwork Pour

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:45am

    Builder Trim, Paint, & Detail Walk-Through

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:24am

    Driveway Approach & CIty-Walk Inspection

  • Marked as complete by Jeff  |  Nov 19, 2018 - 11:24am

    Trim Carpenter On Site - Door & Backout

  • Marked as complete by Jeff  |  Nov 15, 2018 - 5:24pm

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:57pm

    Cabinet Delivery & Installation

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:57pm

    Interior Trim & Doors On Site

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:57pm

    Concrete Flooring Work Complete

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:57pm

    Preliminary Wall Tile Completion

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:57pm

    Preliminary Flooring Completion

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:57pm

    Post Drywall Floor-Cleaning Completion

  • Marked as complete by Jeff  |  Nov 6, 2018 - 1:57pm

    Drywall Tape, Bed, & Texture Completion

  • Marked as complete by Jeff  |  Nov 1, 2018 - 8:38am

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Nov 1, 2018 - 8:38am

    Flatwork Form Setup

  • Marked as complete by Jeff  |  Nov 1, 2018 - 8:37am

    Wall Tile Details Notated On Walls

  • Marked as complete by Jeff  |  Oct 30, 2018 - 11:59am

    Temporary Construction Heat Activated

  • Scheduled by Jeff  |  Oct 30, 2018 - 11:59am

    Cabinet Delivery & Installation

  • Scheduled by Jeff  |  Oct 30, 2018 - 11:46am

    Interior Trim & Doors On Site

  • Scheduled by Jeff  |  Oct 29, 2018 - 2:58pm

    Final Site Grade

  • Scheduled by Jeff  |  Oct 29, 2018 - 2:54pm

    Flatwork Sand On Site

  • Marked as complete by Jeff  |  Oct 29, 2018 - 2:54pm

    Flatwork Sand Ordered

  • Phase Completed!  |  Oct 29, 2018 - 2:53pm

    Exterior Rough

  • Marked as complete by Jeff  |  Oct 29, 2018 - 2:52pm

    Hardscape Design Notes Complete & Posted to CB

  • Scheduled by Jeff  |  Oct 29, 2018 - 9:06am

    Flatwork Form Setup

  • Scheduled by Jeff  |  Oct 29, 2018 - 9:04am

    Temporary Construction Heat Activated

  • Scheduled by Jeff  |  Oct 29, 2018 - 8:59am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:58am

    Temporary Exterior Door Hardware Installation

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:58am

    Interior Trim & Door Delivery Scheduled

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:57am

    Natural Gas Meter Installation Scheduled

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:57am

    Phase 2 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:57am

    Natural Gas Line Installed

  • Marked as complete by Jeff  |  Oct 29, 2018 - 8:57am

    Framing | Accent Panelling Installation

  • Phase Completed!  |  Oct 29, 2018 - 8:57am

    Frame To Inspections

  • Marked as complete by Jeff  |  Oct 24, 2018 - 11:34am

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Oct 23, 2018 - 2:59pm

    Attic Access Installation Completion

  • Marked as complete by Jeff  |  Oct 23, 2018 - 2:58pm

    Garage Door Installation

  • Marked as complete by Jeff  |  Oct 23, 2018 - 2:58pm

    Sheetrock Installation Completion

  • Scheduled by Jeff  |  Oct 22, 2018 - 1:31pm

    Concrete Flooring Work Complete

  • Scheduled by Jeff  |  Oct 22, 2018 - 1:30pm

    Preliminary Flooring Completion

  • Scheduled by Jeff  |  Oct 22, 2018 - 1:30pm

    Drywall Phase Site Clean-Up

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:29pm

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:29pm

    Drywall Phase Site Clean-Up Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:28pm

    Post Drywall Floor-Cleaning Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:28pm

    Drywall Material On Site

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:28pm

    Preliminary Stained Concrete Flooring Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:28pm

    Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:28pm

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:28pm

    Insulation Inspection Requested

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:28pm

    Water Meter Installed & Back-filled

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:27pm

    Post-Masonry Roof Flashing & Metal Capping Completion (Or N/A)

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:26pm

    Electrical Final Meter & Service Installed

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:26pm

    Masonry Site-Haul Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:26pm

    Wall Insulation & Seal Package Completion

  • Marked as complete by Jeff  |  Oct 22, 2018 - 1:26pm

    Insulation Inspection Passed

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:36am

    Concrete Flooring Work Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:36am

    Hardscape/Flatwork Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:36am

    Acid Wash of Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:36am

    Mailbox Constructed (If Feasible)

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:36am

    Exterior Brick Masonry Completion

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:36am

    Phase 2 Design Session Completed

  • Marked as complete by Jeff  |  Oct 16, 2018 - 8:36am

    Insulation Inspection Requested & Confirmed by Jeff

  • Marked as complete by Jeff  |  Oct 15, 2018 - 1:32pm

    Phase 2 Design Session Scheduled

  • Marked as complete by Jeff  |  Oct 15, 2018 - 1:31pm

    Framer Punch-List Completion

  • Marked as complete by Jeff  |  Oct 15, 2018 - 1:31pm

    Building Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Oct 12, 2018 - 3:57pm

    Tile & Hardwood Flooring Take-Off & Ordered

  • Marked as complete by Jeff  |  Oct 12, 2018 - 3:57pm

    Preliminary Floor &/or Wall Tile Scheduled

  • Scheduled by Jeff  |  Oct 12, 2018 - 3:56pm

    Preliminary Wall Tile Completion

  • Scheduled by Jeff  |  Oct 12, 2018 - 12:09pm

    Attic Access Installation Completion

  • Scheduled by Jeff  |  Oct 12, 2018 - 12:09pm

    Garage Door Installation

  • Marked as complete by Jeff  |  Oct 12, 2018 - 12:09pm

    Garage Door Installation Scheduled

  • Marked as complete by Jeff  |  Oct 12, 2018 - 12:09pm

    Attic Access Installation Scheduled

  • Marked as complete by Jeff  |  Oct 12, 2018 - 12:08pm

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 12, 2018 - 12:08pm

    Drywall Material Ordered

  • Marked as complete by Jeff  |  Oct 12, 2018 - 12:08pm

    Sheetrock & Materials Order Scheduled For Delivery

  • Scheduled by Jeff  |  Oct 12, 2018 - 11:55am

    Drywall Material On Site

  • Marked as complete by Jeff  |  Oct 12, 2018 - 11:54am

    Drywall Contractor Scheduled

  • Marked as complete by Jeff  |  Oct 12, 2018 - 11:54am

    Drywall Material Ordered

  • Scheduled by Jeff  |  Oct 12, 2018 - 11:51am

    Wall Insulation & Seal Package Completion

  • Marked as complete by Jeff  |  Oct 12, 2018 - 11:50am

    Natural Gas Line Installation Scheduled

  • Marked as complete by Jeff  |  Oct 11, 2018 - 1:03pm

    Electrical Final Meter & Service Installation Scheduled

  • Marked as complete by Jeff  |  Oct 11, 2018 - 1:03pm

    Masonry Site-Haul Scheduled

  • Marked as complete by Jeff  |  Oct 10, 2018 - 9:15pm

    Building Rough-In Inspection Requested

  • Marked as complete by Jeff  |  Oct 10, 2018 - 9:15pm

    Electric Meter Installation Scheduled

  • Marked as complete by Jeff  |  Oct 10, 2018 - 9:15pm

    Electrical Rough-In Inspection Passed

  • Scheduled by Jeff  |  Oct 4, 2018 - 8:17am

    Final Exterior Door Installed

  • Marked as complete by Jeff  |  Oct 4, 2018 - 8:15am

    Supplemental Masonry Material On Site

  • Marked as complete by Jeff  |  Oct 4, 2018 - 8:15am

    Masonry Sand On Site

  • Marked as complete by Jeff  |  Oct 4, 2018 - 8:14am

    Final Exterior Door Ordered

  • Marked as complete by Jeff  |  Oct 4, 2018 - 8:14am

    Temporary Exterior Door Installation

  • Marked as complete by Jeff  |  Sep 28, 2018 - 11:24am

    Surplus Lumber Pickup

  • Marked as complete by Jeff  |  Sep 28, 2018 - 11:24am

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Sep 27, 2018 - 4:32pm

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Sep 27, 2018 - 4:31pm

    Cabinet Delivery & Installation Scheduled

  • Marked as complete by Jeff  |  Sep 27, 2018 - 4:29pm

    Electrical Rough-In Inspection Requested & JCH Verified

  • Marked as complete by Jeff  |  Sep 27, 2018 - 4:29pm

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Sep 27, 2018 - 4:26pm

    Plumbing Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 27, 2018 - 4:26pm

    HVAC Rough-In Inspection Passed

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:13am

    Plumbing Rough Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:13am

    HVAC Rough-In Inspection Contractor-Requested & JCH-Verified

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:13am

    Super's On-Site Rough-In & Frame Review With Builder

  • Marked as complete by Jeff  |  Sep 26, 2018 - 9:13am

    Builder's Framing & Rough-In Review & Notation

  • Marked as complete by Jeff  |  Sep 20, 2018 - 11:05am

    Window & Exterior Door Installation Completion

  • Marked as complete by Jeff  |  Sep 20, 2018 - 11:04am

    Brick On Site

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:16am

    Masonry Sand Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:16am

    Supplemental Masonry Material Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:16am

    Drywall Take-off Requested

  • Scheduled by Jeff  |  Sep 14, 2018 - 9:15am

    Tech & Security Rough-In Completion

  • Scheduled by Jeff  |  Sep 14, 2018 - 9:13am

    Brick On Site

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:12am

    Exterior Masonry Scheduled

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:12am

    Trim & Interior Door Material Take-Off & Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:12am

    Silt-Fencing & Storm-Water Run-Off Protection Verified

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:12am

    Exterior Facade Materials Ordered

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:11am

    HVAC Rough-In Completion

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:11am

    Drywall Take-off Requested

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:11am

    Cabinet Take-Off & Design Review

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:11am

    Exterior Moisture Barrier Inspection Requested (Or N/A)

  • Marked as complete by Jeff  |  Sep 14, 2018 - 9:11am

    Roof Installation

  • Marked as complete by Jeff  |  Sep 13, 2018 - 11:35am

    Frame Debris Site-Haul & Interior Sweep Completion

  • Scheduled by Jeff  |  Sep 11, 2018 - 5:44pm

    Frame Debris Site-Haul & Interior Sweep Completion

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:43pm

    Frame Debris Site-Haul & Interior Sweep Scheduled

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:43pm

    Exterior Moisture Barrier Inspection Passed

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:43pm

    Exterior Wall Sheathing Inspection Passed

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:43pm

    Exterior Wall Sheathing Inspection Requested

  • Marked as complete by Jeff  |  Sep 11, 2018 - 5:43pm

    Lighting Selections Scheduled

  • Marked as complete by Jeff  |  Sep 10, 2018 - 9:42am

    Plumbing Rough-In Completion

  • Marked as complete by Jeff  |  Sep 10, 2018 - 9:38am

    Framing - Cornice & Detail Phase Completion

  • Marked as complete by Jeff  |  Sep 10, 2018 - 9:38am

    Framing - Rafter & Decking Phase Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:55am

    Window & Exterior Door Installation Scheduled

  • Scheduled by Jeff  |  Aug 30, 2018 - 9:55am

    Roof Installation

  • Scheduled by Jeff  |  Aug 30, 2018 - 9:55am

    Window & Exterior Door Installation Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 9:53am

    HVAC Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 9:53am

    Plumbing Rough-In Completion

  • Scheduled by Jeff  |  Aug 30, 2018 - 9:52am

    Electrical Rough-In Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Tech & Security Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Electrical Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Plumbing Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    HVAC Rough-In Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Roofing Material & Labor Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Window & Exterior Door Installation Scheduled

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Framing - Joist Phase Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Framing - Wall & Sheathing Phase Completion

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Preliminary Wall Layout / Frame Started

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Framing Lumber - Decking & Cornice Order

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Framing Lumber - Joist & Rafter Order

  • Marked as complete by Jeff  |  Aug 30, 2018 - 9:51am

    Post-Design Session Pricing Audit

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Framing Lumber - Wall Pack Order

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Phase 2 Design Session Scheduled

  • Phase Completed!  |  Aug 27, 2018 - 9:28am

    Pad To Foundation

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Phase 1 Design Session Notes Reviewed & Posted to Clickbuild

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Phase 1 Design Session Completed

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    2nd Part Permit Obtained (Or N/A)

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Framing Wall-Pack Delivery Scheduled

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Windows & Exterior Doors Ordered

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Future Storm Shelter Location Poured/Not Poured Per Specifications

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Foundation Form Removal

  • Marked as complete by Jeff  |  Aug 27, 2018 - 9:28am

    Foundation Poured

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:56am

    Dropped Shower Floor(s) Formed & Verified

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:56am

    Future Storm Shelter Location Formed & Verified

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    3rd Party Engineering Inspection

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Ground Electrical Installed

  • Marked as complete by Jeff  |  Aug 16, 2018 - 11:55am

    Post-Tension Foundation Cables Set

  • Marked as complete by Jeff  |  Aug 1, 2018 - 2:53pm

    Closing of Lot & Construction Financing Secured

  • Phase Completed!  |  Aug 1, 2018 - 2:53pm

    Start To Permit

  • Marked as complete by Jeff  |  Jul 31, 2018 - 10:56am

    Framing Plans Distributed to Framing Contractor

  • Marked as complete by Jeff  |  Jul 31, 2018 - 10:53am

    Sewer Installed, Tapped, & Back-filled

  • Marked as complete by Jeff  |  Jul 31, 2018 - 10:53am

    Ground Plumbing Inspection Passed

  • Marked as complete by Jeff  |  Jul 31, 2018 - 10:53am

    Ground Plumbing Installed

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Foundation Forms Constructed

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Trash Bin Constructed

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Porta-Potty Delivered

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Foundation Plans Distributed To Plumbing & Foundation Contractors

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Site Identification Sign Installed

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Purchase Agreement Signed by Builder

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Purchase Agreement Signed by Client

  • Marked as complete by Jeff  |  Jul 16, 2018 - 10:13am

    Purchase Agreement Pricing Completed

  • Marked as complete by Jeff  |  May 7, 2018 - 11:36am

    Pad Site Grading

  • Marked as complete by Jeff  |  Apr 15, 2018 - 9:04am

    Phase 1 Design Session Scheduled

  • Marked as complete by Jeff  |  Apr 15, 2018 - 9:04am

    Issuance Of Building Permit

  • Marked as complete by Jeff  |  Apr 15, 2018 - 9:04am

    Site Drainage Analysis & Plan

  • Marked as complete by Jeff  |  Apr 15, 2018 - 9:04am

    Final Design Notes Created

  • Marked as complete by Jeff  |  Apr 15, 2018 - 9:04am

    Window Take-Off & Bid Received

  • Marked as complete by Jeff  |  Apr 15, 2018 - 9:04am

    Window Take-Off & Bid Requested

  • Marked as complete by Jeff  |  Apr 15, 2018 - 9:04am

    Framing Engineering & Material Take-Off Received

  • Marked as complete by Jeff  |  Apr 9, 2018 - 8:06am

    Temp Electric Pole Installed

  • Marked as complete by Jeff  |  Apr 9, 2018 - 8:06am

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Apr 5, 2018 - 12:33pm

    Trash Bin Materials Ordered

  • Posted by Jeff Click  |  Apr 5, 2018 - 12:33pm
    It's about to become official.
    The application for permit, along with printed plans, have been submitted to the governing municipality for review. This usually takes between a few days to a week. Once approved, we are ready for construction on site! While the review is taking place, I am getting your project "in the queue" with my contractors and suppliers to ensure that everything is in order once the permit has been approved.

    Stand by for some fun visual progress on site in the coming days!

    -JC
  • Marked as complete by Jeff  |  Apr 5, 2018 - 12:33pm

    Plans & Application Submitted for Permits

  • Marked as complete by Jeff  |  Apr 5, 2018 - 12:33pm

    Foundation Engineering JCH-Verified

  • Marked as complete by Jeff  |  Apr 5, 2018 - 12:33pm

    Foundation Engineering Printed & Ready For Distribution

  • Marked as complete by Jeff  |  Apr 5, 2018 - 12:32pm

    Award Of Project To Trades & Contractors

  • Marked as complete by Jeff  |  Apr 5, 2018 - 12:32pm

    Lot Closing Scheduled

  • Marked as complete by Jeff  |  Apr 5, 2018 - 12:32pm

    Construction Financing Budget Submitted to Bank

  • Scheduled by Jeff  |  Apr 5, 2018 - 11:58am

    Temp Electric Pole Installed

  • Scheduled by Jeff  |  Apr 5, 2018 - 11:56am

    Property Pins Located On Site

  • Marked as complete by Jeff  |  Mar 9, 2018 - 1:49pm

    Foundation Engineering Complete

  • Scheduled by Jeff  |  Mar 5, 2018 - 10:33am

    Foundation Engineering Complete

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:31am

    Permit-Ready Plans Printed For Permitting

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:30am

    Framing Engineering Ordered

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:30am

    Foundation Engineering Ordered

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:30am

    Final Project Data Updated in CB

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:22am

    Final Plan Revisions JCH-Verified

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:22am

    Final Plan Revisions Received

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:22am

    Pricing Updated From Pre-Con

  • Marked as complete by Jeff  |  Mar 5, 2018 - 10:22am

    Draft of Plans Sent To Bank for Pre-Appraisal (or N/A)

  • Marked as complete by Jeff  |  Feb 27, 2018 - 3:38pm

    Final Plan Revisions Submitted To Draftsman

  • Marked as complete by Jeff  |  Feb 27, 2018 - 3:38pm

    Final Pre-Con Redline Notes

  • Marked as complete by Jeff  |  Feb 27, 2018 - 3:38pm

    Pre-Con Plan Review with Client

  • Marked as complete by Jeff  |  Feb 27, 2018 - 3:38pm

    Jeff's Plan Review & Pre-Con Comments

  • Marked as complete by Jeff  |  Jan 29, 2018 - 11:29am

    Pre-con Meeting Packet Created

  • Marked as complete by Jeff  |  Jan 29, 2018 - 11:29am

    Client Pre-Con Scheduled

  • Marked as complete by Jeff  |  Jan 29, 2018 - 11:29am

    Initial Draft of Plans Received

  • Marked as complete by Jeff  |  Jan 29, 2018 - 11:29am

    Plan Redline Submitted To Draftsman

  • Marked as complete by Jeff  |  Invalid date - Invalid date

    Plumbing Final Inspection